Morgarts Beach Road Project c
Kimley>>)Horn
March 4, 2016
Jamie Oliver
Project Manager, Engineering Division
Isle of Wight County
13048 Poor House Road
Isle of Wight County, VA 23397
RE: Mogarts Beach Road(East) Rural Rustic Road Project
Scope and Fee
Dear Ms Oliver,
Kimley-Horn and Associates, Inc. ("Kimley-Horn" or "the Consultant") is pleased to submit this
Agreement (the "Agreement") to Isle of Wight County ("the Client" or the County"), to provide
engineering services for the design and construction of roadway improvements along Mogarts Beach
Road (East). This work will be performed under the Professional Services On-Call agreement (dated
April 23, 2014) between Isle of.Wight County and Kimley-Horn. Below is our understanding of the
project and our anticipated scope of work.
Project Understanding
This project consists of the design of roadway improvements to Mogarts Beach Road (East), a local
road within the County. Roadway improvements shall be in accordance with the Virginia Department
of Transportation Rural Rustic Road Program, which provides a practical approach to paving low
volume unpaved roads within the Commonwealth. The limits of proposed improvements extend from
State Route 674 (Blounts Corner Road) to State Route 705 (Fort Boykin Trail). The project is
approximately 1.05 miles long.
Roadway improvements will consist of paving existing gravel roads with no planned widening or
shoulder restoration and minimal drainage improvements to include minor grading and/or maintaining
existing ditches. Improvements will not include adjustments to the horizontal or vertical alignment of the
existing road and no additional Right-of-Way will be required.
Through conversations with Isle of Wight County, Kimley-Horn understands that this project meets the
eligibility requirements for the Rural Rustic Road Program and have been approved by VDOT and the
County's Board of Supervisors.
Scope of Services
Kimley-Horn will provide professional services to develop a"No Plan"set of construction documents in
accordance with Section A-7 "No Plan" Projects in the VDOT Road Design Manual and IIM-LD-245
Rural Rustic Road Projects. Documents will consist of minimal essential information and notes
necessary to govern construction.
kimley-horn:corn 4500 Main Street, Suite 500,Virginia Beach,VA 23462 757 213 8600
Kinky) Horn Page 2
Outlined below are the necessary tasks required to create construction documents for approval by
VDOT:
Task 1 - Field Visit and Data Collection
Kimley-Horn will perform a site visit to observe existing conditions, roadway dimensions, drainage
patterns and any potential conflicts. This site visit will include confirming conditions previously
documented in the field and documenting any changed conditions. It is anticipated that the field work
will occur within a single day. No topographic survey will be required for work on this project.
Task 2 - "No Plan" First Submittal
Kimley-Horn will prepare a set of"No Plan"construction documents with minimal essential information
as described in the VDOT Road Design Manual. Kimley-Horn will coordinate with VDOT throughout the
design and review process. Coordination efforts will consist of providing the environmental documents
as outlined in Task 4, proposed pavement section coordination with the geotechnical engineer and
VDOT Pavement Division, and bid phase and construction phase services. The "No Plans" package
will consist of the following:
• Title Sheet • Field Narrative
• Project Location Map • Details
• Typical Sections • Quantity Summary Tables
• General Notes • Cost Estimate
• Erosion and Sediment Control Plan • Specifications
and Narrative
A First Submittal will be made to the County for review and comment. Upon approval from the County,
Kimley-Horn will provide a copy of the First Submittal to VDOT for review and comment. Kimley-Horn
will provide both hard copies and an electronic version of the document to the County and VDOT for
review.
Kimley-Horn will attend up to one scoping meeting to discuss the projects with the County and VDOT
representatives. Kimley-Horn will attend up to one review meeting with Isle of Wight County and VDOT
representatives to discuss the First Submittal.
