3/10/2016 - Change Order #8 Benn's Church Intersection Improvement •
Howard Brothers Contractor, Inc. Change Order
P.O.Box 96
lt Providence Forge VA 23140 Order#: 8
804-966-2762
Order Date: 03/10/2016
License: 2701 039212A
To: County of Isle of Wight Project: 1063
P. O. Box 80 #15-4110-21 Benns Church
Isle of Wight VA 23397 UPC#98244
VDOT#0010-046-RI0,C501
The contractor agrees to perform and the owner agrees to Plans Attached n
pay for the following changes to this contract.
Ordered By: Customer Order: Specifications Attached E
Description of Work Amount
Master Traffic Signal Controller 7,977.09
Notes
HBCI's subcontractor(Dagan Electric)to furnish and install (1)Master Controller as determined by
RFI#17 and submitted by proposal.
Line Item to be added to contract.
Negative changes will lower the overall contract
price requiring no additional payment by owner. Requested Amount of Change 7,977.09
The original Contract Sum was 4,225,263.55
Net change by previous Change Orders .- 152,683.24
The Contract Sum prior to this Change Order ._ 4,377,946.79
The Contract Sum will be changed by this Change Order 7,977.09
The new Contract Sum including this Change Order will be .._ 4,385,923.88
The Contract Time will be changed by 0 Days
Owner:
Contractor: � ary
auza.�C Yy�� Date: _ 03/ 0/2016