Community Development Building Low Slope Roof Replacement IFB #16-4110-01 •
Local Roots,Global Reach
ISLE OF WIGHT
COUNTY VIRGINIA
December,18,2015
IFB#16-4110-01
INVITATION FOR BID
DEPARTMENT OF BUDGET AND FINANCE
Community Development Building Low Slope Roof Replacement
Section A
(Submit with the bid)
•
I-1
•
rer
Local Roots,Global Reach
ISLE OF WIGHT
COUNTY,VIRGINIA
December 18,2015
IFB#16-4110-01
• INVITATION FOR BID
DEPARTMENT OF BUDGET AND FINANCE
Community Development Building Low Slope Roof Replacement
Sealed bids subject to the conditions and instructions contained herein,will be received at the office of the Purchasing Agent listed below,until
the time and date shown below(local prevailing time),for furnishing the items or services described herein.
SCOPE OF WORK: Contractor shall provide all labor,superintendence,materials,tools,equipment,and other
ancillary items necessary to perform the Work outlined in the Specifications and Drawings.This work is to include
the removal and disposal of the existing thermoplastic roof systems on Roof Sections Al,A2,A3,A4,B1,and B2
down to the metal roof deck.Work is to include the complete removal and disposal of the existing roof membrane,
flashings,insulation,gravel,wood blocking(not shown to remain)and sheet metal flashing down to existing deck.
Provide a newly fully adhered EPDM roof membrane system over new mechanically attached polyisocyanurate
insulation.Please see the full Scope of Work to follow.
Optional Prebid Meeting: 10:00 AM, January 12, 2016 at the site: 17146 Monument Circle, Isle
Wight County,VA 23397
Bid Due: 3:00 PM., February 2, 2016
Contract Officer:
Michael Coburn,Sr.,Purchasing Agent,Michael.coburn@isleofwightus.net
**SECTION"A"AND ONE ELECTRONIC CD COPY IS REQUESTED AT SUBMITTAL**
In compliance with this invitation for bids,and subject to all the conditions thereof,the undersigned offers,if this bid is accepted within ninety
(90)calendar days from the date of the opening,to furnish any or all of the items and/or services upon which prices are quoted,at the price set
opposite each item,to be delivered at the time and place specified herein.The undersigned certifies he has read,understands,and agrees to all
terms,conditions,and requirements of this bid,and is authorized to contract on behalf of firm named below.
Company
Name:
Address:
City/State/
Zip:
Telephone: FAX No.:
E-mail:
Print Name: Title:
Signature: Date:
I-2
Table of Contents
Section A 1
Bid Due: 3:00 PM.,February 2,2016 2
SCOPE OF WORK 4
INVITATION FOR BIDS 4
BID SUBMITALS: 4
QUESTIONS: 5
BID OPENING: 5
LIQUIDATED DAMAGES: 5
PRE-BID MEETING: 5
BID FORM 6
SCHEDULE OF UNIT PRICES 9
BID BOND 10
CONDITIONS AND INSTRUCTIONS 11
Section B 21
AGREEMENT 22
PERFORMANCE BOND 23
PAYMENT BOND 26
Section C 28
1-3
SCOPE OF WORK
1. Remove and dispose of the existing thermoplastic roof systems on Roof Sections Al,A2,A3,
A4,B1, and B2 down to the metal deck. Work is to include the complete removal and disposal of
the existing roof membrane,flashings, insulation, gravel,wood blocking(not shown to remain)
and sheet metal flashing down to the existing deck.The approximate roof areas are as follows:
• Roof Section Al —Approximately 3,500 SF(Metal Deck)
• Roof Section A2—Approximately 50 SF(Metal Deck)
• Roof Section A3—Approximately 130 SF(Metal Deck)
• Roof Section A4—Approximately 80 SF(Metal Deck)
• Roof Section B1 —Approximately 700 SF(Metal Deck)
• Roof Section B2—Approximately 150 SF(Metal Deck)
2. Provide a new fully adhered EPDM roof membrane system over mechanically attached
polyisoyanurate insulation.
3. Provide new fully adhered EPDM membrane flashings, sheet metal flashings,plywood sheathing
and wood blocking as outlined in the Contract Documents.
4. Provide all necessary utility disconnects,reconnects and utility extensions needed to complete the
work.
5. Remove the existing asphalt shingles from the steep slope roof adjacent to Roof Section Al as
necessary to remove and replace the deteriorated tongue and groove deck boards 12 inches up
from the roof eave.Provide new replacement tongue and grove decks boards to match existing.
Provide new self-adhered underlayment.
6. Provide new through wall flashing at the masonry rising wall and Roof Section A2 interface as
outlined in the Contract Documents.
7. Provide a 3 year contractor's warranty and a 20 year manufacture's roof system warranty.
INVITATION FOR BIDS
Contractor shall provide all labor, superintendence,materials,tools, equipment, and other ancillary items
necessary as identified to replace the roofing system on the Community Development Building.
Bids received prior to the opening time specified below shall be publicly opened and read aloud at the
specified opening time in the IOWC Department of Budget and Finance. Sealed bids,subject to the
conditions and instructions contained herein,will be accepted at:
Department of Budget and Finance
Isle of Wight County
17090 Monument Circle, Suite 137
Isle of Wight,VA 23397
BID SUBMITALS:
Bid Documents may be obtained on the Isle of Wight website under Budget and Finance:
http://www.co.isle-of-wight.va.us/budget-and-finance/and on the State's eVA website:
http://eva.virginia.gov/,or from the Purchasing office at: Isle of Wight County,Department of Budget and
Finance, 17090 Monument Circle, Suite 137,Isle of Wight,Virginia,23397
I-4
QUESTIONS:
Questions concerning this project must be in writing and addressed to the Purchasing Agent as shown on
the cover page; and,must be received no later than five(5)business days preceding the date that the bids
are accepted.
BID OPENING:
Bids shall be publicly opened and read aloud on the date that the bids are accepted.Public opening will be
held at 3:15 PM. (local prevailing time),in the Isle of Wight Purchasing Office at: 17090 Monument
Circle,Isle of Wight,Virginia 23397.
LIQUIDATED DAMAGES:
If said work is not completed within the time stated in the Notice to Proceed,the Contractor shall be liable
and hereby agrees to pay to the Owner as liquidated damages, and not as a penalty,the amount of five
hundred dollars($100.00)per calendar day for each and every part of a day thereafter that said work
remains substantially incomplete. The County reserves the right,at its sole discretion,to deduct liquidated
damages from any outstanding amount due the Contractor.
IF YOU NEED ANY REASONABLE ACCOMMODATION FOR ANY TYPE OF DISABILITY IN
ORDER TO PARTICIPATE IN THIS PROCUREMENT, PLEASE CONTACT THIS DIVISION AS
SOON AS POSSIBLE.
F PRE-BID MEETING:
An Optional prebid meeting shall occur at 10:00 AM, January 12, 2016 at the site: 17146 Monument
Circle,Isle Wight County,VA 23397
Bids must be submitted on the designated Bid Form, signed by an authorized representative, delivered in a sealed
opaque envelope bearing the Bidder's name,address,project name, acceptance date and time. An electronic copy is
requested and should be included with your submittal. Revisions, changes, and deletions contained in the bid
documents must be initialed by the Bidder. Failure to comply with this instruction may result in the bid being
deemed non-responsive.
Bidders should carefully examine the specifications and fully inform themselves to all conditions and matters that
could have an effect on the cost. Should a Bidder find discrepancies in or omissions from the specifications or
Invitation to Bid,or should be in doubt as to their meanings,he shall notify Procurement,personnel as noted above.
The right is reserved to revise or amend these specifications prior to the date set for receipt of bids as may be
required by the County. That date may be delayed if deemed necessary by the County. Any revisions and/or
amendments will be in the form of an addendum to this document.
The right is reserved to accept or reject any or all bids in whole or in part and to waive any informalities in the IFB,
and to enter into any contract deemed to be in the best interest of IOWC.
Bidder has examined copies of all the Bid Documents including the following Addenda:
Date Number
Bidder has made such independent investigations as Bidder deems necessary to fully inform himself as to the
conditions affecting cost and progress of performance of the Work.
I-5
BID FORM
TO: Isle of Wight County,Virginia
Director of Budget and Finance
17090 Monument Circle, Suite 137
Post Office Box 80
Isle of Wight,Virginia 23397
RE: Isle of Wight County,Virginia
IOWC Community Development Building,Low Slope Roof Replacement
Isle of Wight County IFB#16-4110-01
The undersigned Bidder, , offers and agrees, if this Bid is
accepted, to enter into an Agreement with the Owner in the form included in the Contract Documents to
complete all Work as specified or indicated in the Contract Documents for the Lump Sum of
($ ).
Bidder agrees to begin the Work within ten (10) days of Notice to Proceed and that Final Completion
shall be within seventy(70) calendar days of Notice to Proceed. In submitting this bid,Bidder represents,
as more fully set forth in the Bid Documents,that:
Bidder has examined copies of all the Bid Documents including the following Addenda:
Date Number
Bidder has examined the site and locality where the Work is to be performed, the legal requirements
(federal, State and local laws, ordinance, rules and regulations) and has made such independent
investigations as Bidder deems necessary to fully inform himself as to the conditions affecting cost and
progress of performance of the Work.
The Method of Payment is invoice processing upon presentation with Terms of Net 30 days.
Not more than fifty percent (50%) of the work shall be subcontracted and the amount of any
subcontractors proposed by the bidder in excess of ten percent (10%) of the bid price shall be identified
on the Bid Form.
Subcontractor:
Subcontractor:
I-6
Bidders shall provide a list of at least three (3) references (1 each from the last 3 construction projects).
Each reference shall include the name of the organization, the complete mailing address,the name of the
contact person and telephone number.
ORGANIZATION ADDRESS CONTACT PERSON TELEPHONE
1.
2.
3.
Bidder accepts all terms and conditions of the Contract Documents.
I certify by my signature below that I have received the documents associated with this Bid and
understand that the review for completeness of these documents and the understanding and
comprehension of the specifications is solely my responsibility; based on this, by my signature below, I
waive all rights to future claims against Isle of Wight County that the documents were incomplete or not
understandable.
My signature below certifies that this Bid is not the result of or affected by, any act of collusion with
another person or company engaged in the same line of business or commerce, or any act of fraud
punishable under Section 18.2-498.1 et. seq. of the Code of Virginia (1950, as amended). Furthermore, I
understand that fraudulent bidding is a crime under the Virginia Governmental Frauds Act, the Virginia
Government Bid Rigging Act, the Virginia Anti-Trust Act, and federal law and can result in fines, prison
sentences,and civil damage awards.
I certify that the bidder represented herein is eligible to bid with respect to all applicable sections of State
and Local Government Conflict of Interest Act,Section 2.2-3100 Et Seq., of the Code of Virginia(1950,
as amended).
I agree to abide by all conditions of this Bid and certify that I am authorized to sign this Bid.
Virginia Contractor No.
Signature Date _
Print
State Corporation Commission Identification No:
Or
Describe why the bidder or offeror is not required to be authorized by the State Corporation Commission:
•
I-7
(An Individual,Partnership,or Non-Incorporated Organization)
Type/Print
Name
Title
Name of Organization
Business Address
Phone Number Fax No.
(A Corporation)
Corporation Name
State of Incorporation
Person Authorized to Sign
Title
(Corporate Seal)
Attest(Secretary)
Business Address
Phone Number Fax No.
(A Joint Venture)
By(Signature)
Type/Print Name
Title
Virginia Contractor No.
Business Address
Phone Number Fax No.
By(Signature)
Type/PrintName
Title
Virginia Contractor No.
Business Address
Phone Number Fax No.
(Each joint venturer must sign. The name of signing for each individual,partnership and corporation that is a party to the joint
venture shall be in the manner indicated above.)
III
I-8
SCHEDULE OF UNIT PRICES
Project: Community Development Building Low Slope Roof Replacement
IFB#16-4110-01
Bid Submitted By:
Unit Prices shall include the furnishing of labor,material and all incidental work called for in the Contract
Documents.
A. Unit Price#1:
Provide a unit price to remove, dispose of, and provide new wood nailers/blocking in accordance with
specifications Section 06105 "Miscellaneous Carpentry."
$ per Board Foot Replaced
-B. Unit Price#2:
Provide a unit price to remove, dispose of and provide new metal roof decking and secure to framing.
Decking shall match existing profile and grade.
$ per Square Foot Replaced
I-9
BID BOND
KNOW ALL PERSONS BY THESE PRESENTS,that we,the undersigned,
as Principal, and ,as Surety, are hereby held and firmly
bound unto Isle of Wight County as Owner in the penal sum of for payment of
which,well and truly to be made,we hereby jointly and severally bind ourselves,successors and assigns.
Signed,this day of 2016.The condition of the above obligation is such that
whereas the Principal has submitted to Isle of Wight County a certain BID, attached hereto and hereby
made a part thereof to enter into an Agreement in writing, for the roof replacement as described in
construction plans entitled Community Development Building Low Slope Roof Replacement,IFB#
16-4110-01. Details shown on plans.
NOW THEREFORE,
(a) If said BID shall be rejected, or
(b) If said BID shall be accepted and the Principal shall execute and deliver an Agreement in the
form attached hereto (properly completed in accordance with said BID) and shall furnish a
BOND for his faithful performance of said Agreement, and for the payment of all persons
performing labor or furnishing materials in connection therewith, and shall in all respects perform
the Agreement created by the acceptance of said BID, then this obligation shall be void;
otherwise the same shall remain in force and effect, it being expressly understood and agreed that
the liability of the Surety for any and all claims hereunder shall, in no event, exceed the penal
amount of this obligation as herein stated.
The Surety, for value received, hereby stipulates and agrees that the obligations of said Surety and its
Bond shall be in no way impaired or affected by any extension of the time within which the OWNER may
accept such BID; and said Surety does hereby waive notice of any such extension.
IN WITNESS WHEREOF,the Principal and the Surety have hereunto set their hands and seals, and such
of them as are corporations have caused their corporate seals to be hereto affixed and these presents to be
signed by their proper officers,the day and year first set forth above.
Principal
Surety
BY:
IMPORTANT - Surety companies executing BONDS must appear on the Treasury Department's most
current list(Circular 570 as amended) and be authorized to transact business in the state where the project
is located.
I-10
CONDITIONS AND INSTRUCTIONS
Rev: 12/15/2015
1. Use of Form: All bids shall be submitted on and in accordance with this form. If more space is
required to furnish a description of the goods and/or services bid, or delivery terms, the bidder
may attach a letter hereto that will be made a part of the bid. In case of a conflict with published
requirements, the bid may be considered non-responsive. The County's published specifications
shall supersede any additional writings submitted with the bid. Such additional writings shall be
clearly marked and noted as an exception.
2. Submittals: All bids shall be submitted sealed,plainly marked showing the bid number, date and
time. Section `A' of the solicitation document is to be returned when submitting a bid. Failure to
The entire Section `A' may result in a determination that the submittal is non-responsive. In
addition, an electronic ".pdf' copy of your submittal is requested to be included in the package.
Either CD or thumb drives are acceptable.
3. Late Bids: Bids and amendments thereto, if received by Purchasing after the date and time
specified for bid opening, will not be considered. It will be the responsibility of the bidder to see
that their bid is received by Purchasing as specified. There will be no exceptions. Date of
postmark will not be considered. Telephone, facsimile, electronic and verbal bids will not be
accepted. Prices or changes shown on the outside of an envelope will not be considered in
determination of low bid.
4. County Closures: If County Offices are closed for business at the time scheduled for the bid
opening, for whatever reasons, sealed bids will be accepted and opened on the next business day
of the County,at the original scheduled hour.
5. Acceptance of Bid: Receipt of the bid by the County is not to be construed as an award or an
order to ship.
6. Bid Security: Each bid shall be accompanied with a bid bond equal to five (5) percent of the
total amount of the bid, made payable to Isle of Wight County. Upon approval of the County
Attorney, a Bidder may furnish a personal bond or a bank or savings and loan association's letter
of credit on certain designated funds for the amount required for the Bid Security. Such bid
security shall be left with the County as a guarantee of good faith on the part of the Bidder that if
the bid is accepted,the Bidder shall provide all required submittals and execute the contract.
7. Offer/Acceptance: Each bid is received with the understanding that the acceptance in writing by
the County of the bidder to furnish any or all of the goods and/or services described therein, shall
constitute a contract between the bidder and the County, which shall bind the bidder to furnish
and deliver the goods and/or services quoted at the prices stated and in accordance with the
conditions of the accepted bid; and the County on its part to order from such bidder, except for
causes beyond reasonable control; and pay for, at the agreed prices, all goods and/or services
specified and delivered.
8. Withdrawal of Bids: Bidder has the right to request withdrawal of their bids from consideration
due to error by giving notice not later than two business days after the bids are publicly opened.
Work papers showing evidence of error(s)may be required.
I-11
Bids may be withdrawn any time prior to the bid opening. Withdrawal of bids may be
accomplished by submitting such request in writing on the issuing company's letterhead in
person, electronically(email) or by certified mail.
9. Addenda: If issued, addenda to this solicitation will be posted on the Purchasing website
http://www.co.isle-of-wight.va.us/budget-and-finance/and on the Commonwealth's website,
http://eva.virginia.gov/. It is the bidder's responsibility to check one of the websites or to
contact the Purchasing division prior to the submittal deadline to ensure that the bidder has a
complete, up-to-date package. Acknowledgement of all issued Addenda shall be indicated on the
bid form in the appropriate spaces.
10. Governing Document: The solicitation document maintained by Purchasing in the bid file, shall
be considered the official copy. In the case of any inconsistency between bid documents
submitted to the County, but not clearly listed as an exception, the language of the official copy
shall prevail. Furthermore, any exception or change to the specifications made by the bidder may
be cause to disqualify your bid.
11. Award: Award will be made to the lowest responsive and responsible bidder. The quality of the
goods and/or services to be supplied, their conformity with the specifications, their suitability to
the requirements, the delivery, qualifications and references will be taken into consideration in
making the award. The County reserves the right to refuse all bids.Determination of low bid shall
be determined by the audited figure shown on the pricing page titled `Lump Sum.'
12. Negotiation: Unless canceled or rejected, a responsive bid from the lowest responsible bidder
shall be accepted as submitted; except that if the bid from the lowest responsible bidder exceeds
available funds, the County may negotiate with the apparent low bidder to obtain a contract price
within the available funds.
13. Announcements: Upon the award or the announcement of the decision to award a contract, the
County will publicly post such notice on the bulletin board located outside of the Purchasing
Division and on the County's web site: http://www.co.isle-of-wight.va.us/budget-and-finance/
14. County's Rights: The County reserves the right to reject any and all bids, and to waive any
informality if it is determined to be in the best interest of the County.
15. Cooperative Agreements: If authorized by the bidder(s), the resultant contract(s) may be
extended to any jurisdiction within the Commonwealth of Virginia to purchase at the contract
prices in accordance with the contract terms. Any jurisdiction using such contracts shall place its
own order(s) directly with the successful contractor(s). The County of Isle of Wight acts only as
the contracting agent and is not responsible for placement of orders,payment, or discrepancies of
the participating jurisdictions. It is the contractor's responsibility to notify the jurisdictions of the
availability of contract(s).
16. Prices: Prices shall be stated in units of quantity specified. No additional charges shall be passed
to the County, including any applicable taxes, delivery, or surcharges. Prices quoted shall be the
final cost to the County. In case of error in the extension of prices,the unit price shall govern.
17. Corrections: All prices and notations should be in ink or typewritten. Mistakes may be crossed
out and corrections made in ink and must be initialed and dated by the person signing the bid.
I-12
•
18. Delivery: The time of delivery must be stated in definite terms. If time of delivery for different
goods and/or services varies,the bidder shall so state.
19. Samples: Samples, when requested, must be furnished free of expense, and upon request, if not
destroyed,will be returned at the bidder's risk and expense.