Prior to finalizing the"No Plan" construction documents, Kimley-Horn shall coordinate a field meeting
with VDOT, VDOT Maintenance Division, and Isle of Wight County to discuss the proposed design at
each project location and coordinate efforts between the proposed design and maintenance plans on
each roadway.
kimley-horn.com 4500 Main Street, Suite 500,Virginia Beach, VA 23462 757 213 8600
pn
Kim ey>>>Horn Page 3
Task 3 - "No Plan" Final Submittal
Upon review and reconciliation of comments from the County and VDOT review of First Submittal,
Kimley-Horn will proceed with the Final Submittal. This task will consist of incorporating appropriate
review comments into the following package:
• Title Sheets • Field Narrative
• Project Location Map • Details
• Typical Sections • Quantity Summary Tables
• General Notes • Cost Estimate
• Erosion and Sediment Control Plan • Specifications
and Narrative
A Final Submittal will be made to the County and VDOT for review and approval. Kimley-Horn will
provide two (2) sets of documents each to the County and VDOT for review. Both hard copies and
electronic copies will be provided.
Task 4— Environmental Compliance
As a result of state funding being applied to this project, this project must comply with the State
Environmental Review Process (SERP). This scope assumes the total project cost will not exceed
$500,000 and therefore it is anticipated that this project will be exempt from the preparation of a
Preliminary Environmental Inventory(PEI). The completion of the Project Early Notification Form (EQ-
429)is still required. In general accordance with Part 3,Chapter 15 of the Locally Administered Projects
(LAP) Manual, Kimley-Horn will complete the Project Early Notification Form (EQ-429) which will
consist of information relating to the proposed project and a topographic map depicting the project
limits.
The County is still responsible for'obtaining any environmental clearances necessary to satisfy
state/federal regulatory requirements. Therefore, Kimley-Horn will conduct the following:
• Site visit — Kimley-Horn will conduct a field review of the project corridor from public
thoroughfares. The purpose of the site visit will be to document the current land use and
photograph structures greater than 50 years old, if any.
• Historic Resources Review — Kimley-Horn will search the Virginia Department of Historic
Resources (VDHR) archives using the Virginia Cultural Resource Information System (V-
CRIS) database, prepare photo documentation of structures appearing to be greater than 50
years old located on properties adjacent to the proposed improvements, and submit the
project for review to VDHR. Given the nature of the proposed project, it is anticipated that a
finding of "no effect" or "no adverse effect" will be determined. Additional coordination is
excluded from the scope herein.
• Threatened and Endangered Species Coordination-Kimley-Horn will solicit comments from
the Department of Game and Inland Fisheries (DGIF), Department of Conservation and
Recreation (DCR), and US Fish and Wildlife Service (USFWS) regarding listed state or
kirnley-horn.corn 4500 Main Street, Suite 500,Virginia Beach,VA 23462 757 213 8600
•
rn
Kim ey>>>Horn Page 4
federal threatened or endangered species which have been reported within the project area.
Technical studies or additional coordination is excluded from the scope herein.
• Wetlands Review — Kimley-Horn will conduct a delineation of wetlands and waters within
existing VDOT right-of-way along the project corridors. The wetlands and WOUS boundaries
will be flagged and numbered for inspection by the COE. The flags will be located using
Global Positioning System (GPS) and plotted on a base map of the site. Kimley-Horn will
prepare an exhibit and letter memo summarizing the approximate location, size, and type of
wetlands and WOUS on the project site. Kimley-Horn will then schedule a field confirmation
with the COE to review and approve the flagged wetland boundaries. Kimley-Horn will
accompany the COE on up to one wetland delineation confirmation site visit.
• Hazardous Materials Review—Kimley-Horn will conduct a preliminary review of the proposed
project area to assess the potential to encounter hazardous materials or petroleum-impacted
soil during the construction of the proposed project. The preliminary review will consist of a
field review of the project area from public thoroughfares and a review of major state and
federal environmental databases. As the project does not include the acquisition of additional
right-of-way, this assessment will not be to the level of an ASTM Standard E1527-05 Phase
I Environmental Site Assessment and will not include a review of the Department of
Environmental Quality files, interviews or review of historical aerial photographs and
topographic maps.
• Kimley-Horn will complete the EQ-555 (Water Quality Permits and Natural Resources Form)
and EQ-121 (Hazardous Material Form) for submittal to VDOT utilizing the above T&E
species clearances and wetland and waters delineation.
It is assumed that there will be no impact to historic resources and threatened and endangered species.
Therefore, additional coordination with these agencies beyond the scoping letters is not included
herein. Kimley-Horn will prepare a brief memorandum documenting the site conditions of the proposed
project area, a summary of findings based on the above investigations, and recommendations for
additional studies, if any.
Task 5 - Hydraulic Review Requirements
Based on the VDOT Road Design Manual and Instructional and Informational Memoranda (IIM),
minimal hydraulic reviews are required for this project. A detailed hydraulic review will only be
performed when existing ditches have been determined to not function appropriately to meet hydraulic
requirements. Detailed analyses are not included in this scope of work and if identified during the initial
field work will be identified and performed as additional services.
Task 6 - Public Involvement
It is Kimley-Horn's understanding that this roadway improvement project has been presented to the
public through the public hearing process and no further public involvement is required. Therefore, no
public involvement is included in this scope of work. In a previous meeting with the County, the
County suggested the adjacent property owners within the project limits be informed of construction
activities directly before they begin. This communication will be handled by either the County or the
Contractor once the construction phase of the project has begun.
kirnley-1 orn.com 4500 Main Street, Suite 500, Virginia Beach, VA 23462 757 213 8600
Kimley> Horn Page 5
Task 7— Pavement Section Coordination
Kimley-Horn will procure a geotechnical engineer to provide professional services for determining
existing stone depths along the project. The geotechnical engineer will perform hang auger borings
every 500'along each project, alternating from left outside edge of travel location, centerline location,
to right outside edge of travel location and provide a report of findings to Kimley-Horn and the County.
Kimley-Horn will review the report and coordinate with VDOT, including a field meeting, to discuss
any potential reductions to the standard pavement section recommendation from VDOT.
Task 8 — Bid Phase Services
Kimley-Horn will oversee the reprographics and distribution of the bid packages consisting of the plans
and specifications notebook and maintain a list of known plan holders. Kimley-Horn will attend and
conduct the Pre-Bid Meeting to be held at the County office and answer questions from Contractor's
both during the Pre-Bid meeting and throughout the bidding process.
The County will attend and conduct the Bid Opening and compile the bid packages from all bidders and
review the packages for procurement related conformance. The County will forward the bid packages
to Kimley-Horn for tabulation and review. Kimley-Horn will tabulate the bids, comment on any errors
or inconsistencies, and provide an opinion on the contract award to the County.
Task 9— Construction Phase Services
Pre-Construction Meeting-Kimley-Horn will attend and conduct a Pre-Construction Meeting to be
held at the County General Services building.
Shop Drawings and Samples-During construction, Kimley-Horn will review and approve or take other
appropriate action in respect to Shop Drawings and Samples and other data which the Contractor is
required to submit, but only for conformance with the information given in the Contract Documents.
Such review and approvals or other action will not extend to means, methods, techniques, equipment
choice and usage, sequences,schedules,or procedures of construction or to related safety precautions
and programs.
Site Visits to Observe Construction - Kimley-Horn will provide on-site construction observation
services during the construction phase. Kimley-Horn will make visits at construction milestones and
intervals as directed by Client in order to observe the progress of the Work. Such visits and
observations by Kimley-Horn are not intended to be exhaustive or to extend to every aspect of
Contractor's work in progress. Observations are to be limited to spot checking, selective measurement,
and similar methods of general observation of the Work based on Kimley-Horn's exercise of
professional judgment. Based on information obtained during such visits and such observations,
Kimley-Horn will evaluate whether Contractor's work is generally proceeding in accordance with the
Contract Documents, and Kimley-Horn will keep Client informed of the general progress of the Work.