20. Brand Names: The use of the name of a manufacturer, brand, make or catalog designation in
specifying an item shall restrict bidders to the manufacturer, brand, make or catalog designation
identified, unless qualified by the provision "or equal." If qualified by the provision "or equal"
the Brand Names are used simply to indicate the character, quality and/or performance
equivalence of the goods and/or services desired. The goods and/or services on which bids are
submitted must be of such character, quality and/or performance equivalence that it will serve as
that specified. In submitting bids on goods and/or services other than as specified, bidder shall
furnish complete data and identification with respect to the alternate goods and/or services that
they propose to furnish. It shall be in the County's sole judgment if a substitute product offered is
an approved equal and acceptable.
21. Standard equipment: Any equipment delivered must be standard, new and unused equipment,
latest model, except as otherwise specifically stated in the bid. Where any part or the normal
accessories of equipment is not described, it shall be understood that all the equipment and
accessories that are usually provided in the manufacturer's stock model shall be furnished.
22. Silence of Specifications: The apparent silence of these specifications and any supplemental
specifications as to any detail or the omission from the specifications of a detailed description
concerning any point shall be regarded as meaning that only the best commercial.practices are to
prevail and correct type, size and design are to be used. All interpretations of these specifications
shall be made on the basis of this statement.
23. Capacity of Bidder: All bids must be signed by a responsible officer or employee having the
authority to bind the firm in contract. The bidder agrees that its contract performance shall be in
strict conformance with the contract documents.
24. Rights to Damages: By signing this bid,the bidder assigns to the County and all rights that it
may have under the antitrust laws of the United States and the Commonwealth of Virginia in any
way arising from or pertaining to this bid. This provision is remedial in nature and is to be
liberally construed by any court in favor of the County.
25. Anti-collusion: The bidder certifies by signing this Invitation of Bid that this bid is made without
prior understanding, agreement, or accord with any other person or firm submitting a bid for the
same goods and/or services and that this bid is in all respects bona fide, fair, and not the result of
any act of fraud or collusion with another person or firm engaged in the same line of business or
commerce. Any false statement hereunder may constitute a felony and can result in a fine and
imprisonment,as well as civil damages.
•
26. Indemnification: The Contractor shall defend, indemnify and hold the County, and the County's
employees, agents, and volunteers, harmless, from and against any and all damage claim,
liability, cost, or expense (including, without limitation, attorney's fees and court costs) of every
kind and nature (including, without limitation, those arising from any injury or damage to any
person,property or business) incurred by or claimed against the contractor, its employees, agents,
and volunteers, or incurred by or claimed against the County, the County's employees, agents,
and volunteers, arising out of, or in connection with, the performance of all services hereunder by
I-13
the contractor. This indemnification and hold harmless includes, but is not limited to, any
financial or other loss including, but not limited to, any adverse regulatory, agency or
administrative sanction or civil penalties, incurred by the County due to the negligent, fraudulent
or criminal acts of the contractor or any of the Contractor's officers, shareholders, employees,
agents, contractors, subcontractors, or any other person or entity hact i
acting on behalf of the
Contractor. Unless otherwise provided by law, the Contractor indemnification obligations
hereunder shall not be limited in any way by the amount or type of damages, compensation, or
benefits payable by or for the Contractor under worker's compensation acts, disability benefit
acts, other employee benefit acts, or benefits payable under any insurance policy. This paragraph
shall survive the termination of the contract including any renewal or extension thereof.
27. Copyright Protection: The Contractor agrees to defend and save the County, its agents, officials,
and employees, harmless from liability of any nature or kind, for use of any copyright,
composition, secret process, patented or unpatented invention, articles or appliances furnished or
used in the performance of the contract, or which the Contractor is not the patentee, assignee, or
licensee,to the same extent as provided in the above paragraph.
28. Laws,Regulations: The Contractor shall keep fully informed of all federal, state, and local laws,
ordinances and regulations that in any manner affect the conduct of the work. The Contractor
shall at all times observe and comply with all such laws, ordinances and regulations.
29. Alien employment: The Contractor certifies that he does not and shall not during the
performance of the contract for goods and services in the Commonwealth, knowingly employ
unauthorized aliens as defined in the federal Immigration Reform and Control Act of 1986, as
amended.
30. SCC Authorization: All bidders or offerors organized or authorized to transact business in the
Commonwealth pursuant to Title 13.1 or Title 50, as amended, shall include the identification
number issued to it by the State Corporation Commission. Any bidder or offeror that is not
required to be authorized to transact business in the Commonwealth as a foreign business entity
under Title 13.1 or Title 50, as amended, or as otherwise required by law shall include in its bid
or proposal a statement describing why the bidder or offeror is not required to be so authorized.
SCC Number or Statement:
Any business entity that enters into a contract with a public body pursuant to this chapter shall not
allow its existence to lapse or its certificate of authority or registration to transact business in the
Commonwealth, if so required under Title 13.1, or Title 50, as amended,to be revoked or
cancelled at any time during the term of the contract.The County may void any contract with a
business entity if the business entity fails to remain in compliance with the provisions of this
section.
31. Contractor's License: If any of the services promulgated under this solicitation consist of
construction work, it is required under Title 54.1, Chapter 11, Code of Virginia, for a contractor
who performs or manages construction, removal, repair, or improvement when the total value
referred to in a single contract or project is:
One hundred twenty thousand dollars($120,000)or more,or the total value of all such
construction,removal,repair or improvements undertaken by such person within any twelve-
month period is seven hundred fifty thousand dollars($750,000)or more shall show evidence of
being licensed as a Class A Contractor.
I-14
Ten thousand dollars($10,000) or more,but less than one hundred twenty thousand dollars
or the total value of all such construction,removal,repair, or improvement undertaken
($120,000) P � P
by such person within any twelve-month period is one hundred and fifty thousand dollars
($150,000) or more,but less than seven hundred fifty thousand dollars($750,000)shall show
evidence of being licensed as a Class B Contractor.
Over one thousand($1,000)but less than ten thousand($10,000), or the total value of all such
construction,removal,repair, or improvements undertaken by such person within any twelve-
month period is one hundred and fifty thousand dollars($150,000)shall show evidence of being
licensed as a Class C Contractor.
The County shall require master certification as a condition of licensure or certification of
electrical,plumbing and heating,ventilation and air conditions contractors.
A valid business license from the County may be required.The bidder shall complete whichever
of the following notations as appropriate:
"Licensed Class A Virginia Contractor Number
"Licensed Class B Virginia Contractor Number ."
"Licensed Class C Virginia Contractor Number ."
32. Payment Terms: Payment terms shall be `Net 30'days, from the date of Contractor invoice
approval by the County.
Payment terms, if offered, shall not be considered in determining the low bidder.
Discount period,if offered,shall be computed from the date of proper receipt of the contractor's
correct invoice,or from the date of acceptable receipt of the goods and/or services,whichever is
latest.
The payment terms stated herein must appear on the contractor's invoice.Failure to comply with
this requirement shall result in the invoice being returned to the contractor for correction.
Late payment charges shall not exceed the allowable rate specified by the Commonwealth of
Virginia Prompt Payment Act. (1%per month)
Contractor shall submit invoices in duplicate, such statement to include detailed breakdown of all
charges, and shall be based on completion of tasks or deliverables.
Individual Contractors shall provide their social security numbers, and proprietorships,
partnerships, and corporations shall provide their federal employer identification number on their
submittal.
The County prefers to make payment with the County's Purchasing Card.Typically this enables
faster payments to the Contractor.Are you willing and able to accept this type of payment?
Yes No (See paragraph 65 for links)
I-15
33. Default: In event of default by the Contractor,the County reserves the right to procure the goods
and/or services from other sources, and hold the Contractor liable for any excess cost occasioned
thereby. Such actions taken by the County shall not release the contractor from additional
remedies that may be allowed by law.
34. .Availability of Funds: A contract shall be deemed in force only to the extent of appropriations
available to each department for the purchase of such goods and/or services. The County's
extended obligations on those contracts that envision extended funding through successive fiscal
periods shall be contingent upon actual appropriations for the following years.
35. Appeals Procedure: Upon your request, administrative appeals information will be provided that
shall be used for hearing protests of a decision to award, or an award, appeals from refusal to
allow withdrawal of bids, appeals from disqualification, appeals for debarment or suspension, or
determination of non-responsibility and appeals from decision or disputes arising during the
performance of a contract. To be timely all appeals shall be made within the time periods set forth
by the Virginia Public Procurement Act, §2.2-4357, et seq. Contact the buyer at once for
assistance.
36. Faith-based Organizations: The County of Isle of Wight does not discriminate against faith-
based organizations.
37. Anti-Discrimination: By submitting their bids, bidders certify to the County that they will
conform to the provisions of the Federal Civil Rights Act of 1964, as amended, as well as the
Virginia Fair Employment Contracting Act of 1975, as amended, where applicable, the
Virginians with Disabilities Act,the Americans with Disabilities Act and 2.2-4311 of the Virginia
Public Procurement Act (VPPA). If the award is made to a faith-based organization, the
organization shall not discriminate against any recipient of goods, services, or disbursements
made pursuant to the contract on the basis of the recipient's religion, religious belief, refusal to
participate in a religious practice, or on the basis of race, age, color, gender or national origin and
shall be subject to the same rules as other organizations that contract with public bodies to
account for the use of the funds provided; however, if the faith-based organization segregates
public funds into separate accounts, only the accounts and programs funded with public funds
shall be subject to audit by the public body. (Code of Virginia 2.2.4343.1E).
In every contract over$10,000 shall include the following provisions:
1. During the performance of this contract,the Contractor agrees as follows:
a. The Contractor will not discriminate against any employee or applicant for employment
because of race,religion, color, sex,national origin,age, disability, service disabled
veterans or any other basis prohibited by state law relating to discrimination in
employment, except where there is a bona fide occupational qualification reasonably
necessary to the normal operation of the Contractor.The Contractor agrees to post in
conspicuous places, available to employees and applicants for employment,notices
setting forth the provisions of this nondiscrimination clause.
b. The Contractor,in all solicitations or advertisements for employees placed by or on
behalf of the Contractor,will state that such Contractor is an equal opportunity employer.
c. Notices,advertisements and solicitations placed in accordance with federal law,rule or
regulation shall be deemed sufficient for the purpose of meeting these requirements.
I-16
2. The Contractor will include the provisions of Section a,b, and c above in every subcontract
or purchase order over$10,000, so that the provisions will be binding upon each
subcontractor or vendor.
38. Drug-Free Workplace: During the performance of this contract, the Contractor agrees to (1)
provide a drug-free workplace for the Contractor's employees; (2) post in conspicuous place,
available to employees and applicants for employment, a statement notifying employees that the
unlawful manufacture, sale, distribution, dispensation, possession, or use of a controlled
substance or marijuana is prohibited in the Contractor's workplace and specifying the actions that
will be taken against employees for violations of such prohibition; (3) state in all solicitation or
advertisement for employees placed by or on behalf of the Contractor that the Contractor
maintains a drug-free workplace; and(4) include the provisions of the foregoing clauses in every
subcontract or purchase order of over $10,000, so that the provisions will be binding upon each
subcontractor or vendor.
For the purposes of this section, "drug-free workplace"means a site for the performance of work
done in connection with a specific contract awarded to a Contractor,the employees of whom are
prohibited from engaging in the unlawful manufacture,sale, distribution, dispensation,possession
or use of any controlled substance or marijuana during the performance of the contract.
39. Assignment of Contract: A contract shall not be assignable by the Contractor in whole or in part
without the written consent of the County.
40. Independent Contractor: The Contractor and any employees, agents, or other persons or entities
acting on behalf of the Contractor shall act in an independent capacity and not as officers,
employees, or agents of the County.
41. Scheduling and Delays: The parties to any contract resultant of this solicitation acknowledge
that all or part of the work to be performed hereunder may be delayed and extended at the option
of the County. Such delays may be caused by delays, denials and modifications of the various
state or federal permits, or for other reasons. The County shall not be required to pay any of the
Contractor's direct or indirect costs, or claims for compensation, extended overhead, or other
damage or consequential damages arising out of or related to any delays or interruptions required
or ordered by the County. If the County delays the project for any reason for a continuous period
of ninety (90) days or more, the County and Contractor will negotiate a mutually agreeable
adjustment to the Contractor's award amount. Notwithstanding the above, in construction
contracts,to the extent that an unreasonable delay is caused by the act or omissions of the County
due to causes within the County's control,the above waiver or release shall not apply.
42. Governing Law: This Agreement is made, entered into, and shall be performed in the County of
Isle of Wight, Virginia, and shall be governed by the applicable laws of the Commonwealth of
Virginia without regard to its conflict of law rules. In the event of litigation concerning this
Agreement, the parties agree to the exclusive jurisdiction and,venue of the Circuit Court of the
County of Isle of Wight, Virginia; however, in the event that the federal court has jurisdiction
over the matter, then the parties agree to the exclusive jurisdiction and venue of the U.S. District
Court for the Eastern District of Virginia,Norfolk Division.
The Contractor shall not cause a delay in services because of the pending or during litigation
proceedings, except with the express,written consent of the County or written instruction/order
from the Court.
I-17
43. Severability: If any provision of this contract or the application thereof to any person or
circumstances shall to any extent be invalid or unenforceable, the remainder of this contract, or
the application of such provision to persons or circumstances other than those which it is invalid
or unenforceable, shall not be affected hereby, and each provision of this contract shall be valid
and enforced to the full extent permitted by law.
44. Termination for Convenience: The County may at any time, and for any reason, terminate this
Contract by written notice to Contractor specifying the termination date, which shall be not less
than thirty(30)days from the date such notice is mailed.
Notice shall be given to Contractor by certified mail/return receipt requested at the address set
forth in Contractor's Bid Proposal or as provided in this Contract. In the event of such
termination,Contractor shall be paid such amount as shall compensate Contractor for the work
satisfactorily completed, and accepted by the County, at the time of termination. If the County
terminates this Contract, Contractor shall withdraw its personnel and equipment, cease
performance of any further work under this Contract,and turn over to the County any work
completed or in process for which payment has been made.
45. Termination for Cause: In the event that Contractor shall for any reason or through any cause be
in default of the terms of this Contract, the County may give Contractor written notice of such
default by certified mail/return receipt requested at the address set forth in Contractor's
Bid/Proposal or as provided in this Contract.
Unless otherwise provided,Contractor shall have ten(10)days from the date such notice is
mailed in which to cure the default. Upon failure of Contractor to cure the default,the County
may immediately cancel and terminate this Contract as of the mailing date of the default notice.
Upon termination,Contractor shall withdraw its personnel and equipment, cease performance of
any further work under the Contract,and turn over to the County any work in process for which
payment has been made.In the event of violations of law,safety or health standards and
regulations,this Contract may be immediately cancelled and terminated by the County and
provisions herein with respect to opportunity to cure default shall not be applicable.
46. Contact Prohibition: Direct contact with County departments other than Purchasing,on the
subject of this bid is expressly forbidden except with the foreknowledge and permission of
the Contract Officer.Violation may result in a determination that your firm is ineligible for
an award.
All questions shall be in writing to the Contract Officer shown on the title page of the bid. The
respondents to this IFB shall not contact,either directly or indirectly,any other employee or agent
of the County regarding this IFB. This prohibition shall also extend to the County Board of
Supervisors and locally elected officials.Any such unauthorized contact may disqualify the
bidder from this procurement.
47. Additional Conditions: The Conditions and Instructions in this solicitation are intended to apply
to the resulting contract and shall supersede any conflicting terms offered. Any additional
conditions a bidder intends be considered must be submitted with the bid and noted as an
exception. Such exceptions may result in a finding that the submittal is `non-responsive' to the
bid, negating possibility of an award to that bidder. Contractual documents submitted by the
successful firm after an award will not be accepted.
I-18
48. Contractor Failure to Perform: Failure of the Contractor to perform the contract by reason of
the County's non-acceptance of additional conditions submitted after the award shall result in
termination of the contract by the County, and may result in debarment of the Contractor for a
period of up to three (3) years. Termination and /or debarment of the Contractor shall not
constitute a waiver by the County of any other rights or remedies available to the County by law
or contract.
49. Conflict: In the event of a conflict between the contract documents, including these Conditions
and Instructions, and the terms of a purchase order or related document issued by Purchasing,the
contract documents shall control.
50. Records and Inspection: The Contractor shall maintain full and accurate records with respect to
all matters covered under this contract, including, without limitation, accounting records, written
policies, procedures, time records, telephone records, and any other supporting evidence used to
memorialize, reflect, and substantiate charges or fees related to this contract. The Contractor's
records shall be open to inspection and subject to audit and/or reproduction, during normal
working hours,by the County and its employees,agents or authorized representatives after giving
at least three (3) days' notice to the Contractor by the County. The County shall have access to
such records from the effective date of this contract, for the duration of the contract, and for five
(5) years after the date of final payment by the County to the Contractor pursuant to this contract
or any renewal or extension of this contract. The County's employees, agents or authorized
representatives shall have access to the Contractor's facilities, shall have access to all necessary
records and shall be provided adequate and appropriate work space, in order to conduct audits.
51. Rights and Remedies Not Waived: In no event shall the making by the County of any payment
to the Contractor, or the waiver by the County of any provision under this contract including any
obligation of the Contractor, constitute or be construed as a waiver by the County of any other
provision, obligation, breach of covenant, or any default which may exist under this contract on
the part of the Contractor, and the making of any such payment by the County while any such
breach or default exists shall not impair or prejudice any right or remedies available to the
County.
52. Entire Agreement: This contract and any additional or supplementary documents incorporated
herein by reference contain all the terms and conditions agreed upon by the parties hereto, and no
other agreements, oral or otherwise, regarding the subject matter of this contract or any part
thereof shall have any validity or bind any of the parties hereto. This contract shall not be
modified, altered, changed or amended unless in writing and signed by the parties hereto.
53. Conflicts of Interests: Contractor shall not accept or receive commissions or other payments
from third parties for soliciting, negotiating, procuring, or effecting insurance on behalf of the
County.
54. Responsibility of Contractor: The Contractor shall, without additional costs or fee to the
County, correct or revise any errors or deficiencies in his performance. Neither the County's
review, approval or acceptance of, nor payment for any of the services required under this
Agreement shall be deemed a waiver of rights by the County, and the Contractor shall remain
liable to the County for all costs which are incurred by the County as a result of the Contractor's
negligent performance of any of the services furnished under this Agreement.
I-19
55. Changes and Additions: It shall be the responsibility of the Contractor to notify the County, in
writing, of any necessary modifications or additions in the Scope of this Agreement.
Compensation for changes or additions in the Scope of this Agreement will be negotiated and
approved by the County,in writing.
It is understood and agreed to by both the County and the Contractor that such modifications or
additions to this Agreement shall be made only by the full execution of the County's standard
Agreement change order form. Furthermore,it is understood and agreed by both parties that any
work done by the Contractor on such modification or addition to this Agreement prior to the
County's execution of its standard Agreement change order form shall be at the total risk of the
Contractor and said work may not be compensated by the County.
56. Debarment Status: By submitting a bid, bidders certify that they are not currently debarred by
the Commonwealth of Virginia from submitting bids or proposals on contracts for the type of
goods and/or services covered by this solicitation, nor are they an agent of any person or entity
that is currently so debarred.
57. Safety: All Contractors and subcontractors performing services for the County are required and
shall comply with all Occupational Safety and Health Administration (OSHA), State and County
Safety and Occupational Health Standards and any other applicable rules and regulations. Also all
Contractors and subcontractors shall be held responsible for the safety of their employees and any
unsafe acts or conditions that may cause injury or damage to any persons or property within and
around the work site area under this contract.
58. License Requirement: All firms doing business in the County of Isle of Wight are required to be
licensed in accordance with the County of Isle of Wight business license ordinance. Wholesale
and retail merchants without a business location in the County of Isle of Wight are exempt from
this requirement. Any questions concerning business licenses should be directed to the
Commissioner of the Revenue's Office.
59. Contractor's Form: In cases where the County may accept the Contractor's form agreement,
whereas certain standard clauses that may appear in the Contractor's form agreement cannot be
accepted by the County, and in consideration of the convenience of using that form, and this
form, without the necessity of negotiating a separate contract document, the parties hereto
specifically agree that, notwithstanding any provisions appearing in the attached Contractor's
form contract, the County's contract addendum shall prevail over the terms of the Contractor's
agreement in the event of a conflict.
60. Bidder Qualifications: Only bids from established contractors for work similar in scope to work
herein shall be considered; the County reserves the right to request specific reference information
prior to award. Bidder shall demonstrate that he has adequate and appropriate manpower, tools
and equipment to respond and perform in accordance with the provisions herein.
The County may, at its option, disqualify a bidder and reject his bid for cause. Reasons deemed to
be sufficient for this action shall include,but not be limited to,the following:
o Evidence of collusion among bidders.
o Receipt of more than one bid on any project from an individual,or from a corporation.
This restriction does not apply to subcontractors
o Default on any previous contract.
I-20
o For unreasonable failure to complete a previous contract within the specified time or for
being in arrears on an existing contract without reasonable cause for being in arrears.
o Inability to perform as revealed by an investigation of the Bidder's financial statement,
experience and/or plant and equipment.
o Contractor does not meet project-specific requirements,as identified in the Contract
Documents
61. Pricing to be F.O.B.Destination—Freight Allowed: Pricing shall be F.O.B. destination-freight
included for all competitive bids. F.O.B. Destination-Freight Included shall include all shipping
costs to the County location(s)at the unit cost.No additional shipping charges shall be allowed.
62. Contract Quantities:_The quantities specified in the Invitation for Bid are estimates only unless
otherwise clearly noted, and are given for the information of bidders and for the purpose of bid
evaluation. They do not indicate the actual quantity that will be required, since such volume will
depend upon requirements that may develop during the contract period. Quantities shown shall
not be construed to represent any amount which the County shall be obligated to purchase under
the contract, or relieve the Contractor of his obligation to fill all orders placed by the County,
except as clearly noted.
63. Competition Intended: It is the County's intent that the Invitation for Bid (IFB) permits
competition. It shall be the bidder's responsibility to advise the Buyer in writing if any language
requirement, specification, etc., or any combination thereof, inadvertently restricts or limits the
requirements stated in this IFB to a single source. Such notification must be received by the
Contract Officer prior to the date set for bids to close.
64. Default on Taxes: No bid or proposal will be accepted from, or any Contract awarded to
any person, firm, or corporation that is in arrears, or in default to the County upon any debt or
Contract,or that is a defaulter as surety, or otherwise upon any obligation to the County.
65. The County prefers to make payment with t he County's s Purchasin Card, or b direct deposit. If you are
willing to use either of these methods please register at the following sites:
Pcards: www.bankofamerica.com/epayablesvendors
Direct Deposit: www.paymode.com/isleofwight
Section B
(To be filled out and returned by Successful Bidder)
I-21
AGREEMENT
THIS AGREEMENT, made and entered into this day of , 2016, by and between the
COUNTY OF ISLE OF WIGHT, VIRGINIA, whose principal office is 17090 Monument Circle, Suite
137, Isle of Wight, Virginia 23397, hereinafter called "OWNER", party of the first part, and
hereinafter referred to as
"CONTRACTOR",party of the second part.
The CONTRACTOR did, on the day of 2016, submit a sealed bid to perform the
services stipulated in accordance with plans and specifications prepared by the OWNER entitled
which by reference is made a part
hereof.
It is mutually understood and agreed by the parties hereto that the Invitation to Bid inviting Contractors to
bid as published, Instructions to Bidder, Schedule of Unit Prices, Bid Form, Bid Bond, Contract
Agreement, Hold Harmless Agreement, Certificate of Insurance, Scope of Services and Drawings, all
proceedings by the governing body of the OWNER pertaining to the subject matter of this Contract, all of
which documents are hereinafter referred to as Contract Documents and are a part of this Contract by
reference the same as if each had been fully set out and attached hereto.
In consideration of the following mutual agreements and covenants to be kept by each party:
a. The CONTRACTOR agrees to furnish and pay for all labor,tools, equipment,machinery,
supplies, facilities, superintendence, insurance, taxes, utilities and services necessary to
perform all items set forth in the written Contract Documents hereto attached and made a
part hereof in strict compliance with the Contract Documents and Lump Sum of
(the "Contract Sum"), subject to adjustment as provided in said
documents.
b. Invoice payments for work completed under this contract shall be made in strict
accordance with the project specifications and any special conditions attached thereto.
c. It is understood and agreed that all work shall be accomplished in strict compliance with
the provisions of the Contract Documents. It is understood and agreed by both the
County and the Contractor that any modifications or additions to this agreement shall be
made only by the full execution of the County's standard contract change order form.
Furthermore, it is understood and agreed by both parties that any work done by the
CONTRACTOR on any such modification or addition to this AGREEMENT prior to the
County's execution of its standard Contract Change Order form shall be at the total risk of
the CONTRACTOR and said work shall not be compensated by the County.
d. CONTRACTOR agrees to begin the work within ten (10) days of Notice to Proceed and
I-22
• that final completion shall be within ninety(70) calendar days of Notice to Proceed.
e. The parties agree that damages due to delay in completion of the work are uncertain and
not readily capable of ascertainment. Accordingly, if the CONTRACTOR shall fail to
complete the work or any part thereof within the time stipulated, or an applicable
extension thereof, the CONTRACTOR shall pay to the OWNER as fixed and agreed,
liquidated damages for each calendar day of delay until the delayed work is corrected or
accepted, an of $100 per day. The parties agree that this sum is proportionate to the
probable loss and is not a penalty.
(a) The CONTRACTOR expressly waives any defense as to the validity of any
liquidated damages stated in this Agreement as they may appear on the grounds that
such liquidated damages are void as penalties or are not reasonably related to actual
damages.
IN WITNESS WHEREOF, the parties hereto have executed and sealed this Agreement as of the day and
year first above written.
OWNER:County of Isle of Wight,Virginia
By:
County Administrator
CONTRACTOR:
By:
ATTEST:
By:
Title:
Approved as to form:
Mark C.Popovich,Isle of Wight County Attorney
PERFORMANCE BOND
(CONTRACT DOCUMENT TO BE COMPLETED AT TIME OF AWARD)
Bond No.
Amount: $
I-23
KNOW ALL PERSONS BY THESE PRESENTS,that
of ,hereinafter called the Contractor
and a corporation duly organized and existing under and by virtue of the laws of the
State of ,hereinafter called the Surety,and authorized to transact business within the
Commonwealth of Virginia as the Surety,are held and firmly bound unto Isle of Wight County,Virginia as Owner,
in the sum of dollars($ ),lawful money of the United
States of America,for payment of which,well and truly be made to the Owner,the Contractor and the Surety bind
themselves and each of their heirs,executors,administrators,successors,and assigns,jointly and severally,firmly
by these presents as follows:
THE CONDITION OF THE ABOVE OBLIGATION IS SUCH THAT:
WHEREAS,the Contractor has executed and entered into a certain Agreement,hereto attached,with the
Owner dated ,2016, for roof replacement as described in the bid titled Community
Development Building Low Slope Roof Replacement, IFB# 16-4110-01.
NOW THEREFORE, if the Contractor,and its successors and assigns,shall at all times duly,promptly,
and faithfully perform the Work and any alteration in or addition to the obligations of the Contractor
arising there under,including the matter of infringement,if any,of patents or other proprietary rights, and
shall assure all guarantees against defective workmanship and materials,including the guarantee period
following final completion by the Contractor and final acceptance by the Owner and comply with all the
covenants therein contained in the Specifications,Drawings, and other Contract Documents required to be
performed by the Contractor, in the manner and within the times provided in the Agreement,and shall
fully indemnify and save harmless the Owner from all costs and damage which it may suffer by reason or
failure to do so, and shall fully reimburse and repay it all outlay and expenses which it may incur in
making good any default,and reasonable counsel fees incurred in the prosecution of or defense of any
action arising out of or in connection with any such default,then this obligation shall be void; otherwise
to remain in full force and effect.
PROVIDED, HOWEVER,that the Surety, for value received,for itself and its successors and assigns,
hereby stipulates and agrees that no change, extension of time, alteration, or addition to the terms of the
Contract Documents or to the Work to be performed there under, or payment there under before the time
required therein, or waiver of any provision thereof, or assignment,subletting or transfer thereof or any
part thereof, shall in any way affect its obligation on this Bond,and it does hereby waive notice of any
such change, extension of time, alteration, addition to the terms of the Contract Documents or any such
payment,waiver,assignment, subcontract or transfer.
PROVIDED,FURTHER,that no final settlement between the Owner and the Contractor shall abridge the
right of any beneficiary hereunder,whose claim may be unsatisfied.
Whenever Contractor shall be declared by Owner to be in default under the Contract,the Owner having
performed Owner's obligations there under,the Owner shall have the right, at its option,to require the
Surety to promptly proceed to remedy the default within 30 days of notice by proceeding or procuring
others to proceed with completing the Agreement with its terms and conditions; and all reserves, deferred
payments, and other funds provided by the Agreement to be paid to Contractor shall be paid to Surety at
the same times and under the same conditions as by the terms of that Agreement such fund would have
been paid to Contractor had the Agreement been performed by Contractor; and Surety shall be entitled to
such funds in preference to any assignee of Principal of any adverse claimant.Notwithstanding the above,
the Owner shall have the right,with the approval of the Surety which shall not be unreasonably withheld,
to take over and assume completion of the Agreement and be promptly paid in cash by the Surety for the
cost of such completion less the balance of the Contract price.
I-24
IN WITNESS WHEREOF, all above parties bounded together have executed this instrument this
day of ,2016,the name and corporate seal of each corporate party being hereto affixed
and those presents duly signed by its undersigned representative,pursuant to authority of its governing
body.
CONTRACTOR
By: (Seal)
Name:
Title:
Attest
SURETY
By: (Seal)
Attest
APPROVED AS TO FORM: ,2016
Mark Popovich,County Attorney
NOTE:Date of Bond shall not be prior to the date of the Agreement. If the Contractor is a partnership,
all partners shall execute the Bond.
IMPORTANT:The Surety named on this Bond shall be one who is licensed to conduct business in the
Commonwealth of Virginia,and named in the current list of Companies Holding Certificates of Authority
as Acceptable Sureties on Federal Bonds and as Acceptable Reinsuring Companies, as published in
Circular 570(amended)by the Audit Staff Bureau of Accounts,U.S.Treasury Department. All Bonds
signed by an agent shall be accompanied by a certified copy of the authority to act for the Surety at the
time of signing of this Bond.
I-25
PAYMENT BOND
(CONTRACT DOCUMENT TO BE COMPLETED AT TIME OF AWARD)
Bond No.
Amount:
KNOW ALL PERSONS BY THESE PRESENTS, that of
hereinafter called the Contractor and , a
Corporation duly organized and existing under and by virtue of the laws of the State
, Virginia as the Surety, are held and firmly bound unto Isle of Wight
County, Virginia as Owner, in the sum of dollars
($ ), lawful money of the United States of America, for payment of which, well and truly
be made to the Owner, the Contractor and the Surety bind themselves and each of their heirs, executors,
administrators, successors,and assigns,jointly and severally, firmly by these presents as follows:
THE CONDITION OF THE ABOVE OBLIGATION IS SUCH THAT:
WHEREAS, the Contractor has executed and entered into a certain Agreement, hereto attached, with the
Owner dated , 2016, for roof replacement as described in the bid titled, Community
Development Building Low Slope Roof Replace,IFB# 16-4110-01.
NOW THEREFORE, if the Contractor shall promptly make payments to all persons, firms,
subcontractors, and corporations furnishing materials for or performing labor in the prosecution of the
Work provided for in the Agreement, and any authorized extension or modification thereof, including all
amounts due for materials, lubricants, oil, gasoline, repairs on machinery, equipment, and tools
consumed,used or rented in connection with the construction of the Work, and all insurance premiums on
the Work, and for all labor performed in the Work, whether by Subcontractor or otherwise, then this
obligation shall be void, otherwise to remain in full force and effect.
PROVIDED, HOWEVER, that the Surety, for value received, hereby stipulates and agrees that no
change, extension of time, alteration, or addition to the terms of the Contract Documents or to the Work
to be performed there under, shall in any way affect its obligation on this Bond, and it does hereby waive
notice of any such change, extension of time, alteration, or addition to the terms of the Contract
Documents.
PROVIDED, FURTHER,that no final settlement between the Owner and the Contractor shall abridge the
right of any beneficiary hereunder,whose claim may be unsatisfied.
IN WITNESS WHEREOF, all above parties bounded together have executed this instrument this
day of , 2016, the name and corporate seal of each corporate party being hereto affixed and
those presents duly signed by its undersigned representative,pursuant to authority of its governing body.
I-26
CONTRACTOR
By: (Seal)
Name:
Title:
Attest
SURETY
By:
Attest
APPROVED AS TO FORM: ,2016
Mark Popovich,County Attorney
NOTE: Date of Bond shall not be prior to the date of the Agreement. If the Contractor is a partnership,
all partners shall execute the Bond.
IMPORTANT: The Surety named on this Bond shall be one who is licensed to conduct business in the
Commonwealth of Virginia, and named in the current list of Companies Holding Certificates of Authority
as Acceptable Sureties on Federal Bonds and as Acceptable Reinsuring Companies, as published in
Circular 570 (amended) by the Audit Staff Bureau of Accounts, U.S. Treasury Department. All Bonds
signed by an agent shall be accompanied by a certified copy of the authority to act for the Surety at the
time of signing of this Bond.
I-27
Section C
(Drawings and Technical Specifications)
I-28
Local Roots,Global Reach
ISLE OF WIGHT
COUNTY,VIRGINIA
PROJECT MANUAL
FOR
COMMUNITY DEVELOPMENT BUILDING
LOW SLOPE ROOF REPLACEMENT
17146 MONUMENT CIRCLE
ISLE OF WIGHT, VIRGINIA
December 8, 2015
Hentz Engineering Project Number: 15116-110
Prepared By:
Hentz Engineering, Inc.
4 Pi Building Solutions
750 Lord Dunmore Drive,Suite 103 •Virginia Beach,VA 23464
Phone:(757)961-7224 Fax: (757)961-7641
www.hentzengineering.com
COMMUNITY DEVELOPMENT BUILDING
LOW SLOPE ROOF REPLACEMENT
TABLE OF CONTENTS
DIVISION 1-GENERAL REQUIREMENTS
01100 SUMMARY
01140 WORK RESTRICTIONS
01250 CONTRACT MODIFICATOIN PROCEDURES
01270 UNIT PRICES
01290 PAYMENT PROCEDURES
01310 PROJECT MANGEMENT AND COORDINATION
01320 CONSTRUCTION PROGRESS DOCUMENTATION
01330 SUBMITTAL PROCEDURES
01500 TEMPORARY FACILITIES AND CONTROLS
01610 MATERIAL STORAGE&HANDLING
01720 PROJECT RECORD DOCUMENTS
01750 WARRANTIES
01770 CLOSEOUT PROCEDURES
DIVISION 2-3 NOT USED
DIVISION 4- MASONRY
04520 MASONRY REPAIR
DIVISION 5 NOT USED
DIVISION 6-WOOD AND PLASTICS
06105 MISCELLANEOUS CARPENTRY
DIVISION 7-THERMAL AND MOISTURE PROTECTION
07311 ASPHALT SHINGLES
07531 EPDM MEMBRANE ROOFING
07591 MEMBRANE ROOFING PREPARATION/DEMOLITION
07620 SHEET METAL FLASHING AND TRIM
DIVISION 8-16 NOT USED
DRAWING INDEX
Community Development Building December 8,2015
SECTION 01100-SUMMARY
PART 1 -GENERAL
1.1 RELATED DOCUMENTS
A. Drawings and general provisions of the Contract, including General and Supplementary
Conditions and other Division 1 Specification Sections, apply to this Section.
B. Related Sections include the following:
1. Division 4, Section 04520"Masonry Repair"
2. Division 6, Section 06105 "Miscellaneous Carpentry"
3. Division 7, Section 07311 "Asphalt Shingles"
4. Division 7, Section 07531 "EPDM Membrane Roofing"
5. Division 7, Section 07591 "Membrane Roofing Preparation/Demolition"
6. Division 7, Section 07620"Sheet Metal Flashing and Trim"
1.2 WORK COVERED BY CONTRACT DOCUMENTS
A. Project Name: Community Development Building Low Slope Roof Replacement.
1. Project Location: 17146 Monument Circle,Isle Wight County,VA 23397
2. Owner: Isle of Wight County
B. Engineer Identification: The Contract Documents, dated December 8, 2015 which were
prepared for the Project by Hentz Engineering, Inc., 750 Lord Dunmore Drive Suite 103,
Virginia Beach,VA 23464.
1.3 WORK INCLUDED
A. This Section includes providing all labor, materials, equipment and supervision as outlined in
the Specifications and Drawings. The following is a summary description of the Project:
1. Remove and dispose of the existing theromoplastic roof systems on Roof Sections Al,
A2, A3, A4, B1 and B2 down to the metal roof deck. Work is to include the complete
removal and disposal of the existing roof membranes, flashings, insulation, gravel, wood
blocking (not shown to remain) and sheet metal flashing down to the existing deck. The
approximate roof areas are as follows:
• Roof Section Al -Approximately 3,500 SF(Metal Deck)
• Roof Section A2-Approximately 50 SF(Metal Deck)
• Roof Section A3 -Approximately 130 SF (Metal Deck)
• Roof Section A4-Approximately 80 SF (Metal Deck)
• Roof Section B1 -Approximately 700 SF (Metal Deck)
• Roof Section B2-Approximately 150 SF (Metal Deck)
SUMMARY 01100 - 1
Community Development Building December 8,2015
2. Provide a new fully adhered EPDM roof membrane system over new mechanically
attached polyisocyanurate insulation.
3. Provide new fully adhered EPDM membrane flashings, sheet metal flashings, plywood
sheathing and wood blocking as outlined in the Contract Documents.
4. Provide all necessary utility disconnects, reconnects and utility extensions needed to
complete the work.
5. Remove the existing asphalt shingles from the steep slope roof adjacent to Roof Section
Al as necessary to remove and replace the deteriorated tongue and groove deck boards
12 inches up from the roof eave. Provide new replacement tongue and groove decks
boards to match existing. Provide new self adhered underlayment.
6. Provide new through wall flashing at the masonry rising wall and Roof Section A2
interface as outlined in the Contract Documents.
7. Provide a 3 year contractor's warranty and a 20 year manufacture's roof system warranty.
1.4 USE OF PREMISES
A. General: Owner will occupy the facility during the Work, the Contractor shall coordinate the
Work which will impact the use of the facility with the Owners onsite personnel.
PART 2 -PRODUCTS (Not Used)
PART 3 -EXECUTION(Not Used)
END OF SECTION 01100
SUMMARY 01100 -2
Community Development Building December 8,2015
SECTION 01140-WORK RESTRICTIONS
PART 1 -GENERAL
1.1 RELATED DOCUMENTS
A. Drawings and general provisions of the Contract, including General and Supplementary
Conditions and other Division 1 Specification Sections,apply to this Section.
1.2 USE OF PREMISES
A. Use of Site: Limit use of premises to work in areas indicated. Do not disturb portions of site
beyond areas in which the Work is indicated.
1. Limits: Confine construction operations to the roof areas where work is to be performed.
2. Owner Occupancy: Allow for Owner occupancy of site.
3. Driveways and Entrances: Keep driveways and entrances serving premises clear and
available to Owner, Owner's employees, and emergency vehicles at all times. Do not use
these areas for parking or storage of materials.
a. Schedule deliveries to minimize use of driveways and entrances.
b. Schedule deliveries to minimize space and time requirements for storage of
materials and equipment on-site.
B. Use of Existing Building: Maintain existing building in a weathertight condition throughout
construction period. Repair damage caused by construction operations. Protect building and its
occupants during construction period.
1.3 CONSTRUCTION SEQUENCE
A. The removal and replacement of the existing roof systems above Roof Section Al and A3 is to
be scheduled first. Work on these roof sections will require the temporary removal of the
existing roof top HVAC unit and duct work. Removal of the existing HVAC unit and duct
work is to be performed by the Owner. The Contractor shall coordinate with the Owner for the
removal of the roof top HVAC unit. The Contractor shall provide all necessary temporary
flashings and tie-ins of the existing roof system once the roof top HVAC unit and duct work has
been removed.