k mley-horn.corn: 4500 Main Street, Suite 500, Virginia Beach, VA 23462 757 213 8600
Kimley>>>Horn Page 6
The purpose of Kimley-Horn's site visits will be to enable Kimley-Horn to better carry out the duties and
responsibilities specifically assigned in this Agreement, and to provide the County a greater degree of
confidence that the completed Work will conform in general to the Contract Documents. Kimley-Horn
shall not, during such visits or as a result of such observations of Contractor's work in progress,
supervise, direct, or have control over Contractor's work, nor shall Kimley-Horn have authority over or
responsibility for the means, methods, techniques, equipment choice and usage, sequences,
schedules, or procedures of construction selected by Contractor, for safety precautions and programs
incident to Contractor's work, nor for any failure of Contractor to comply with laws and regulations
applicable to Contractor's furnishing and performing the Work. Accordingly, Kimley-Horn neither
guarantees the performance of any Contractor nor assumes responsibility for any Contractor's failure
to furnish and perform its work in accordance with the Contract Documents.
Engineering Support-Kimley-Horn will be available during construction to answer questions, resolve
construction conflicts, evaluate value engineering proposals, and review field changes. Kimley-Horn
will provide engineering support when required for design changes based on findings in the field.
Clarifications and Interpretations - Kimley-Horn will respond to reasonable and appropriate
Contractor requests for information and issue necessary clarifications and interpretations of the
Contract Documents to Client as appropriate to the orderly completion of Contractor's work. Any orders
authorizing variations from the Contract Documents will be made by the County. .
Change Orders - Kimley-Horn may recommend Change Orders to the County, and will review and
make recommendations related to Change Orders submitted or proposed by the Contractor.
Progress Meetings- Kimley-Horn will attend monthly construction progress meetings as directed by
the County.
Limitation of Responsibilities—Kimley-Horn shall not be responsible for the acts or omissions of any
Contractor, or of any of their subcontractors, suppliers, or of any other individual or entity performing or
furnishing the Work. Kimley-Horn shall not have the authority or responsibility to stop the work of any
Contractor.
Services Not Included
The following services have not been included in this scope of services but can be included as
additional services upon written request by the County:
• Right-of-Way Acquisition Coordination
• Acquisition Plats
• Test Pits
kimley-horncom 4500 Main Street, Suite 500,Virginia Beach, VA 23462 757 213 8600
Kimley>>>Horn Page 7
• Public Involvement
• Wetland Permits
Schedule
Kimley-Horn will complete the work detailed in this scope of services based on the schedule below.
Our tentative schedule is as follows:
Task 1 will take approximately 7 days to complete
Task 2 will take approximately 21 days to complete,followed by an anticipated 90 day review period
by the County and VDOT.
Task 3 will take approximately 14 days to complete,followed by an anticipated 90 day review period
by the County and VDOT.
Fee and Billing
All tasks included in this scope of services will be accomplished based on a cost plus contract (time
and materials). Below is a breakdown of the anticipated fee.
Construction Documents $ 7,810.00
Environmental Coordination $ 4,060.00
Expenses $ 500.00
Environmental Expense $ 600.00
Pavement Borinns(Geotechnical Engineer) $ 2,000.00
TOTAL $ 14,970.00
A breakdown of the estimated man-hours to complete this task is shown in the Appendix.
Fees will be invoiced monthly based upon the man-hours of service provided as of the invoice date.
Payment will be due within 25 days of your receipt of the invoice.
Also included in the Appendix is additional information on project team members and their roles on
the project, experience within the County for key project members, and a description of qualifications
on similar projects.
kimley-horn:com . 4500 Main Street, Suite 500,Virginia Beach, VA 23462 757 213 8600
Kimley>>>Horn Page 8
Closure
We appreciate the opportunity to provide these services to you. We can begin work immediately upon
receipt of authorization from Isle of Wight County. Given that this work will be performed under the
Professional Services On-Call contract between Isle of Wight County and Kimley-Horn, we anticipate
a purchase order or some similar form of written notice to proceed. If the County determines that verbal
authorization is appropriate,we would respectfully request that you sign in the space below and return
a copy of the signed form to Kimley-Horn.