1.4 OCCUPANCY REQUIREMENTS.
A. Full Owner Occupancy: Owner will occupy site and existing building during entire
construction period. Cooperate with Owner during construction operations to minimize
conflicts and facilitate Owner usage. Perform the Work so as not to interfere with Owner's
operations.
B. Access to the roof shall be limited to a ladder or temporary stairs from the exterior.
WORK RESTRICTIONS 01140- 1
Community Development Building December 8,2015
C. Owner reserves the right to postpone or delay contractor work schedule to accommodate
interior facility use.
D. The Contractor shall be solely responsible for supervising and directing the Work competently
and efficiently, devoting such attention thereto and applying such skills and expertise as may be
necessary to perform the Work in accordance with the Contract. The Contractor shall be solely
responsible for the means, methods, techniques, sequences and procedures of construction and
for coordinating all portions of the Work under the Contract, except where otherwise specified
in the Contract Documents. The Contractor is solely responsible to the Owner that the finished
Work complies with the Contract Documents.
E. The Contractor shall be solely responsible for health and safety precautions and programs for
workers and others in connection with the Work.No inspection by, knowledge on the part of, or
acquiescence by the Consultant, the Project Observer, the Owner, the Owner's employees and
agents, or any other entity whatever shall relieve the Contractor from its sole responsibility for
compliance with the requirements of the Contract or its sole responsibility for health and safety
programs and precautions.
PART 2 -PRODUCTS (Not Used)
PART 3 -EXECUTION(Not Used)
END OF SECTION 01140
WORK RESTRICTIONS 01140-2
Community Development Building December 8,2015
SECTION 01250 -CONTRACT MODIFICATION PROCEDURES
PART 1 -GENERAL
1.1 RELATED DOCUMENTS
A. Drawings and general provisions of the Contract, including General and Supplementary
Conditions and other Division 1 Specification Sections, apply to this Section.
1.2 SUMMARY
A. This Section specifies administrative and procedural requirements for handling and processing
Contract modifications.
1.3 PROPOSAL REQUESTS
A. Owner-Initiated Proposal Requests: Engineer will issue a detailed description of proposed
changes in the Work that may require adjustment to the Contract Sum or the Contract Time. If
necessary, the description will include supplemental or revised Drawings and Specifications.
1. Proposal Requests issued by Engineer are for information only. Do not consider them
instructions either to stop work in progress or to execute the proposed change.
2. Within time specified in Proposal Request after receipt of Proposal Request, submit a
quotation estimating cost adjustments to the Contract Sum and the Contract Time
necessary to execute the change.
a. Include a list of quantities of products required or eliminated and unit costs, with
total amount of purchases and credits to be made. If requested, furnish survey data
to substantiate quantities.
b. Indicate applicable taxes, delivery charges, equipment rental, and amounts of trade
discounts.
c. Include an updated Contractor's Construction Schedule that indicates the effect of
the change, including, but not limited to, changes in activity duration, start and
finish times, and activity relationship. Use available total float before requesting
an extension of the Contract Time.
B. Contractor-Initiated Proposals: If latent or unforeseen conditions require modifications to the
Contract,Contractor may propose changes by submitting a request for a change to the Engineer.
1. Include a statement outlining reasons for the change and the effect of the change on the
Work. Provide a complete description of the proposed change. Indicate the effect of the
proposed change on the Contract Sum and the Contract Time.
2. Include a list of quantities of products required or eliminated and unit costs, with total
amount of purchases and credits to be made. If requested, furnish survey data to
substantiate quantities.
3. Indicate applicable taxes, delivery charges, equipment rental, and amounts of trade
discounts.
CONTRACT MODIFICATION PROCEDURES 01250 - 1
Community Development Building December 8,2015
4. Include an updated Contractor's Construction Schedule that indicates the effect of the
change, including, but not limited to, changes in activity duration, start and finish times,
and activity relationship. Use available total float before requesting an extension of the
Contract Time.
C. Proposal Request Form: For Change Order proposals,use forms provided by Owner.
1.4 ALLOWANCES
A. Allowance Adjustment: To adjust allowance amounts, base each Change Order proposal on the
difference between purchase amount and the allowance, multiplied by final measurement of
work-in-place. If applicable, include reasonable allowances for cutting losses, tolerances,
mixing wastes,normal product imperfections,and similar margins.
1. Include installation costs in purchase amount only where indicated as part of the
allowance.
2. If requested, prepare explanation and documentation to substantiate distribution of
overhead costs and other margins claimed.
3. Submit substantiation of a change in scope of work, if any, claimed in Change Orders
related to unit-cost allowances.
4. Owner reserves the right to establish the quantity of work-in-place by independent
quantity survey,measure, or count.
B. Submit claims for increased costs because of a change in scope or nature of the allowance
described in the Contract Documents, whether for the Purchase Order amount or Contractor's
handling, labor, installation, overhead, and profit. Submit claims within 14 days of receipt of
the Change Order or Construction Change Directive authorizing work to proceed. Owner will
reject claims submitted later than 14 days after such authorization.
1.5 CHANGE ORDER PROCEDURES
A. On Owner's approval of a Proposal Request, Engineer will issue a Change Order for signatures
of Owner and Contractor on AIA Form G701 or on the Isle of Wight County Change Order
Form.
1.6 MINOR CHANGES IN THE WORK
A. Engineer will issue supplemental instructions authorizing Minor Changes in the Work, not
involving adjustment to the Contract Sum or the Contract Time, on AIA Document G710 Form.
1.7 CONSTRUCTION CHANGE DIRECTIVE
A. Construction Change Directive: Engineer may issue a Construction Change Directive on AIA
Form G714. Construction Change Directive instructs Contractor to proceed with a change in
the Work,for subsequent inclusion in a Change Order.
CONTRACT MODIFICATION PROCEDURES 01250 -2
Community Development Building December 8,2015
1. Construction Change Directive contains a complete description of change in the Work. It
also designates method to be followed to determine change in the Contract Sum or the
Contract Time.
B. Documentation: Maintain detailed records on a time and material basis of work required by the
Construction Change Directive.
1. After completion of change, submit an itemized account and supporting data necessary to
substantiate cost and time adjustments to the Contract.
PART 2-PRODUCTS (Not Used)
PART 3 -EXECUTION(Not Used)
END OF SECTION 01250
CONTRACT MODIFICATION PROCEDURES 01250-3
Community Development Building December 8,2015
SECTION 01270 -UNIT PRICES
PART 1 -GENERAL
1.1 RELATED DOCUMENTS
A. Drawings and general provisions of the Contract, including General and Supplementary
Conditions and other Division 1 Specification Sections,apply to this Section.
1.2 SUMMARY
A. This Section includes administrative and procedural requirements for unit prices.
B. Related Sections include the following:
1. Division 6, Section 06105 "Miscellaneous Carpentry"
1.3 DEFINITIONS
A. Unit price is an amount proposed by bidders, stated on the Bid Form, as a price per unit of
measurement for materials or services added to or deducted from the Contract Sum by
appropriate modification, if estimated quantities of Work required by the Contract Documents
are increased or decreased.
B. Board Foot (BF): A unit of measure equal to 144 cubic inches, calculated by measuring board
nominal thickness x nominal face width x length divided by 144. Example: 2 x 4 x 8 foot long
=(2"x 4"x 96")/ 144=5.33 board feet.
C. Square Foot (SF): A unit of measure equal to 144 square inches, calculated by the nominal
length x nominal width of an item
1.4 PROCEDURES
A. Unit prices include all necessary material, plus cost for delivery, installation, insurance,
applicable taxes, overhead,and profit.
B. Measurement and Payment: Refer to individual Specification Sections for work that requires
establishment of unit prices. Methods of measurement and payment for unit prices are specified
in those Sections.
C. Owner reserves the right to reject Contractor's measurement of work-in-place that involves use
of established unit prices and to have this work measured, at Owner's expense, by an
independent surveyor acceptable to Contractor.
UNIT PRICES 01270- 1
Community Development Building December 8,2015
D. List of Unit Prices: A list of unit rices is included at the end of this Section. Specification
P P
Sections referenced in the schedule contain requirements for materials described under each unit
price.
PART 2-PRODUCTS (Not Used)
PART 3 -EXECUTION
3.1 LIST OF UNIT PRICES
A. Unit Price No. 1 —Remove and replace deteriorated wood nailers/blocking.
1. Description: Provide a unit price to remove, dispose of and provide new wood
p P p P
nailers/blocking in accordance with specification Section 06105 "Miscellaneous
Carpentry".
2. Unit of Measurement: Board Foot Replaced.
B. Unit Price No. 2—Remove and replace deteriorated metal deck.
1. Description: Provide a unit price to remove, dispose of and provide new metal roof
decking and secure to framing. Decking shall match existing profile and grade.
2. Unit of Measurement: Square Foot Replaced.
END OF SECTION 01270
UNIT PRICES 01270-2
Community Development Building December 8,2015
SECTION 01290-PAYMENT PROCEDURES
PART 1 -GENERAL
1.1 RELATED DOCUMENTS
A. Drawings and general provisions of the Contract, including General and Supplementary
Conditions and other Division 1 Specification Sections,apply to this Section.
1.2 SUMMARY
A. This Section specifies administrative and procedural requirements necessary to prepare and
process Applications for Payment.
B. Related Sections include the following:
1. Division 1, Section 01250 "Contract Modification Procedures" for administrative
procedures for handling changes to the Contract.
2. Division 1, Section 01320 "Construction Progress Documentation" for administrative
requirements governing preparation and submittal of Contractor's Construction Schedule
and Submittals Schedule.
1.3 DEFINITIONS
A. Schedule of Values: A statement furnished by Contractor allocating portions of the Contract
Sum to various portions of the Work and used as the basis for reviewing Contractor's
Applications for Payment.
1.4 SCHEDULE OF VALUES
A. Coordination: Coordinate preparation of the Schedule of Values with preparation of
Contractor's Construction Schedule.
1. Correlate line items in the Schedule of Values with other required administrative forms
and schedules,including the following:
a. Application for Payment forms with Continuation Sheets.
b. Submittals Schedule.
2. Submit the Schedule of Values to Engineer at earliest possible date but no later than 14
days before the date scheduled for submittal of initial Applications for Payment.
B. Format and Content: Use the Project Manual table of contents as a guide to establish line items
for the Schedule of Values. Provide at least one line item for each Specification Section.
PAYMENT PROCEDURES 01290 - 1
Community Development Building December 8,2015
1. Identification: Include the following Project identification on the Schedule of Values:
a. Project name and location.
b. Name of Engineer.
c. Engineer's project number.
d. Contractor's name and address.
e. Date of submittal.
2. Arrange the Schedule of Values in tabular form with separate columns to indicate the
following for each item listed:
a. Related Specification Section or Division.
b. Description of the Work.
c. Change Orders(numbers)that affect value.
d. Dollar value.
1) Percentage of the Contract Sum to nearest one-hundredth percent, adjusted
to total 100 percent.
3. Provide a breakdown of the Contract Sum in enough detail to facilitate continued
evaluation of Applications for Payment and progress reports. Coordinate with the Project
Manual table of contents. Provide several line items for principal subcontract amounts,
where appropriate.
4. Round amounts to nearest whole dollar; total shall equal the Contract Sum.
5. Provide a separate line item in the Schedule of Values for each part of the Work where
Applications for Payment may include materials or equipment purchased or fabricated
and stored,but not yet installed.
a. Differentiate between items stored on-site and items stored off-site. Include
evidence of insurance or bonded warehousing if required.
6. Provide separate line items in the Schedule of Values for initial cost of materials,for each
subsequent stage of completion,and for total installed value of that part of the Work.
7. Each item in the Schedule of Values and Applications for Payment shall be complete.
Include total cost and proportionate share of general overhead and profit for each item.
a. Temporary facilities and other major cost items that are not direct cost of actual
work-in-place may be shown either as separate line items in the Schedule of
Values or distributed as general overhead expense, at Contractor's option.
8. Schedule Updating: Update and resubmit the Schedule of Values before the next
Applications for Payment when Change Orders or Construction Change Directives result
in a change in the Contract Sum.
1.5 APPLICATIONS FOR PAYMENT
A. Each Application for Payment shall be consistent with previous applications and payments as
certified by Engineer and paid for by Owner.
PAYMENT PROCEDURES 01290-2
Community Development Building December 8,2015
1. Initial Application for Payment, Application for Payment at time of Substantial
Completion,and final Application for Payment involve additional requirements.
B. Payment Application Times: The date for each progress payment is the 25 day of each month.
The period covered by each Application for Payment starts on the day following the end of the
preceding period.
C. Payment Application Forms: Use AIA Form G702 and G703 as forms for Applications for
Payment.
D. Application Preparation: Complete every entry on form. Notarize and execute by a person
authorized to sign legal documents on behalf of Contractor. Engineer will return incomplete
applications without action.
1. Entries shall match data on the Schedule of Values and Contractor's Construction
Schedule. Use updated schedules if revisions were made.
2. Include amounts of Change Orders and Construction Change Directives issued before last
day of construction period covered by application.
E. Transmittal: Submit three (3) signed and notarized original copies of each Application for
Payment to Engineer by a method ensuring receipt. One copy shall include waivers of lien and
similar attachments if required.
1. Transmit each copy with a transmittal form listing attachments and recording appropriate
information about application.
F. Waivers of Mechanic's Lien: With each Application for Payment, submit waivers of mechanic's
lien from every entity who is lawfully entitled to file a mechanic's lien arising out of the
Contract and related to the Work covered by the payment.
1. Submit partial waivers on each item for amount requested,before deduction for retainage,
on each item.
2. When an application shows completion of an item, submit final or full waivers.
3. Owner reserves the right to designate which entities involved in the Work must submit
waivers.
4. Submit final Application for Payment with or preceded by final waivers from every entity
involved with performance of the Work covered by the application who is lawfully
entitled to a lien.
5. Waiver Forms: Submit waivers of lien on forms, executed in a manner acceptable to
Owner.
G. Initial Application for Payment: Administrative actions and submittals that must precede or
coincide with submittal of first Application for Payment include the following:
1. List of subcontractors.
2. Schedule of Values.
3. Contractor's Construction Schedule(preliminary if not final).
4. Products list.
5. Submittals/Submittal Log.
6. Report of preconstruction conference.
7. Performance and payment bonds if required in the contract.
PAYMENT PROCEDURES 01290 -3
Community Development Building December 8,2015
H. Application for Payment at Substantial Completion: After issuing the Certificate of Substantial
Completion, submit an Application for Payment showing 100 percent completion for portion of
the Work claimed as substantially complete.
1. Include documentation supporting claim that the Work is substantially complete and a
statement showing an accounting of changes to the Contract Sum.
I. Final Payment Application: Submit final Application for Payment with releases and supporting
documentation not previously submitted and accepted, including, but not limited, to the
following:
1. Evidence of completion of Project closeout requirements.
2. Insurance certificates for products and completed operations where required and proof
that taxes,fees, and similar obligations were paid.
3. Updated final statement, accounting for final changes to the Contract Sum.
4. AIA Form G706A, "Contractor's Affidavit of Release of Liens"
PART 2 -PRODUCTS (Not Used)
PART 3 -EXECUTION(Not Used)
END OF SECTION 01290
PAYMENT PROCEDURES 01290-4
Community Development Building December 8,2015
SECTION 01310-PROJECT MANAGEMENT AND COORDINATION
PART 1 -GENERAL
1.1 RELATED DOCUMENTS
A. Drawings and general provisions of the Contract, including General and Supplementary
Conditions and other Division 1 Specification Sections,apply to this Section.
1.2 SUMMARY
A. This Section includes administrative provisions for coordinating construction operations on
Project including,but not limited to,the following:
1. General project coordination procedures.
2. Coordination Drawings.
3. Administrative and supervisory personnel.
4. Project meetings.
B. Each contractor shall participate in coordination requirements. Certain areas of responsibility
will be assigned to a specific contractor.
C. Related Sections: The following Sections contain requirements that relate to this Section:
1. Division 1 Section "Construction Progress Documentation" for preparing and submitting
the Contractor's Construction Schedule.
2. Division 1 Section"Closeout Procedures" for coordinating Contract closeout.
1.3 COORDINATION
A. Coordination: Coordinate construction operations included in various Sections of the
Specifications to ensure efficient and orderly installation of each part of the Work. Coordinate
construction operations, included in different Sections, that depend on each other for proper
installation, connection, and operation.
1. Schedule construction operations in sequence required to obtain the best results where
installation of one part of the Work depends on installation of other components, before
or after its own installation.
2. Coordinate installation of different components with other contractors to ensure
maximum accessibility for required maintenance, service, and repair.
3. Make adequate provisions to accommodate items scheduled for later installation.
B. If necessary, prepare memoranda for distribution to each party involved, outlining special
procedures required for coordination. Include such items as required notices, reports, and list of
attendees at meetings.
PROJECT MANAGEMENT AND COORDINATION 01310 - 1
Community Development Building December 8,2015
1. Prepare similar memoranda for Owner and separate contractors if coordination of their
Work is required.
C. Administrative Procedures: Coordinate scheduling and timing of required administrative
procedures with other construction activities and activities of other contractors to avoid conflicts
and to ensure orderly progress of the Work. Such administrative activities include, but are not
limited to,the following:
1. Preparation of Contractor's Construction Schedule.
2. Preparation of the Schedule of Values.
3. Installation and removal of temporary facilities and controls.
4. Delivery and processing of submittals.
5. Progress meetings.
6. Preinstallation conferences.
7. Project closeout activities.
1.4 SUBMITTALS
A. Staff Names: Within 14 days of starting construction operations, submit a list of principal staff
assignments,including superintendent and other personnel in attendance at Project site. Identify
individuals and their duties and responsibilities and provide a telephone number for each.
1.5 PROJECT MEETINGS
A. General: Schedule and conduct meetings and conferences at Project site, unless otherwise
indicated.
1. Attendees: Inform participants and others involved, and individuals whose presence is
required, of date and time of each meeting. Notify Owner and Engineer of scheduled
meeting dates and times.
2. Agenda: Prepare the meeting agenda. Distribute the agenda to all invited attendees.
3. Minutes: Record significant discussions and agreements achieved. Distribute the
meeting minutes to everyone concerned, including Owner and Engineer, within 3 days of
the meeting.
B. Preconstruction Conference: Schedule a preconstruction conference before starting
construction, at a time convenient to Owner and Engineer. Hold the conference at Project site
or another convenient location. Conduct the meeting to review responsibilities and personnel
assignments.
1. Attendees: Authorized representatives of Owner, Engineer and Contractor and its
superintendent; major subcontractors; manufacturers; suppliers; and other concerned
parties shall attend the conference. All participants at the conference shall be familiar
with Project and authorized to conclude matters relating to the Work.
2. Agenda: Discuss items of significance that could affect progress, including the
following:
a. Tentative construction schedule.
b. Phasing.
PROJECT MANAGEMENT AND COORDINATION 01310-2
Community Development Building December 8,2015
c. Critical work sequencing.
d. Designation of responsible personnel.
e. Procedures for processing field decisions and Change Orders.
f. Procedures for processing Applications for Payment.
g. Distribution of the Contract Documents.
h. Submittal procedures.
i. Preparation of Record Documents.
j. Use of the premises/restrictions.
k. Responsibility for temporary facilities and controls.
1. Parking availability.
m. Site laydown and storage areas.
n. Equipment deliveries and priorities.
o. First aid.
p. Security.
q. Progress cleaning.
r. Working hours.
C. Progress Meetings: Conduct progress meetings at monthly intervals. Coordinate dates of
meetings with preparation of payment requests.
1. Attendees: In addition to representatives of Owner and Engineer, each contractor,
subcontractor, supplier, and other entity concerned with current progress or involved in
planning, coordination, or performance of future activities shall be represented at these
meetings. All participants at the conference shall be familiar with Project and authorized
to conclude matters relating to the Work.
2. Agenda: Review and correct or approve minutes of previous progress meeting. Review
other items of significance that could affect progress. Include topics for discussion as
appropriate to status of Project.
a. Contractor's Construction Schedule: Review progress since the last meeting.
Determine whether each activity is on time, ahead of schedule, or behind schedule,
in relation to Contractor's Construction Schedule. Determine how construction
behind schedule will be expedited; secure commitments from parties involved to
do so. Discuss whether schedule revisions are required to ensure that current and
subsequent activities will be completed within the Contract Time.
b. Review present and future needs of each entity present, including the following:
1) Delivery requirements.
2) Sequence of operations.
3) Status of submittals.
4) Access.
5) Site utilization.
6) Temporary facilities and controls.
7) Work hours.
8) Hazards and risks.
9) Progress cleaning.
10) Quality and work standards.
11) Change Orders.
12) Documentation of information for payment requests.
PROJECT MANAGEMENT AND COORDINATION 01310 -3
it
Community Development Building December 8,2015
3. Reporting: Distribute minutes of the meeting to each party present and to parties who
should have been present. Include a brief summary, in narrative form, of progress since
the previous meeting and report.
a. Schedule Updating: Revise Contractor's Construction Schedule after each progress
meeting where revisions to the schedule have been made or recognized. Issue
revised schedule concurrently with the report of each meeting.
PART 2-PRODUCTS (Not Used)
PART 3 -EXECUTION(Not Used)
END OF SECTION 01310
PROJECT MANAGEMENT AND COORDINATION 01310-4
Community Development Building December 8,2015
SECTION 01320 -CONSTRUCTION PROGRESS DOCUMENTATION
PART 1 -GENERAL
1.1 RELATED DOCUMENTS
A. Drawings and general provisions of the Contract, including General and Supplementary
Conditions and other Division 1 Specification Sections,apply to this Section.
1.2 SUMMARY
A. This Section includes administrative and procedural requirements for documenting the progress
of construction during performance of the Work,including the following:
1. Contractor's Construction Schedule.
B. Related Sections include the following:
1. Division 1, Section 01290 "Payment Procedures".
2. Division 1, Section 01310 "Project Management and Coordination".
3. Division 1, Section 01330 "Submittal Procedures".
1.3 DESCRIPTION
A. Work Included:
1. To assure adequate planning and execution of the work so the work is completed within the
number of calendar days allowed in the contract, and to assist Consultant in evaluating
progress of the work, prepare and maintain the schedules and reports described in this
section.
B. Definition
1. "Day"used throughout the contract,unless otherwise stated means"calendar day.".
1.4 RELIANCE UPON APPROVED SCHEDULE
A. Should any activity not be completed within fifteen days after the stated scheduled date, Owner
shall have the right to order Contractor to expedite completion of the activity by whatever means
Owner deems appropriate and necessary,without additional compensation to Contractor.
B. Should any activity be 30 or more days behind schedule,the owner shall have the right to perform
the activity or have the activity performed by whatever method Owner deems appropriate.
C. Costs incurred by Owner in connection with expediting construction activity under this article shall
be reimbursed to Owner by Contractor.
CONSTRUCTION PROGRESS DOCUMENTATION 01320 - 1
Community Development Building December 8,2015
D. It is expressly understood and agreed that failure by Owner to exercise the option to either order
Contractor to expedite an activity or to expedite the activity by other means shall not be considered
precedent-setting for any other activities.
1.5 SUBMITTALS
A. Contractor's Construction Schedule: Submit three(3)printed copies to Engineer for review.
1.6 COORDINATION
A. Coordinate Contractor's Construction Schedule with the Schedule of Values, list of
subcontracts, Submittals Schedule, progress reports, payment requests, and other required
schedules and reports.
1. Secure time commitments for performing critical elements of the Work from parties
involved.
2. Coordinate each construction activity in the network with other activities and schedule
them in proper sequence.
PART 2 -PRODUCTS
2.1 CONTRACTOR'S CONSTRUCTION SCHEDULE, GENERAL
A. Time Frame: Extend schedule from date established for the Notice to Proceed to date of
Substantial Completion.
1. Contract completion date shall not be changed by submission of a schedule that shows an
early completion date,unless specifically authorized by Change Order.
B. Diagram:
1. Legibly in either a typed or ink format, graphically show the order and interdependence of
all activities necessary to complete the work,and the sequence in which each activity is to be
accomplished, as planned by Contractor and his project field superintendent in coordination
with all Subcontractors whose work is shown on the diagram.
2. The detail of information shall be such that duration times of activities shall be more than
one day. The selection and number of activities shall be subject to Owner's approval.
PART 3 -EXECUTION
3.1 CONTRACTOR'S CONSTRUCTION SCHEDULE
A. At the pre-construction meeting,present the completed construction schedule.
CONSTRUCTION PROGRESS DOCUMENTATION 01320 -2
Community Development Building December 8,2015
B. Contractor's Construction Schedule Updating: At monthly intervals, update schedule to reflect
actual construction progress and activities. Issue schedule one day before each regularly
scheduled progress meeting.
C. Distribution: Distribute copies of approved schedule to Engineer, Owner, separate contractors,
and other parties identified by Contractor with a need-to-know schedule responsibility.
When revisions are made, distribute updated schedules to the same parties.
END OF SECTION 01320
•
CONSTRUCTION PROGRESS DOCUMENTATION 01320 -3
Community Development Building December 8,2015
SECTION 01330-SUBMITTAL PROCEDURES
PART 1 -GENERAL
1.1 RELATED DOCUMENTS
A. Drawings and general provisions of the Contract, including General and Supplementary
Conditions and other Division 1 Specification Sections,apply to this Section.
1.2 SUMMARY
A. This Section includes administrative and procedural requirements for submitting Shop
Drawings,Product Data, Samples, and other miscellaneous submittals.
1.3 DEFINITIONS
A. Action Submittals: Written and graphic information that requires Engineer's responsive action.
B. Informational Submittals: Written information that does not require Engineer's approval.
Submittals may be rejected for not complying with requirements.
1.4 SUBMITTAL PROCEDURES
A. Manufacturers literature, certificates,warranties, schedule of values,color charts:
1. The Contractor shall submit four copies of the requested submittals to the Engineer for
review. The Engineer will process submittals within seven(7)days of receipt.
2. Submittals shall be clearly marked with the Project Name and clearly show which
portions of the contents is being submitted for review. The submittal shall be organized
into a single bound submittal package with an index of the items included. Submittals
that are not in the proper form or are incomplete will be returned without review.
B. Samples:
1. The Contractor shall submit three samples to the Engineer for review.
2. Samples shall be clearly marked with the Project name and clearly show the products
utilized to construct the Sample.
3. An approved sample shall be maintained on the project site throughout the duration of the
project.
1.5 SUBMITTAL SCHEDULE
A. Attached to this section is a Submittal Schedule. Contractor is to fully complete the attached
schedule and include with submittal package.
SUBMITTAL PROCEDURES 01330 - 1
Communi ty Development ve opment Building December 8,2015
PART 2-PRODUCTS (Not Used)
PART 3 -EXECUTION(Not Used)
END OF SECTION 01330
SUBMITTAL PROCEDURES 01330 -2
Community Development Building December 8,2015
SUBMITTAL SCHEDULE
Item Specification Section Contractors Initials l
Number Number Description Indicating Item is Reviewers Comments
Included
1 01290— 1.4- A Schedule of Values
2 01310 - 1.4-A Staff Names
3 01320 - 1.5 - A Construction Schedule
4 04520 -2.1 -A Face Brick Sample
5 04520 -2.2 -A Mortar
6 04520 -2.4 -A Self Adhering Flashing Membrane and Mastic
7 04520 -2.5 - A Termination Bar
8 04520 -2.7 - A Weeps
9 07311 -2.2 -A Self Adhered Underlayment
10 07311 -2.3 - A Fascia Intake Vent
11 07531 —2.2 -A EPDM Membrane
12 07531 —2.3 —C Bonding Adhesive Data Sheet
13 07531 —2.3 - D Membrane Seam Tape
14 07531 —2.3—E Lap Sealant Data Sheet
15 07531 —2.3 —F Water Cut-Off Sealant Data Sheet
16 07531 —2.3 —J Membrane Seam Plates &Fasteners
17 07531 —2.6—B,C,D Polyisocyanurate Insulation(Tapered/Flat)
18 07531 —2.4—A Roof Drain and Accessories
19 07531 —2.8—A Cable Fasteners
20 07531 —2.8—B Cone Vent and Base
21 07531 —2.8—C Cobra FasciaFlow
22 07531 — 1.5—B Insulation Board Fastening Pattern
23 07531 — 1.5—C Contractor Certification Letter from Roof
Manufacturer
24 07531 — 1.5—D Manufacturer Certification/Assembly Letter
25 07531 — 1.5 -E Qualification Data: For Installer and
Manufacturer
26 07531 — 1.5—F Product Test Reports
SUBMITTAL PROCEDURES 01330
Community Development Building December 8,2015
Item Specification Section Contractors Initials
Number Number Description Indicating Item is Reviewers Comments
Included
27 07531 — 1.5 —G Roof Maintenance Data
28 07531 - 1.5 - H Roofing Installer's &Manufacturer's Warranty
29 07591 — 1.6—A Photos/Video of Existing Damage
30 07620— 1.5 - B Aluminum Sheet Metal Data Sheet and Color
Chart
SUBMITTAL PROCEDURES 01330
Community Development Building December 8,2015
SECTION 01500 -TEMPORARY FACILITIES AND CONTROLS
PART 1 -GENERAL
1.1 RELATED DOCUMENTS
A. Drawings and general provisions of the Contract, including General and Supplementary
Conditions and other Division 1 Specification Sections,apply to this Section.
1.2 SUMMARY
A. This Section includes requirements for temporary facilities and controls, including temporary
utilities, support facilities, and security and protection facilities.
B. Temporary utilities include,but are not limited to,the following:
1. Water service and distribution.
2. Sanitary facilities,including toilets and wash facilities.
3. Electric power service.
C. Support facilities include,but are not limited to,the following:
1. Project identification and temporary signs.
2. Waste disposal facilities.
3. Lifts and hoists.
4. Temporary stairs.
5. Construction aids and miscellaneous services and facilities.
D. Security and protection facilities include,but are not limited to,the following:
1. Environmental protection.
2. Stormwater control.
3. Tree and plant protection.
4. Site enclosure fence.
5. Security enclosure and lockup.
6. Barricades,warning signs,and lights.
7. Covered walkways.
8. Temporary enclosures.
9. Temporary partitions.
10. Fire protection.
1.3 USE CHARGES
A. General: Cost or use charges for temporary facilities are not chargeable to Owner or Engineer
and shall be included in the Contract Sum. Allow other entities to use temporary services and
facilities without cost,including,but not limited to,the following:
TEMPORARY FACILITIES AND CONTROLS 01500- 1
Community Development Building December 8,2015
1. Owner's construction forces.
2. Occupants of Project.
3. Engineer.
4. Testing agencies.
5. Personnel of authorities having jurisdiction.
B. Water Service: Pay water service use charges, whether metered or otherwise, for water used by
all entities engaged in construction activities at Project site.
C. Electric Power Service: Use electric power from Owner's existing system without metering and
without payment of use charges.
1.4 PROJECT CONDITIONS
A. Conditions of Use: The following conditions apply to use of temporary services and facilities
by all parties engaged in the Work:
1. Keep temporary services and facilities clean and neat.
2. Relocate temporary services and facilities as required by progress of the Work.
3. Make all required connections to existing utility systems with minimum disruption to
services in the existing utility systems. When disruption of the existing service is
required, do not proceed without the Owner's approval and, when required, provide
alternate temporary service.
PART 2 -PRODUCTS
2.1 MATERIALS
A. General: All temporary facilities shall be subject to the Owner's approval.
2.2 ELECTRICAL FACILITIES •
A. The contractor shall make arrangements with the Owner to connect into the existing electrical
service for temporary power. Contractor shall provide all temporary wiring and upon
completion of the work, remove such temporary facility. If electrical power is not available by
Owner, Contractor shall provide temporary power.
B. Unless otherwise designated by the Owner, the circuit provided for the Contractors use shall be
limited to 110 volts for the operation of hand power tools and small machines.
C. Runs of the temporary power lines to the construction area shall not pass through areas of the
facility open to the patrons of the Owner. These lines shall have adequate safety protection
against harm to personnel and property.
TEMPORARY FACILITIES AND CONTROLS 01500 -2
Community Development Building December 8,2015
2.3 WATER FACILITIES
A. The Contractor shall designate a source for construction water and shall pay the cost of water
used for construction purposes.
B. The Contractor shall provide temporary connections to the water source and all piping, fittings,
and hoses required to extend the water supply to the work area, and remove same at the
completion of the project.
2.4 SANITARY FACILITIES
A. Contractor shall provide temporary sanitary facilities in the quantity required, for use of all
personnel. Maintain in a sanitary condition at all times.
B. Locate temporary sanitary facilities in the area designated by the Owner.
2.5 ENCLOSURES
A. Contractor shall provide and maintain for the duration of the project all required scaffolds,
tarpaulins, barricades, warning signs, steps, ramps, bridges, platforms and other temporary
construction necessary for proper completion of the work in compliance with all safety
regulations and local codes.
B. Contractor is responsible for the structural integrity of all temporary construction. Temporary
construction shall meet all pertinent safety regulations.
2.6 FENCING OF THE CONSTRUCTION AREA
A. Contractor shall provide temporary traffic barricades, directional arrows, signs and caution tape
as directed by the Owner and in compliance with all safety regulations and local codes around
all ground located equipment and materials.
2.7 EXTERIOR PROTECTION
A. The Contractor shall provide and maintain ballasted reinforced polyethylene or canvas tarps
over all exterior walls where equipment, material and/or debris is required to be raised or
lowered from various roof elevations or from roof elevations to the designated staging areas
during the construction project.
B. The Contractor shall be responsible for the cleaning of all wall surfaces and adjacent building
components which are scheduled to remain which have been soiled during the construction
project. The cleaning shall be performed to the satisfaction of the Owner.
C. Walls and adjacent building components scheduled to remain which cannot be cleaned to the
satisfaction of the Owner shall be sandblasted, repainted, repaired or replaced at no additional
cost to the Owner.
TEMPORARY FACILITIES AND CONTROLS 01500-3
Community Development Building December 8,2015
2.8 GROUND PROTECTION
A. The contractor shall provide ground protection as necessary in all material storage areas, staging
areas,dumpster locations and along all haul routes that may exist between these areas.
B. All parking lot paving materials, sidewalks, curbs, walls, fences, windows, HVAC units, etc.
located in any material storage areas, staging areas and along all haul routes that may exist
between these areas shall be protected.
C. Any and all of the property on the ground which is damaged during the construction project
shall be repaired or replaced at no additional cost to the Owner. Lanscaping including grass
areas shall be restored to Owners satisfaction. Contractor shall grade and provide new sod in all
grass areas disturbed during construction.
D. Photographic documentation of any existing deficiencies on the roof, building surfaces, or on
the ground is recommended prior to beginning any Work. The Contractor shall be responsible
for documenting and providing the Owner documentation of all damages prior to beginning
work.
2.9 PROTECTION OF ROOF SURFACES
A. 15/32" oriented strand board or plywood and 1" extruded polystyrene insulation for use over
finished roofing surfaces.
PART 3 -EXECUTION
3.1 TEMPORARY UTILITY INSTALLATION
A. Water Service: Install water service and distribution piping in sizes and pressures adequate for
construction.
B. Sanitary Facilities: Provide temporary toilets and wash facilities. Comply with regulations and
health codes for type,number,location, operation, and maintenance of fixtures and facilities.
1. Disposable Supplies: Provide toilet tissue, paper towels and similar disposable materials
for each facility. Maintain adequate supply. Provide covered waste containers for
disposal of used material.
2. Toilets: Install self-contained toilet units. Shield toilets to ensure privacy.
C. Electric Power Service: Use of Owner's existing electric power service will be permitted, as
long as equipment is maintained in a condition acceptable to Owner.
3.2 SUPPORT FACILITIES INSTALLATION
A. General: Comply with the following:
1. Locate storage sheds, sanitary facilities, and other temporary construction and support
facilities for easy access.
TEMPORARY FACILITIES AND CONTROLS 01500-4
Community Development Building December 8,2015
2. Provide incombustible construction for offices, shops, and sheds located within
construction area or within 30 feet of building lines. Comply with NFPA 241.
3. Maintain support facilities until near Substantial Completion. Remove before Substantial
Completion. Personnel remaining after Substantial Completion will be permitted to use
permanent facilities,under conditions acceptable to Owner.
B. Waste Disposal Facilities: Provide waste-collection containers in sizes adequate to handle
waste from construction operations. Containerize and clearly label hazardous, dangerous, or
unsanitary waste materials separately from other waste.
C. Temporary Stairs: Provide temporary stairs to access roof from the exterior.
3.3 PROTECTION FACILITIES INSTALLATION
A. Environmental Protection: Provide protection, operate temporary facilities, and conduct
construction in ways and by methods that comply with environmental regulations and that
minimize possible air, waterway, and subsoil contamination or pollution or other undesirable
effects. Avoid using tools and equipment that produce harmful noise. Restrict use of
noisemaking tools and equipment to hours that will minimize complaints from persons or firms
near Project site.
B. Barricades, Warning Signs, and Lights: Comply with standards and code requirements for
erecting structurally adequate barricades. Paint with appropriate colors, graphics, and warning
signs to inform personnel and public of possible hazard. Where appropriate and needed,
provide lighting,including flashing red or amber lights.
C. Covered Walkway: Erect a structurally adequate, protective, covered walkway for passage of
persons along'adjacent public streets and sidewalks. Coordinate with entrance gates, other
facilities,and obstructions. Comply with regulations of authorities having jurisdiction.
1. Construct covered walkways using scaffold or shoring framing.
2. Provide wood-plank overhead decking, protective plywood enclosure walls, handrails,
barricades, warning signs, lights, safe and well-drained walkways, and similar provisions
for protection and safe passage.
3. Paint and maintain in a manner approved by Owner and Engineer.
3.4 OPERATION,TERMINATION,AND REMOVAL
A. Supervision: Enforce strict discipline in use of temporary facilities. To minimize waste and
abuse,limit availability of temporary facilities to essential and intended uses.
B. Maintenance: Maintain facilities in good operating condition until removal. Protect from
damage caused by freezing temperatures and similar elements.
C. Termination and Removal: Remove each temporary facility when need for its service has
ended, when it has been replaced by authorized use of a permanent facility, or no later than
Substantial Completion. Complete or, if necessary, restore permanent construction that may
have been delayed because of interference with temporary facility. Repair damaged Work,
clean exposed surfaces,and replace construction that cannot be satisfactorily repaired.
TEMPORARY FACILITIES AND CONTROLS 01500 -5
Community Development Building December 8,2015
3.5 ROOF PROTECTION
A. Protection of Existing Roofing
1. Roof Membrane Protection
a. Roof membrane protection shall be provided and installed at all areas where
materials, equipment and/or debris will be transported across roof sections that are
scheduled to remain or on newly replaced roof sections.
b. Roof membrane protection is also required under all equipment, scaffolding,ramps
and/or ladders required to complete the work.
c. Roof membrane protection is also required under all materials, tool boxes, or
equipment stored on the roof membrane surfaces.
d. Plywood shall be fully supported by foam insulation board over 100% of the
surface of the plywood.
e. Roof membrane protection shall be a minimum of 4 feet in width.
f. Roof membrane protection shall be in place prior to the start of the roof demolition
work.
g. Contractor shall inspect, maintain and secure the membrane protection on a daily
basis throughout the course of the project.
h. Maintain all roof membrane protection as long as needed for the safe and proper
completion of the work. Remove all such roof membrane protection as rapidly as
progress of the work will permit, or as directed by the consultant.
i. The Contractor shall be responsible for the repair of damages to the existing
remaining roofs,or the replacement roof systems,as a result of construction.
3.6 Protection of Replacement Roofing
A. Traffic over any replaced roof area shall be limited to light foot traffic only. No hauling of
heavy materials or storage of materials over these areas will be allowed unless membrane
protection is provided.
B. The contractor shall be responsible for the replacement of any damaged roof system
materials,metal flashing components and/or related roof insulation as a result of traffic
END OF SECTION 01500
TEMPORARY FACILITIES AND CONTROLS 01500-6
Community Development Building December 8,2015
SECTION 01610-MATERIAL STORAGE AND HANDLING
PART 1 -GENERAL
1.1 RELATED DOCUMENTS
A. Drawings and general provisions of the Contract, including General and Supplementary
Conditions and other Division 1 Specification Sections, apply to this Section.