Please contact us if you have any questions.
Sincerely,
KIMLEY-HORN AND ASSOCIATES, INC.
feflea
William Mackey Jr. P.E. Andrew P. Farthing, P.E.
Vice-President Project Manager
Nat-AAA County Administrator
kimley-horn.com . 4500 Main Street, Suite 500,Virginia Beach, VA 23462 757 213 8600
Kim ley> Horn Page 9
Appendix
Isle of Wight County-Mogarts Beach Road(East)
Senior
Professional Professional Engr/Plnr Analyst Admin. TOTAL
Kicicoff/WorIcplan 4 — 4
-
Field Visit/Data Collection 4 4
M?tlarl-Firt Submittal
Details and Narrative 2 4 6
Specifications 2 4 6
Review Meetings 4 4
Environmental Requirements
-77.777-77-7777 77-717
EQ-429 2 2
Coordination with VDHR 6 6
Other Agency Coordination 4 _ _ _ 4
Site Visit-delineation,has mat,Historic Resources 4 __ _ 4
COE Site Visit and Coordination 4 4
— _
Additional Forms(121,555,EDR) 8 8
Site Visit to Coordinate Design with VDOT 4
No Plan Second Submittal 4 4
Pavement Section Coordination 4 4
_
Bid Phase Services 4 4
--------- -- --
Construction Phase Services 4 4
QA/QC 4 4
Opinion of Probable Construction Costs 2 4 6
Accounting 4 4
Total 4 66 0 12 4 86
Is 185.00 $ 145.00 $ 125.004! 105.00 I $ 75.00
$
kirnley-horn,cbm 4500 Main Street, Suite 500, Virginia Beach,VA 23462 757 213 8600
Kim ey>>>Horn Page 10
DESIGN TEAM MEMBERS
Project Manager:Andrew Farthing, PE, ENV SP
• Over 10 years of experience providing engineering design services on transportation projects
within the state of Virginia.
• Locally Administered Project(LAP) experience with various municipalities including Isle of
Wight County, City of Suffolk, City of Virginia Beach, and James City County.
• Recently served as project manager on the completed Windsor Middle School Sidewalk
Project within the County.
• Recently served as project manager for ten (10) successfully completed Rural Rustic Road
projects within the County and partnered with County staff to develop a prioritization tool for
ranking future Rural Rustic Road and Rural Addition projects within the County.
• On this project, Andrew will perform the project site visit, attend and lead design meetings
with the County and VDOT staff, prepare construction documents, coordinate pavement
section requirements with VDOT, and assist the County with bid phase and construction
phase services.
Environmental Task Manager: Katie Crum, PWS, CPWD
• Over 12 years of experience in environmental planning and permitting including extensive
experience with managing and preparing NEPA documents for locally administered
transportation projects throughout Virginia
• Has experience in conducting wetland delineations in accordance with methods outlined in
the U.S.Army Corps of Engineers (USACE) 1987 Wetland Delineation Manual
• Has experience in preparing Joint Permit Applications(JPAs)for a wide array of projects for
both tidal and non-tidal wetland and waters impacts.
• Performs permit compliance activities during construction activities
• Recently served as environmental task manager on ten (10) successfully completed Rural
Rustic Road projects within the County
• On this project, Katie will serve as the Environmental Task Manager and perform the required
environmental due diligence and environmental documentation for this project. _
Quality Assurance/Quality Control:William F. Mackey, Jr, PE, ENV SP
• Over 28 years of experience on design projects throughout Virginia that range from rural
secondary roads to large complex interstate interchange improvement projects
• Specializes in locally administered projects and currently plays an integral role in the
planning, design, and phasing of CIP projects in an on-call environment
• His array of experience in roadway design coupled with his focus on delivering quality
products provides Isle of Wight County with both an assurance manager and quality control
reviewer for this project.
• On this project, Bill Mackey will serve as the Quality Assurance and Quality Control manager
for the project to consist of continual support of the project and review of design documents.