B. Related Sections include the following:
1. Division 4, Section 04520"Masonry Repair"
2. Division 6, Section 06105 "Miscellaneous Carpentry"
3. Division 7, Section 07311 "Asphalt Shingles"
4. Division 7, Section 07531 "EPDM Membrane Roofing"
5. Division 7, Section 07591 "Membrane Roofing Preparation/Demolition"
6. Division 7, Section 07620"Sheet Metal Flashing and Trim"
1.2 SUMMARY
A. This Section specifies provisions governing the delivery, storage and handling of equipment
and materials required to complete the Work include,but are not limited to:
1. Ground staging and storage areas for materials and equipment.
2. Rooftop storage of materials and equipment.
3. Handling and protection of materials to be incorporated into the roof system.
PART 2-PRODUCTS (Not Used)
PART 3 - EXECUTION
3.1 PRODUCT DELIVERY, STORAGE AND HANDLING—GENERAL
A. Protection
1. Use all means to protect the materials to be included in the Work before, during, and
after installation and to protect the work and materials of all other trades.
B. Delivery and Storage
1. Deliver materials to the job site in original, unopened containers no sooner than thirty
(30)days prior to start of job.
a. Materials and equipment are to be stored in the areas designated by the Owner.
MATERIAL STORAGE AND HANDLING 01610-2
Community Development Building December 8,2015
b. Protection of materials and equipment stored on the job site from theft, damage or
other loss is the sole responsibility of the Contractor. Contractor shall replace all
lost, stolen or damaged materials,necessary for the proper completion of the work,
at no cost to the Owner.
2. Materials to be incorporated into the roof system shall be stored up off of the roof deck
or ground, and covered with weatherproof coverings anchored sufficiently so as to resist
wind blow off. Materials damaged due to blown off coverings shall be replaced by the
Contractor at no cost to the Owner.
3. When storing materials on the roof, do not overstress the roof deck. Materials shall not
be stored within 12 feet from any perimeter edge of the roof.
4. Storage of materials at the ground level shall be in an area designated by the Owner.
Building access must be maintained at all times. Contractor shall provide a temporary
chain link fence enclosure around all materials and equipment stored at the ground level.
3.2 STORAGE OF WOOD PRODUCTS
A. All wood products to be incorporated into the work shall be stored a minimum of 6" off of the
ground or roof surface and secured together with rope, wire or twine to prevent materials from
being blown around the site.
B. All wood products shall be covered with breathable canvas tarps securely fastened or weighted
in place to prevent blow off of the tarps.
END OF SECTION 01610
MATERIAL STORAGE AND HANDLING 01610 -3
Community Development Building December 8,2015
SECTION 01720—PROJECT RECORD DOCUMENTS
•
PART 1 -GENERAL
1.1 RELATED DOCUMENTS
A. Drawings and general provisions of the Contract, including General and Supplementary
Conditions and other Division 1 Specification Sections, apply to this Section.
B. Related Sections include the following:
1. Division 4, Section 04520"Masonry Repair"
2. Division 6, Section 06105 "Miscellaneous Carpentry"
3. Division 7, Section 07311 "Asphalt Shingles"
4. Division 7, Section 07531 "EPDM Membrane Roofing"
5. Division 7, Section 07591 "Membrane Roofing Preparation/Demolition"
6. Division 7, Section 07620"Sheet Metal Flashing and Trim"
1.2 SUMMARY
•
A. This Section includes administrative and procedural requirements governing project record
documents.
1.3 DESCRIPTION
A. Throughout the work of this contract,maintain an accurate record of the following
1. Contract documents (project manual with shop drawings).
2. Addendum.
3. Change orders and other modifications to the contract.
4. Field orders and instructions.
5. Construction schedule.
6. Product samples.
7. Progress reports.
1.4 QUALITY ASSURANCE
A. Delegate the responsibility for maintenance of record documents to one person on the
contractor's staff as approved in advance by the owner.
B. Make all entries within 24 hours after receipt of information.
PROJECT RECORD DOCUMENTS 01720 - 1
Community Development Building December 8,2015
1.5 PRODUCT HANDLING
A. Maintain the job set of record documents completely protected from deterioration and from loss
and damage until completion of the work and transfer of the recorded data to the final record
documents.
PART 2-PRODUCTS
2.1 RECORD DOCUMENTS
A. Secure from the Owner at the pre-construction meeting, at no charge to the Contractor, one
complete set of all documents comprising the contract.
PART 3 -EXECUTION
3.1 MAINTENANCE OF RECORD DOCUMENTS
A. Upon receipt of record documents described above, identify each of the documents with the
title "Project Record Documents".
B. Maintain the record documents at the job site. Documents shall be available to the Owner and
Engineer during all working hours.
C. The Contractor shall use record document set to record day by day "as built" information.
Where the drawings are diagrammatic, such drawings shall be corrected or redrawn to show
actual installation.
D. During the phase of construction, if required by the Engineer, Contractor shall obtain a set of
prints from the Engineer without cost and shall, in a neat and legible manner,transfer"as built"
information from the record set.
3.2 REVIEW AND APPROVAL
A. Submit the completed total set of record documents to the Engineer for review. Participate in
review meeting or meetings as required by the Engineer, make all required changes in the
documents and promptly deliver the final project record documents through the Engineer to the
Owner.
END OF SECTION 01720
PROJECT RECORD DOCUMENTS 01720-2
Community Development Building December 8,2015
SECTION 01750-WARRANTIES
PART 1 -GENERAL
1.1 RELATED DOCUMENTS
A. Drawings and general provisions of the Contract, including General and Supplementary
Conditions and other Division 1 Specification Sections,apply to this Section.
B. Related Sections include the following:
1. Division 4, Section 04520"Masonry Repair"
2. Division 6, Section 06105 "Miscellaneous Carpentry"
3. Division 7, Section 07311 "Asphalt Shingles"
4. Division 7, Section 07531 "EPDM Membrane Roofing"
5. Division 7, Section 07591 "Membrane Roofing Preparation/Demolition"
6. Division 7, Section 07620"Sheet Metal Flashing and Trim"
1.2 SUMMARY
A. This Section includes administrative and procedural requirements for Warranties.
1.3 PROCEDURES
A. The following items are to be submitted to the Engineer as part of this Section. -
1. Contractor's written three(3)year guarantee covering all materials and workmanship.
2. Provide manufacturer's twenty year (20) year, no dollar limit labor-and-material
warranty to Owner for the new EPDM membrane roofing system installed. Warranty
shall include coverage for storms with wind speeds of up to 72 mph.
3. Provide manufacturer's standard material warranty's for all other products.
4. A report from the membrane manufacturer's representative indicating that the roof has
been inspected and is suitable for warranty. Include a copy of the manufacturer's punch
list, if any. Owner must be present during the inspection.
1.4 SPECIAL WARRANTIES
A. The Contractor warrants that, unless otherwise specified, all materials and equipment
incorporated in the Work under the Contract shall be new and in compliance with the
Submittals and the Contract Documents. The Contractor further warrants that all workmanship
shall be of the highest quality and in accordance with best industry practices and the Contract
Documents and shall be performed by persons qualified at their respective trades.
WARRANTIES 01750- 1
Community Development Building December 8,2015
B. Work not conforming to these warranties shall be considered Defective.
C. This warranty of materials and workmanship is separate and independent from and in addition
to any of the Contractor's and system manufacturer's other guarantees or obligations in the
Contract or under relevant State law.
PART 2 -PRODUCTS (Not Used)
PART 3 -EXECUTION
3.1 Submit all required documentation upon completion of the Work and prior to final payment.
3.2 All warranties are to be submitted to the Owner,through the Engineer.
END OF SECTION 01750
WARRANTIES 01750-2
Community Development Building December 8,2015
SECTION 01770-CLOSEOUT PROCEDURES
PART 1 -GENERAL
1.1 RELATED DOCUMENTS
A. Drawings and general provisions of the Contract, including General and Supplementary
Conditions and other Division 1 Specification Sections,apply to this Section.
B. Related Sections include the following:
1. Division 4, Section 04520"Masonry Repair"
2. Division 6, Section 06105"Miscellaneous Carpentry"
3. Division 7, Section 07311 "Asphalt Shingles"
4. Division 7, Section 07531 "EPDM Membrane Roofing"
5. Division 7, Section 07591 "Membrane Roofing Preparation/Demolition"
6. Division 7, Section 07620"Sheet Metal Flashing and Trim"
1.2 SUMMARY
A. This Section includes administrative and procedural requirements for contract closeout,
including,but not limited to,the following:
1. Inspection procedures.
2. Warranties.
3. Final cleaning.
1.3 SUBSTANTIAL COMPLETION
A. Preliminary Procedures: Before requesting inspection for determining date of Substantial
Completion, complete the following.
1. Prepare a list of items to be completed and corrected(punch list),the value of items on the
list,and reasons why the Work is not complete.
2. Advise Owner of pending insurance changeover requirements.
3. Submit specific warranties, workmanship bonds, maintenance service agreements, final
certifications, and similar documents.
4. Terminate and remove temporary facilities from Project site, along with mockups,
construction tools,and similar elements.
5. Complete final cleaning requirements.
6. Touch up and otherwise repair and restore marred exposed finishes to eliminate visual
defects.
B. Inspection: Submit a written request for inspection for Substantial Completion. On receipt of
request, Engineer will either proceed with inspection or notify Contractor of unfulfilled
requirements. Engineer will prepare the Certificate of Substantial Completion after inspection
CLOSEOUT PROCEDURES 01770- 1
Community Development Building December 8,2015
or will notify Contractor of items, either on Contractor's list or additional items identified by
Engineer,that must be completed or corrected before certificate will be issued.
1. Re-inspection: Request re-inspection when the Work identified in previous inspections as
incomplete is completed or corrected.
2. Results of completed inspection will form the basis of requirements for Final Completion.
1.4 FINAL COMPLETION
A. Preliminary Procedures: Before requesting final inspection for determining date of Final
Completion,complete the following:
1. Submit a final Application for Payment.
2. Submit certified copy of Engineer's Substantial Completion inspection list of items to be
completed or corrected (punch list), endorsed and dated by Engineer. The certified copy
of the list shall state that each item has been completed or otherwise resolved for
acceptance.
B. Inspection: Submit a written request for final inspection for acceptance. On receipt of request,
Engineer will either proceed with inspection or notify Contractor of unfulfilled requirements.
Engineer will prepare a final Certificate for Payment after inspection or will notify Contractor
of construction that must be completed or corrected before certificate will be issued.
1. Re-inspection: Request re-inspection when the Work identified in previous inspections as
incomplete is completed or corrected.
1.5 LIST OF INCOMPLETE ITEMS (PUNCH LIST)
A. Preparation: Submit three (3) copies of list. Include name and identification of each space and
area affected by construction operations for incomplete items and items needing correction
including,if necessary, areas disturbed by Contractor that are outside the limits of construction.
1. Organize list of spaces in sequential order.
2. Include the following information at the top of each page:
a. Project name.
b. Date.
c. Name of Engineer.
d. Name of Contractor.
e. Page number.
1.6 WARRANTIES
A. Submit written warranties for the Work where commencement of warranties other than date of
Substantial Completion is indicated.
CLOSEOUT PROCEDURES 01770-2
Community Development Building December 8,2015
PART 2-PRODUCTS
2.1 MATERIALS
A. Cleaning Agents: Use cleaning materials and agents recommended by manufacturer or
fabricator of the surface to be cleaned. Do not use cleaning agents that are potentially
hazardous to health or property or that might damage finished surfaces.
PART 3 -EXECUTION
3.1 FINAL CLEANING
A. General: Provide final cleaning. Conduct cleaning and waste-removal operations to comply
with local laws and ordinances and Federal and local environmental and antipollution
regulations.
1. Cleaning: Complete the following cleaning operations before requesting inspection for
certification of Substantial Completion:
a. Clean Project site,yard, and grounds, in areas disturbed by construction activities,
including landscape development areas, of rubbish,waste material, litter, and other
foreign substances.
b. Sweep paved areas broom clean. Remove petrochemical spills, stains, and other
foreign deposits.
c. Rake grounds that are neither planted nor paved to a smooth, even-textured
surface.
d. Remove tools, construction equipment, machinery, and surplus material from
Project site.
e. Remove labels that are not permanent.
B. Comply with safety standards for cleaning. Do not bum waste materials. Do not bury debris or
excess materials on Owner's property. Do not discharge volatile, harmful, or dangerous
materials into drainage systems. Remove waste materials from Project site and dispose of
lawfully.
END OF SECTION 01770
CLOSEOUT PROCEDURES 01770-3
Community Development Building December 8,2015
SECTION 04520—MASONRY REPAIR
PART 1 -GENERAL
1.1 RELATED DOCUMENTS
A. Drawings and general provisions of the Contract, including General and Supplementary
Conditions and Division 1 Specification Sections, apply to this Section.
1.2 SUMMARY
A. This Section includes providing all labor, materials, equipment and supervision as outlined in
the Specifications and Drawings. The following is a brief description of the Work:
1. Removal of existing masonry units as required to facilitate the installation of new through
wall flashing above Roof Section B.
B. Related Sections include the following:
1. Division 7, Section 07531 "EPDM Membrane Roofing"
2. Division 7, Section 07591 "Membrane Roofing Preparation/Demolition"
3. Division 7, Section 07620"Sheet Metal Flashing and Trim"
1.3 SUBMITTALS
A. Product Data: For each type of product indicated. Include brick and mortar samples for owner
approval.
1.4 QUALITY ASSURANCE
A. Restoration Specialist Qualifications: Engage an experienced masonry restoration and cleaning
firm to perform work of this Section. Firm shall have completed work similar in material,
design, and extent to that indicated for this Project with a record of successful in-service
performance.
B. Restoration Worker Qualifications: Persons who are experienced in restoration work of types
they will be performing.
C. Source Limitations: Obtain each type of material for masonry restoration (face brick, cement,
sand, etc.) from one source with resources to provide materials of consistent quality in
appearance and physical properties.
MASONRY REPAIR 04520 - 1
Community Development Building December 8,2015
1.5 DELIVERY, STORAGE,AND HANDLING
A. Deliver masonry units to Project site strapped together in suitable packs or pallets or in heavy-
duty cartons.
B. Deliver other materials to Project site in manufacturer's original and unopened containers,
labeled with manufacturer's name and type of products.
C. Store cementitious materials on elevated platforms, under cover, and in a dry location. Do not
use cementitious materials that have become damp.
D. Store sand where grading and other required characteristics can be maintained and
contamination avoided.
1.6 PROJECT CONDITIONS
A. Repair masonry only when air temperature is between and 40 and 90 deg F and is predicted to
remain so for at least 7 days after completion of work.
B. Cold-Weather Requirements: Comply with the following procedures for masonry repair and
mortar joint pointing:
1. When air temperature is below 40 deg F, heat mortar ingredients, masonry repair
materials, and existing masonry walls to produce temperatures between 40 and
120 deg F.
2. When mean daily air temperature is below 40 deg F, provide enclosure and heat to
maintain temperatures above 32 deg F within the enclosure for 7 days after repair and
pointing.
C. Hot-Weather Requirements: Protect masonry repair and mortar joint pointing when
temperature and humidity conditions produce excessive evaporation of water from mortar and
repair materials. Provide artificial shade and wind breaks and use cooled materials as required.
Do not apply mortar to substrates with temperatures of 90 deg F and above.
D. Patch masonry only when air and surface temperatures are between and 55 and 100 deg F and
are predicted to remain above 55 deg F for at least 7 days after completion of work. On days
when air temperature is predicted to go above 90 deg F, schedule patching work to coincide
with time that surface being patched will be in shade or during cooler morning hours.
E. Clean masonry surfaces only when air temperature is 40 deg F and above and is predicted to
remain so for at least 7 days after completion of cleaning.
1.7 SEQUENCING AND SCHEDULING
A. Order replacement materials at earliest possible date, to avoid delaying completion of the Work.
B. Take delivery of and store at Project site a sufficient quantity of sand to complete Project.
C. Perform all work required for masonry flashing installation prior to installation of new roof
system.
MASONRY REPAIR 04520 -2
Community Development Building December 8,2015
PART 2-PRODUCTS
2.1 MASONRY MATERIALS
A. Face Brick: Provide face brick and accessories where required to complete masonry work.
1. Provide units with colors, surface texture, size, and shape to match existing brickwork
- and with physical properties not less than those determined from preconstruction testing
of selected existing units.
a. For existing brickwork that exhibits a range of colors, provide brick that matches
that range rather than brick that matches an individual color within that range.
2.2 MORTAR MATERIALS
A. Masonry Mortar shall be proportioned in accordance with ASTM C270 to match the color of
the existing mortar and consist of one of the following:
1. Ready mix pre-colored masonry cement with the physical properties specified in ASTM
C91,Type N
2. Masonry sand conforming to ASTM C144
3. Potable water.
2.3 CLEANING MATERIALS
A. Water for Cleaning: Potable.
B. Mild Acidic Cleaner: Manufacturer's standard mildly acidic cleaner containing no hydrochloric,
hydrofluoric, or sulfuric acid; or chlorine bleaches.
1. Products:
a. Diedrich Technologies Inc.; Envirorestore 100.
b. Dominion Restoration, Inc.; DR-60 Stone and Masonry Cleaner.
c. Dumond Chemicals, Inc.; Safe n'Easy Heavy Duty Restoration Cleaner.
d. ProSoCo; Sure Klean Light-Duty Restoration Cleaner.
e. Approved equal
MASONRY REPAIR 04520 -3
Community Development Building December 8,2015
2.4 SELF ADHERING FLASHING MEMBRANE
A. Rubberized-Asphalt Flashing: Manufacturer's standard composite flashing product consisting
of a pliable and highly adhesive rubberized-asphalt compound,bonded to a high-density, cross-
laminated polyethylene film to produce an overall thickness of 0.040 inch. Provide
manufacturers recommended primer.
1. Products:
a. Henry TWF;by Henry Company
b. Perm-A-Barrier Wall Flashing; W. R. Grace & Co., Construction Products
Division.
c. Approved equal
2.5 Termination Bar
A. Aluminum bar approximately 1/8"x 1"with sealant ledge.
2.6 Sealant/Mastic
A. Sealant/mastic as recommended by self-adhering membrane manufacturer.
2.7 Weeps
A. Hohmann&Barnard QV-Quadro-Vent sized to fit existing brick
PART 3 -EXECUTION
3.1 PROTECTION
A. Protect persons, motor vehicles, surrounding surfaces of building being restored, building site,
a t
pl n s, and surrounding buildings from harm resulting from masonry restoration work.
B. Comply protecting with chemical cleaner manufacturer's written instructions for rotectin building and
g
other surfaces against damage from exposure to its products. Prevent chemical cleaning
solutions from coming into contact with pedestrians, motor vehicles, landscaping, buildings,
and other surfaces that could be harmed by such contact.
C. Prevent mortar from staining face of surrounding masonry and other surfaces.
1. Keep wall area wet below rebuilding and pointing work to discourage mortar from
adhering.
2. Immediately remove mortar in contact with exposed masonry and other surfaces.
MASONRY REPAIR 04520-4
Community Development Building December 8,2015
3.2 BRICK REMOVAL AND REPLACEMENT
A. At locations indicated, remove bricks necessary to install the new through wall flashing.
Carefully demolish or remove entire units from joint to joint, without damaging surrounding
masonry, in a manner that permits replacement with full-size units. When removing single
bricks, remove material from center of brick and work toward outside edges. Brick removal
must be performed using dust extraction equipment to prevent dust entry to the building
interior.
B. Support and protect remaining masonry that surrounds removal area. Maintain weather barrier
and adjoining construction in an undamaged condition.
C. Notify Engineer of unforeseen detrimental conditions including voids, cracks, bulges, and loose
masonry units in existing masonry backup, rotted wood, rusted metal, and other deteriorated
items.
D. Remove in an undamaged condition as many whole bricks as possible.
1. Remove mortar, loose particles, and soil from brick by cleaning with hand chisels,
brushes, and water.
2. Store brick for reuse, as indicated.
E. Clean bricks surrounding removal areas by removing mortar, dust, and loose particles in
preparation for replacement.
F. Provide new co pp er through wall flashin g,p rime copper wall surfaces and provide new self
adhering rubberized asphalt membrane. Hold self-adhering membrane flashing back from the
face of brick ''A" to ''h". Install self-adhering flashing without wrinkles and fully adhered to the
substrate. Roll the entire surface of the flashing to ensure a full bond.
G. Secure the top edge of the rubberized asphalt membrane flashing with a continuous termination
bar secured 16 inches on center to metal stud framing. Apply sealant/mastic along the top edge.
Lap rubberized asphalt 4 inches minimum and apply mastic to edges.
H. Provide pre-molded end dams at the end of flashing runs.
I. Provide weeps spaced 24 inches on center.
J. If cutting is required, use a motor-driven saw designed to cut masonry with clean, sharp,
unchipped edges.
K. Mix mortar following ASTM C270 proportion specification using 3 parts masonry sand to one
part masonry cement.
L. Lay replacement brick with completely filled bed and head joints. Butter ends with sufficient
mortar to fill head joints and shove into place. Use wetting methods that ensure that units are
nearly saturated but-surface is dry when laid. Maintain joint width for replacement units to
match existing joints.
1. Tool exposed mortar joints in repaired areas to match joints of surrounding existing
brickwork.
MASONRY REPAIR 04520-5
Community Development Building December 8,2015
2. Rake out mortar used for laying brick before mortar sets and point new mortar joints in
repaired area to comply with requirements for repointing existing masonry, and at same
time as repointing of surrounding area.
3.3 CLEANING MASONRY, GENERAL
A. Proceed with cleaning in an orderly manner; work from top to bottom and from one end of each
elevation to the other.
B. Use only those cleaning methods indicated for each masonry material and location.
1. Do not use wire brushes or brushes that are not resistant to chemical cleaner being used.
2. For chemical cleaner spray application, use low-pressure tank or chemical pump suitable
for chemical cleaner indicated, equipped with cone-shaped spray tip.
C. -Chemical Cleaner Application Methods: Apply chemical cleaners to masonry surfaces to
comply with chemical cleaner manufacturer's written instructions; use brush or spray
application methods, at Contractor's option. Do not spray apply at pressures exceeding 50 psi.
Do not allow chemicals to remain on surface for periods longer than those indicated or
recommended by manufacturer.
D. Rinse off chemical residue and soil. Periodically during each rinse, test pH of rinse water
running off of cleaned area to determine that chemical cleaner is completely removed.
1. Apply neutralizing agent and repeat rinse, if necessary, to produce tested pH of between
6.7 and 7.5.
E. After cleaning is complete, remove protection no longer required. Remove tape and adhesive
marks.
3.4 CLEANING BRICKWORK
A. Chemical Cleaning:
1. Wet masonry with cold water applied by low-pressure spray.
2. Apply cleaner to masonry by brush or low-pressure spray. Let cleaner remain on surface
as recommended by chemical cleaner manufacture.
3. Rinse with cold water applied by medium-pressure spray to remove chemicals and soil.
MASONRY REPAIR 04520 -6
Community Development Building December 8,2015
3.5 CLEAN-UP
A. After mortar has fully hardened, thoroughly clean exposed masonry surfaces of excess mortar
and foreign matter; use wood scrapers, stiff-nylon or -fiber brushes, and clean water, spray
applied at low pressure.
1. Do not use metal scrapers or brushes.
2. Do not use acidic or alkaline cleaners.
B. Wash adjacent woodwork and other nonmasonry surfaces. Use detergent and soft brushes or
cloths.
C. Clean masonry debris from roof; remove debris from drains, gutters and downspouts. Rinse off
roof and flush gutters and downspouts.
D. Sweep and rake adjacent pavement and grounds to remove masonry debris. Where necessary,
pressure wash surfaces to remove mortar, dust, dirt, and stains.
3.6 MASONRY WASTE DISPOSAL
A. Unless otherwise indicated, excess masonry materials are Contractor's property. At completion
of Masonry Repair work,remove from Project site and legally dispose of off Owner's property.
END OF SECTION 04520
MASONRY REPAIR 04520 -7
Community Development Building December 8,2015
SECTION 06105 -MISCELLANEOUS CARPENTRY
PART 1 -GENERAL
1.1 RELATED DOCUMENTS
A. Drawings and general provisions of the Contract, including General and Supplementary
Conditions and Division 1 Specification Sections, apply to this Section.
1.2 SUMMARY
A. This Section includes providing all labor, materials, equipment and supervision as outlined in
the Specifications and Drawings. The following is a brief description of the Work:
1. Wood blocking and nailers
2. Plywood sheathing
3. Wood plank deck
B. Related Sections include the following:
1. Division 7; Section 07531 "EPDM Membrane Roofing"
2. Division 7, Section 07311 "Asphalt Shingles"
3. Division 7, Section 07591 "Membrane Roofing Preparation/Demolition"
4. Division 7, Section 07620"Sheet Metal Flashing and Trim"
1.3 UNIT PRICES
A. Provide quantities specified under Section 01270 — "Unit Prices", materials to be used are
specified in this section.
1.4 SUBMITTALS
A. Product Data:
1. Not Required
1.5 DELIVERY, STORAGE,AND HANDLING
A. Stack lumber, plywood, and other panels; place spacers between each bundle to provide air
circulation. Provide for air circulation around stacks and under coverings.
MISCELLANEOUS CARPENTRY 06105 - 1
Community Development Building December 8,2015
1.6 SCHEDULING
A. Coordinate work of this section with interfacing and adjoining work for proper sequencing of
each installation. Ensure weather resistance,durability and protection of materials and finishes.
PART 2 -PRODUCTS
2.1 MISCELANEOUS LUMBER,NAILERS,BLOCKING,WOOD PLANK
A. For items of dimension lumber size, provide No. 2 grade lumber with any of the following
species:
1. Mixed southern pine; SPIB.
2. Hem-fir or Hem-fir(north);NLGA,WCLIB, or WWPA.
3. Spruce-pine-fir(south)or Spruce-pine-fir;NELMA,NLGA,WCLIB, or WWPA.
4. Eastern softwoods;NELMA.
5. Northern species;NLGA.
B. Kiln-dry material to maximum moisture content of 19 percent for lumber and 15 percent for
plywood. Do not use material that is warped or does not comply with requirements for
untreated material.
1. Mark each item with the treatment quality mark of an inspection agency approved by the
American Lumber Standards Committee Board of Review.
C. Provide lumber in the sizes indicated in the Drawings.
2.2 PANEL PRODUCTS
A. Miscellaneous Concealed Plywood: Exterior tongue and groove CDX sheathing, span rating to
suit framing in each location,nominal 3/4"inch thick.
2.3 FASTENERS
A. General: Provide fasteners of size and type indicated that comply with requirements specified
in this Article for material and manufacture.
1. Provide fasteners with hot-dip zinc coating complying with ASTM A 153/A 153M.
B. Common Nails: Hot dipped galvanized of sizes required.
C. Roofing Nails: Stainless steel ring shank,minimum 1-1/4"long or as indicated.
D. Wood Screws: Corrosion resistant coated meeting ASME B18.6.1.
MISCELLANEOUS CARPENTRY 06105 -2
Community Development Building December 8,2015
PART 3 -EXECUTION
3.1 INSTALLATION, GENERAL
A. Discard units of material with defects that impair quality of carpentry and that are too small to
use with minimum number of joints or optimum joint arrangement.
B. Set carpentry to required levels and lines, with members plumb, true to line, cut, and fitted. Fit
carpentry to other construction; scribe and cope as needed for accurate fit. Locate nailers,
blocking, and similar supports to comply with requirements for attaching other construction.
C. Countersink fastener heads on exposed carpentry work and fill holes with wood filler.
D. Securely attach carpentry work to substrate by anchoring and fastening as indicated, where not
indicated, comply with the following:
1. Table 2304.9.1 "Fastening Schedule," in the 2012 International Building Code.
3.2 WOOD BLOCKING,AND NAILER INSTALLATION
A. Install where indicated and where required for attaching other work. Form to shapes indicated
and cut as required for true line and level of attached work. Coordinate locations with other
work involved.
B. Attach items to substrates to support applied loading. Recess bolts and nuts flush with surfaces,
unless otherwise indicated.
3.3 CLEAN-UP
A. All debris shall be removed from the job site by the Contractor in accordance with Contract
provisions.
END OF SECTION 06105
MISCELLANEOUS CARPENTRY 06105 -3
Community Development Building December 8,2015
SECTION 07311 -ASPHALT SHINGLES
PART 1 -GENERAL
1.1 RELATED DOCUMENTS
A. Drawings and general provisions of the Contract, including General and Supplementary
Conditions and Division 1 Specification Sections,apply to this Section.
1.2 SUMMARY
A. This Section includes the following:
1. Self-Adhering Underlayment.
2. Fascia Intake Vent
B. Related Sections include the following:
1. Division 6, Section 06105 "Miscellaneous Carpentry"
2. Division 7, Section 07531 "EPDM Membrane Roofing"
3. Division 7, Section 07591 "Membrane Roofing Preparation/Demolition"
4. Division 7, Section 07620"Sheet Metal Flashing and Trim"
1.3 DEFINITIONS
A. Roofmg Terminology: Refer to ASTM D 1079 and glossary of NRCA's "The NRCA Roofing
and Waterproofing Manual" for definitions of terms related to roofing work in this Section.
1.4 SUBMITTALS
A. Product Data: For each type of product indicated.
1.5 QUALITY ASSURANCE
A. Installer Qualifications: A firm or individual that is approved, authorized, or licensed by asphalt
shingle roofing system manufacturer to install roofing system indicated.
1.6 DELIVERY, STORAGE,AND HANDLING
A. Store roofing materials in a dry, well-ventilated, weather tight location according to
manufacturer's written instructions. Store underlayment rolls on end on pallets or other raised
surfaces. Do not double-stack rolls.
ASPHALT SHINGLES 07311 - 1
Community Development Building December 8,2015
1. Handle, store, and place roofing materials in a manner to avoid significant or permanent
damage to roof deck or structural supporting members.
B. Protect unused underlayment from weather, sunlight, and moisture when left overnight or when
roofing work is not in progress.
1.7 PROJECT CONDITIONS
A. Weather Limitations: Proceed with installation only when existing and forecasted weather
conditions permit asphalt shingle.roofing to be performed according to manufacturer's written
instructions and warranty requirements.
1. Install self-adhering sheet underlayment within the range of ambient and substrate
temperatures recommended by manufacturer.
PART 2-PRODUCTS
2.1 MANUFACTURERS
1. Available Products: Subject to compliance with requirements, products that may be
incorporated into the Work include,but are not limited to,products specified.
2. Products: Subject to compliance with requirements, provide one of the products
specified.
2.2 UNDERLAYMENT MATERIALS
A. Self Adhered Underlayment: ASTM D 1970, minimum of 55-mil thick sheet; glass-fiber-mat-
reinforced, SBS-modified asphalt; mineral-granule surfaced; with release paper backing; cold
applied.
1. Available Products:
a. CertainTeed Corporation;WinterGuard.
b. Approved equal
2.3 FASCIA INTAKE VENT
A. Fascia Intake Vent: .
1. Available Product:
a. GAF Materials Corporation; Cobra FasciaFlow
b. Approved equal
2. Minimum Net Free Area: 9 sq. in.per foot
ASPHALT SHINGLES 07311 -2
Community Development Building December 8,2015
2.4 ACCESSORIES
A. Roofing Nails: ASTM F 1667; stainless-steel shingle nails, minimum 0.120-inch diameter,
barbed shank, sharp-pointed, with a minimum 3/8-inch diameter flat head and of sufficient
length to penetrate 3/4 inch into solid wood decking or extend at least 1/8 inch through OSB or
plywood sheathing.
1. Where nails are in contact with metal flashing, use nails made from same metal as
flashing.
2.5 METAL FLASHING AND TRIM
A. Sheet Metal Flashing and Trim: Comply with requirements in Division 7 Section "Sheet Metal
Flashing and Trim."
B. Fabricate sheet metal flashing and trim to comply with recommendations in SMACNA's
"Architectural Sheet Metal Manual" that apply to design, dimensions, metal, and other
characteristics of item.
1. Drip Edges: Fabricate in lengths not exceeding 10 feet with 4-inch roof deck flange and
5 -inch fascia flange with 3/8-inch drip at lower edge.
PART 3 -EXECUTION
3.1 EXAMINATION
A. Examine substrates, areas, and conditions, with Installer present, for compliance with
requirements for installation tolerances and other conditions affecting performance of work.
1. Examine roof sheathing to verify that sheathing joints are supported by framing and
blocking or metal clips and that installation is within flatness tolerances.
2. Verify that substrate is sound, dry, smooth, clean, sloped for drainage, and completely
anchored; and that provision has been made for flashings and penetrations through
asphalt shingles.
B. Proceed with installation only after unsatisfactory conditions have been corrected.
3.2 UNDERLAYMENT INSTALLATION
A. Self-Adhering Sheet Underlayment: Install self-adhering sheet underlayment, wrinkle free, on
roof deck. Comply with low-temperature installation restrictions of underlayment manufacturer
if applicable. Install at locations indicated on Drawings, lapped in direction to shed water. Lap
under existing felt paper 6 inches minimum. Lap ends not less than 6 inches staggered. Roll
laps with roller. Cover underlayment within seven days.
ASPHALT SHINGLES 07311 -3
Community Development Building December 8,2015
3.3 METAL FLASHING INSTALLATION
A. General: Install metal flashings and other sheet metal to comply with requirements in
Division 7 Section"Sheet Metal Flashing and Trim."
1. Install metal flashings according to recommendations in ARMA's "Residential Asphalt
Roofing Manual" and asphalt shingle recommendations in NRCA's "The NRCA Roofing
and Waterproofing Manual." .
B. Eave Drip Edges: Install eave drip edge flashings below underlayment and fasten to roof
sheathing.
3.4 ASPHALT SHINGLE INSTALLATION
A. Install asphalt shingles according to manufacturer's written instructions, recommendations in
ARMA's "Residential Asphalt Roofing Manual," and asphalt shingle recommendations in
NRCA's "The NRCA Roofing and Waterproofing Manual."
B. Install starter strip along lowest roof edge, consisting of an asphalt shingle strip with self-
sealing strip face up at roof edge.
1. Extend asphalt shingles 1/2 inch over fascia at eaves.
2. Install starter strip along rake edge.
C. Fasten asphalt shingle strips with a minimum of five roofing nails located according to
manufacturer's written instructions.
1. When ambient temperature during installation is below 50 deg F, seal asphalt shingles
with asphalt roofing cement spots.
D. Fascia Intake Vents: Install continuous fascia intake vent according to manufacturer's written
instructions.
END OF SECTION 07311
ASPHALT SHINGLES 07311 -4
Community Development Building December 8,2015
SECTION 07531 -EPDM MEMBRANE ROOFING
PART 1 -GENERAL
1.1 RELATED DOCUMENTS
A. Drawings and general provisions of the Contract, including General and Supplementary
Conditions and Division 1 Specification Sections, apply to this Section.
1.2 SUMMARY
A. This Section includes the following:
1. Adhered membrane roofing system.
B. Related Sections include the following:
1. Division 4, Section 04520"Masonry Repair"
2. Division 6, Section 06105 "Miscellaneous Carpentry"
3. Division 7, Section 07311 "Asphalt Shingles"
4. Division 7, Section 07531 `EPDM Membrane Roofing"
5. Division 7, Section 07591 "Membrane Roofing Preparation/Demolition"
6. Division 7, Section 07620"Sheet Metal Flashing and Trim"
C. Unit Prices: Refer to Division 1 Section "Unit Prices" for description of Work in this Section
affected by unit prices.
1.3 DEFINITIONS
A. Roofing Terminology: Refer to ASTM D 1079 and glossary of NRCA's "The NRCA Roofing
and Waterproofing Manual" for definition of terms related to roofing work in this Section.
1.4 PERFORMANCE REQUIREMENTS
A. General: Provide installed roofing membrane and base flashings that remain watertight; do not
permit the passage of water; and resist specified uplift pressures, thermally induced movement,
and exposure to weather without failure.
B. Material Compatibility: Provide roofing materials that are compatible with one another under
conditions of service and application required, as demonstrated by roofing membrane
manufacturer based on testing and field experience.
EPDM MEMBRANE ROOFING 07531 - 1
Community Development Building December 8,2015
C. Roofing System Design: Provide a membrane roofing system that is identical to systems that
have been successfully tested by a qualified testing and inspecting agency to resist uplift
pressure calculated according to ASCE 7. (Factor of Safety of 2)
1. Field Uplift Pressure: 38 lbf/sq. ft.
2. Perimeter Uplift Pressure: 64 lbf/sq. ft.
3. Corner Uplift Pressure: 97 lbf/sq. ft.
1.5 SUBMITTALS
A. Product Data: For each type of product indicated.
B. Shop Drawings: For roofing system.
1. Insulation board fastening patterns.
C. Installer Certificates: Signed by roofing system manufacturer certifying that Installer is
approved,authorized,or licensed by manufacturer to install roofing system.
D. Manufacturer Certificates: Signed by roofing manufacturer certifying that roofing system
complies with requirements specified in"Performance Requirements" Article.
1. Submit Roof Assembly Letter indicating evidence of meeting performance requirements.
E. Qualification Data: For Installer and manufacturer.
F. Product Test Reports: Based on evaluation of comprehensive tests performed by manufacturer
and witnessed by a qualified testing agency, for components of roofing system.
G. Maintenance Data: For roofing system to include in maintenance manuals.
H. Warranties: Special warranties specified in this Section.
1.6 QUALITY ASSURANCE
A. Installer Qualifications: A qualified firm that is approved, authorized, or licensed by roofing
system manufacturer to install manufacturer's product and that is eligible to receive
manufacturer's warranty.
B. Manufacturer Qualifications: A qualified manufacturer that has UL listing or FMG approval for
membrane roofing system identical to that used for this Project.
C. Testing Agency Qualifications: An independent testing agency with the experience and
capability to conduct the testing indicated, as documented according to ASTM E 548.
D. Source Limitations: Obtain components for membrane roofing system from same manufacturer
as roofing membrane or as approved by roofing membrane manufacturer..
E. Fire-Test-Response Characteristics: Provide membrane roofing materials with the fire-test-
response characteristics indicated as determined by testing identical products per test method
EPDM MEMBRANE ROOFING 07531 -2
Community Development Building December 8,2015
below by UL, FMG, or another testing and inspecting agency acceptable to authorities having
jurisdiction. Materials shall be identified with appropriate markings of applicable testing and
inspecting agency.
1. Exterior Fire-Test Exposure: Class A; ASTM E 108, for application and roof slopes
indicated.
F. Preconstruction Conference: Conduct conference at Project site. Comply with requirements in
Division 1 Section "Project Management and Coordination." Review methods and procedures
related to roofing system including,but not limited to,the following:
1. Meet with Owner; Engineer; Owner's insurer if applicable; roofing Installer; roofing
system manufacturer's representative and installers whose work interfaces with or affects
roofing, including installers of roof accessories and roof-mounted equipment.
2. Review methods and procedures related to roofing installation, including manufacturer's
written instructions.
3. Review and finalize construction schedule and verify availability of materials, Installer's
personnel, equipment, and facilities needed to make progress and avoid delays.
4. Examine deck substrate conditions and finishes for compliance with requirements,
including flatness and fastening.
5. Review structural loading limitations of roof deck during and after roofing.
6. Review base flashings, special roofing details, roof drainage, roof penetrations,
equipment curbs, and condition of other construction that will affect roofing system.
7. Review governing regulations and requirements for insurance and certificates if
applicable.
8. Review temporary protection requirements for roofing system during and after
installation.
1.7 DELIVERY, STORAGE,AND HANDLING
A. Deliver roofing materials to Project site in original containers with seals unbroken and labeled
with manufacturer's name,product brand name and type, date of manufacture, and directions for
storing and mixing with other components.
B. Store liquid materials in their original undamaged containers in a clean, dry, protected location
and within the temperature range required by roofing system manufacturer. Protect stored
liquid material from direct sunlight.
1. Discard and legally dispose of liquid material that cannot be applied within its stated
shelf life.
C. Protect roof materials from physical damage and from deterioration by sunlight, moisture,
soiling, and other sources. Store in a dry location. Comply with insulation manufacturer's
written instructions for handling, storing, and protecting during installation.
D. Handle and store roofing materials and place equipment in a manner to avoid permanent
deflection of deck.
EPDM MEMBRANE ROOFING 07531 -3
Community Development Building December 8,2015
1.8 PROJECT CONDITIONS
A. Weather Limitations: Proceed with installation only when existing and forecasted weather
conditions permit roofing system to be installed according to manufacturer's written instructions
and warranty requirements.
1.9 WARRANTY
A. Manufacturer's Warranty: Manufacturer's standard form, without monetary limitation, in which
manufacturer agrees to repair or replace components of membrane roofing system that fail in
materials or workmanship within specified warranty period. Failure includes roof leaks.
1. Manufacturer's warranty includes roofing membrane, base flashings, roofing
accessories, fasteners and other components of membrane roofing system.
2. Warranty Period: 20 years from date of Substantial Completion.
B. Roofing Installer's Warranty: Submit Roofing Installer's Warranty, on warranty form at end of
this Section, signed by Installer, covering Work of this Section, including all components of
membrane roofing system such as roofing membrane, base flashing, roof insulation, fasteners,
cover boards, substrate boards, vapor retarders, roof pavers, and walkway products, for the
following warranty period:
1. Warranty Period: Three(3)years from date of Substantial Completion.
PART 2 -PRODUCTS
2.1 MANUFACTURERS
1. EPDM membrane shall be obtained from a single manufacturer. Secondary materials
(insulation, adhesive, fasteners, etc.) shall be by manufacturer of EPDM membrane; or,
as required by manufacturer of EPDM membrane. If secondary materials are provided by
others,they must be approved by the primary membrane manufacturer.
2.2 EPDM ROOFING MEMBRANE
A. EPDM Roofing Membrane: ASTM D 4637, Type I, nonreinforced uniform, flexible sheet
made from EPDM, and as follows:
1. Manufacturers:
a. Carlisle SynTec Incorporated.
b. Firestone Building Products Company.
c. GenFlex Roofing Systems.
d. Versico Inc.
2. Thickness: 60 mils,nominal.
3. Exposed Face Color: Black.
EPDM MEMBRANE ROOFING 07531 -4
Community Development Building December 8,2015
2.3 EPDM ROOF MEMBRANE ACCESSORIES
A. General: Auxiliary materials recommended by roofing system manufacturer for intended use
and compatible with membrane roofing.
1. Liquid-type auxiliary materials shall meet VOC limits of authorities having jurisdiction.
B. Sheet Flashing: 60-mil-thick EPDM,partially cured or cured, according to application.
C. Bonding Adhesive: Manufacturer's standard bonding adhesive.
D. Seaming Material: Manufacturer's standard synthetic-rubber polymer primer and 6-inch-wide
minimum,butyl splice tape with release film.
E. Lap Sealant: Manufacturer's standard single-component sealant, color to match roofing
membrane.
F. Water Cutoff Mastic: Manufacturer's standard butyl mastic sealant.
G. Polyurethane Sealant: Single component polyurethane sealant meeting minimum requirements
of ASTM C920, Type S, Class 25, Grade NS and Use NT, M and A; color to be selected by
Owner.
1. Available Products:
a. Master Builders-Masterseal;NP1
b. Sika; SikaFlex 1A
c. Approved Equal
H. Silicone Sealant: Single component neutral-curing silicone sealant.
1. Available Products:
a. Pecora Corporation; 890
b. Tremco; Spectrem 3
c. Approved equal.
I. Miscellaneous Roof Membrane Accessories: Provide pourable sealers, preformed cone and
vent sheet flashings, preformed inside and outside corner sheet flashings, T-joint covers,
termination reglets, cover strips,and other accessories.
J. Membrane Seam Plates and Fasteners: Factory-coated steel fasteners and metal plates designed
for fastening membrane to substrate,and acceptable to roofing system manufacturer.
2.4 ROOF DRAINS
A. Roof Drains: 3" diameter drain, cast iron bowl, strainers, underdeck clamps, metal drain sump
pan, clamping rings, hardware, no-hub plumbing fitting to connect to piping. Drains, clamping
rings, under deck clamps and strainers shall be cast iron, metal drain sump pans shall be 14
gauge galvanized steel.
1. Available products:
a. Wade, Series 3000 or 3000AE
b. Josam, Series 21500 or 21500AE
EPDM MEMBRANE ROOFING 07531 -5
Community Development Building December 8,2015
c. Zurn, Series Z-100 or Z-100EA
d. J.R. Smith, Series 1010 or 1015
e. Approved equal
2.5 ROOF DRAIN ACCESSORIES
A. Pipe Insulation — preformed glass fiber pipe insulation bonded with a thermosetting resin
complying with ASTM C547, Type 1 with factory applied ASJ jacket meeting ASTM C 1136
and adhesive strip,insulation to be ''A"thick minimum.
1. Available Products
a. Johns Manville Micro-Lok
b. Knauf 1000 ASJ
c. Owens Corning Fiberglass Pipe Insulation
• d. Approved equal
B. Pipe Insulation Tape—ASJ tape,white vapor retarder tape matching factory applied jacket with
acrylic adhesive complying with ASTM C 1136, as recommended by pipe insulation
manufacturer
C. Preformed Insulated Pipe Fittings—PVC jacketing fittings with fiberglass insulation inserts for
insulating pipe fittings,provide all accessory materials,tapes and adhesives for installation.
1. Available Products
a. Johns Manville Zeston 2000
b. Approved equal
D. Drain Bowl Insulation — Foil faced fiberglass batt insulation, meeting the requirements of
ASTM C665,Type 3, CL.B and C,minimum thickness of 2 inches.
E. Drain Insulation Tape—Premium Heavy duty foil tape meeting UL 181A-P standards for use as
a closure material for duct systems.
2.6 ROOF INSULATION
A. General: Provide preformed roof insulation boards that comply with requirements and
referenced standards, selected from manufacturer's standard sizes and of thicknesses indicated.
Roof insulation shall be UL and FM approved. Insulation shall be approved in writing by the
insulation manufacturer for intended use and for use with the specified roof assembly.
B. Polyisocyanurate Board Insulation (Fill): ASTM C 1289, Type II, Class2, Grade 2 glass-fiber
mat facer on both major surfaces. Maximum board size 4 feet by 8 feet. Thickness as required
to maintain specified slope.
C. Tapered Insulation (tapered field insulation): Polyisocyanurate ASTM C 1289, Type II, Class
2, Grade 2 glass-fiber mat facer on both major surfaces. Maximum board size 4 feet by 4 feet.
Provide factory-tapered insulation boards fabricated to slope of 1/4 inch per 12 inches, as
indicated in the drawings.
EPDM MEMBRANE ROOFING 07531 -6
Community Development Building December 8,2015
D. Provide saddles, crickets,manufactured from polyisocyanurate meeting ASTM C 1289,Type II,
Class 2, Grade 2 glass-fiber mat facer on both major surfaces and other insulation shapes where
indicated for sloping to drain. Fabricated to %2"per foot slope unless otherwise indicated
2.7 ROOF INSULATION ACCESSORIES
A. General: Roof insulation accessories recommended by insulation manufacturer for intended use
and compatible with membrane roofing. Roof insulation accessories shall be UL and FM
approved. Insulation shall be approved in writing by the insulation manufacturer for intended
use and for use with the specified roof assembly.
B. Fasteners: Factory-coated steel fasteners and metal or plastic plates meeting corrosion-
resistance provisions in FMG 4470, designed for fastening roof insulation to substrate, and
acceptable to roofing system manufacturer.
2.8 MISCELLANEOUS ROOF ACCESSORIES
A. Aluminum Stamped Adhesive Cable Fasteners
1. Available Products:
a. Erico-Model LPA810
b. Kuefler Lightning Protection-Series 810
c. Approved equal
B. Single Cone Vent and Curb Roofing Mounting Base-Mill Finished aluminum siphon vent, 10"
diameter throat constructed of minimum 0.025" aluminum with #8 aluminum mesh insect
screen and curb mount base.
1. Available Products:
a. Empire Ventilation-Eveco Ventilator
b. Approved equal
C. Fascia Intake Vent: PVC intake vent with insect screen designed for installation along open
rafters.
1. Available Products:
a. GAF/ELK-Cobra FasciaFlow
b. Approved equal
PART 3 -EXECUTION
3.1 EXAMINATION
A. Examine substrates, areas, and conditions, with Installer present, for compliance with the
following requirements and other conditions affecting performance of roofing system:
EPDM MEMBRANE ROOFING 07531 -7
Community Development Building December 8,2015
1. Verify that roof openings and penetrations are in place and set and braced and that roof
drains are securely clamped in place.
2. Verify that wood blocking, curbs, and nailers are securely anchored to roof deck at
penetrations and terminations and that nailers match thicknesses of insulation.
3. Verify the existing deck is suitable for application of the new roof system. Remove and
replace ant deteriorated wood decking. Secure any loose boards.
4. Proceed with installation only after unsatisfactory conditions have been corrected.
3.2 PREPARATION
A. Clean substrate of dust,debris,moisture, and other substances detrimental to roofing installation
according to roofing system manufacturer's written instructions. Remove sharp projections.
B. Complete terminations and base flashings and provide temporary seals to prevent water from
entering completed sections of roofing system at the end of the workday or when rain is
forecast. Remove and discard temporary seals before beginning work on adjoining roofing.
3.3 INSULATION INSTALLATION
A. Comply with roofing system manufacturer's written instructions for installing roof insulation.
B. Install tapered insulation under area of roofing to conform to slopes indicated.
C. Install insulation with long joints of insulation in a continuous straight line with end joints
staggered between rows, abutting edges and ends between boards. Fill gaps exceeding 1/4 inch
with insulation.
1. Cut and fit insulation within 1/4 inch of nailers,projections, and penetrations.
D. Install one or more layers of insulation under area of roofing to achieve required thickness.
Where overall insulation thickness is 2 inches or greater, install 2 or more layers with joints of
each succeeding layer staggered from of previous layer a minimum of 6 inches in each
direction.
E. Trim surface of insulation where necessary at roof drains so completed surface is flush and does
not restrict flow of water.
F. Mechanically Fastened Insulation: Install each layer of insulation and secure to deck using
mechanical fasteners specifically designed and sized for fastening specified board-type roof
insulation to deck type.
3.4 ADHERED ROOFING MEMBRANE INSTALLATION
A. Install roofing membrane over area to receive roofing according to membrane roofing system
manufacturer's written instructions. Unroll roofing membrane and allow to relax before
installing.
B. Start installation of roofing membrane in presence of membrane roofing system manufacturer's
technical personnel.
EPDM MEMBRANE ROOFING 07531 -8
Community Development Building December 8,2015
C. Accurately align roofing membrane and maintain uniform side and end laps of minimum
dimensions required by manufacturer. Stagger end laps.
D. Bonding Adhesive: Apply bonding adhesive to substrate and underside of roofing membrane at
rate required by manufacturer and allow to partially dry before installing roofing membrane.
Do not apply bonding adhesive to splice area of roofing membrane.
E. Mechanically or adhesively fasten roofing membrane securely at terminations,penetrations,and
perimeter of roofing.
F. Apply roofing membrane with side laps shingled with slope of roof deck where possible.
G. Tape Seam Installation: Clean and prime both faces of splice areas, apply splice tape, and
firmly roll side and end laps of overlapping roofing membranes according to manufacturer's
written instructions to ensure a watertight seam installation. Apply lap sealant and seal exposed
edges of roofing membrane terminations.
H. Repair tears,voids, and lapped seams in roofing that does not meet requirements.
3.5 BASE FLASHING INSTALLATION
A. Install sheet flashings and preformed flashing accessories and adhere to substrates according to
membrane roofing system manufacturer's written instructions.
B. Apply bonding adhesive to substrate and underside of sheet flashing at required rate and allow
to partially dry. Do not apply bonding adhesive to seam area of flashing.
C. Flash penetrations and field-formed inside and outside corners with cured or uncured sheet
flashing.
D. Clean splice areas, apply splicing cement, and firmly roll side and end laps of overlapping
sheets to ensure a watertight seam installation. Apply lap sealant and seal exposed edges of
sheet flashing terminations.
E. Terminate and seal top of sheet flashings.
3.6 DRAIN INSTALLATION
A. Access to the underside of the roof deck at each existing roof drain location will be made from
the interior of second floor office spaces. Provide all necessary manpower, equipment and
materials needed to access the underside of the roof drains.
B. Provide all necessary connections, piping and fittings to install new drains. Cut pipes as
necessary to accommodate new roof drain and sump elevations. Complete all plumbing
connections prior to leaving site each day.
C. Provide new drain, sump pan, no hub connection, pipes and fittings to install new drains as
shown in the Drawings. Insulate new roof drain bowls and vertical leaders. All work shall
conform to the International Plumbing Code.
EPDM MEMBRANE ROOFING 07531 -9
Community Development Building December 8,2015
D. Perform water tests of newly added drains by installing plugs and allowing drains to sit for 24
hours. Verify no leaks have occurred; make necessary repairs if leaks are discovered.
3.7 FIELD QUALITY CONTROL
A. Testing Agency: Owner will engage a qualified independent testing and inspecting agency to
perform roof tests and inspections and to prepare test reports.
B. Final Roof Inspection: Arrange for roofing system manufacturer's technical personnel to
inspect roofing installation on completion and submit report to Engineer.
1. Notify Engineer and Owner 48 hours in advance of date and time of inspection.
C. Repair or remove and replace components of membrane roofing system where test results or
inspections indicate that they do not comply with specified requirements.
D. Additional testing and inspecting, at Contractor's expense, will be performed to determine
compliance of replaced or additional work with specified requirements.
3.8 PROTECTING AND CLEANING
A. Protect membrane roofing system from damage and wear during remainder of construction
period. When remaining construction will not affect or endanger roofing, inspect roofing for
deterioration and damage, describing its nature and extent in a written report, with copies to
Architect and Owner.
B. Correct deficiencies in or remove membrane roofing system that does not comply with
requirements, repair substrates and repair or reinstall membrane roofing system to a condition
free of damage and deterioration at time of Substantial Completion and according to warranty
requirements.
C. Clean overspray and spillage from adjacent construction using cleaning agents and procedures
recommended by manufacturer of affected construction.
3.9 ROOFING INSTALLER'S WARRANTY
A. WHEREAS <Insert name> of<Insert address>, herein called the "Roofing Installer," has
performed roofing and associated work("work")on the following project:
1. Owner: Isle of Wight
2. Address: 13048 Poor House Road, Isle of Wight,VA 23397
3. Building Name/Type: Community Development Building
4. Address: 17146 Monument Circle,VA
5. Area of Work: Community Development Building Roof Areas Al, A2, A3, A4, B1 and
B2
6. Acceptance Date: <Insert date.>
7. Warranty Period: 3 Years
8. Expiration Date: <Insert date.>
EPDM MEMBRANE ROOFING 07531 - 10
Community Development Building December 8,2015
B. AND WHEREAS Roofing Installer has contracted(either directly with Owner or indirectly as a
subcontractor) to warrant said work against leaks and faulty or defective materials and
workmanship for designated Warranty Period,
C. NOW THEREFORE Roofing Installer hereby warrants, subject to terms and conditions herein
set forth, that during Warranty Period he will, at his own cost and expense, make or cause to be
made such repairs to or replacements of said work as are necessary to correct faulty and
defective work and as are necessary to maintain said work in a watertight condition.
D. This Warranty is made subject to the following terms and conditions:
1. Specifically excluded from this Warranty are damages to work and other parts of the
building, and to building contents,caused by:
a. lightning;
b. peak gust wind speed exceeding 72 mph;
c. fire;
d. failure of roofing system substrate, including cracking, settlement, excessive
deflection, deterioration,and decomposition;
e. faulty construction of parapet walls, copings, chimneys, skylights, vents,
equipment supports, and other edge conditions and penetrations of the work;
f. vapor condensation on bottom of roofing; and
g. activity on roofing by others, including construction contractors, maintenance
personnel, other persons, and animals, whether authorized or unauthorized by
Owner.
2. When work has been damaged by any of foregoing causes, Warranty shall be null and
void until such damage has been repaired by Roofing Installer and until cost and expense
thereof have been paid by Owner or by another responsible party so designated.
3. Roofing Installer is responsible for damage to work covered by this Warranty but is not
liable for consequential damages to building or building contents resulting from leaks or
faults or defects of work.
4. During Warranty Period, if Owner allows alteration of work by anyone other than
Roofing Installer, including cutting, patching, and maintenance in connection with
penetrations, attachment of other work, and positioning of anything on roof, this
Warranty shall become null and void on date of said alterations, but only to the extent
said alterations affect work covered by this Warranty. If Owner engages Roofing
Installer to perform said alterations, Warranty shall not become null and void unless
Roofing Installer, before starting said work, shall have notified Owner in writing,
showing reasonable cause for claim, that said alterations would likely damage or
deteriorate work, thereby reasonably justifying a limitation or termination of this
Warranty.
5. During Warranty Period, if original use of roof is changed and it becomes used for, but
was not originally specified for, a promenade, work deck, spray-cooled surface, flooded
basin, or other use or service more severe than originally specified, this Warranty shall
become null and void on date of said change, but only to the extent said change affects
work covered by this Warranty.
6. Owner shall promptly notify Roofing Installer of observed, known, or suspected leaks,
defects, or deterioration and shall afford reasonable opportunity for Roofing Installer to
inspect work and to examine evidence of such leaks, defects, or deterioration.
EPDM MEMBRANE ROOFING 07531 - 11
Community Development Building December 8,2015
7. This Warranty is recognized to be the only warranty of Roofing Installer on said work
and shall not operate to restrict or cut off Owner from other remedies and resources
lawfully available to Owner in cases of roofing failure. Specifically, this Warranty shall
not operate to relieve Roofing Installer of responsibility for performance of original work
according to requirements of the Contract Documents, regardless of whether Contract
was a contract directly with Owner or a subcontract with Owner's General Contractor.
E. IN WITNESS THEREOF, this instrument has been duly executed this <Insert day> day of
<Insert month>, <Insert year>.
1. Authorized Signature: <Insert signature.>
2. Name: <Insert name.>
3. Title: <Insert title.>
END OF SECTION 07531
EPDM MEMBRANE ROOFING 07531 - 12
Community Development Building November 13, 2015
Roof Approximate Existing Asbestos
Section Roof Area Roof Deck Existing Roof Construction Containing
ID (Square Feet) Type Roofing
Materials
Mechanically attached thermoplastic membrane over a separator sheet over a 1/4"
Al 3,500 Metal Deck thick layer of extruded polystyrene insulation over a separator sheet over a No
thermoplastic membrane over another thermoplastic membrane over a separator
sheet over two layers of 2"thick extruded polystyrene insulation on a metal deck.
A2 50 Metal Deck Mechanically attached thermoplastic membrane over a thermoplastic membrane No
over a separator sheet over a 6" thick layer of extruded polystyrene on a metal
deck.
Mechanically attached thermoplastic membrane over a separator sheet over a 1/4"
A3 130 Metal Deck thick layer of extruded polystyrene insulation over a separator sheet over a No
thermoplastic membrane over another thermoplastic membrane over a separator
sheet over two layers of 2" thick extruded polystyrene insulation on a metal deck.
Mechanically attached thermoplastic membrane over a separator sheet over a 1/4"
A4 80 Metal Deck thick layer of extruded polystyrene insulation over a separator sheet over a No
thermoplastic membrane over another thermoplastic membrane over a separator
sheet over two layers of 2" thick extruded polystyrene insulation on a metal deck.
B1 700 Metal Deck Mechanically attached thermoplastic membrane over a 1-1/2" thick layer of No
polyisocyanurate insulation.
B2 150 Metal Deck Mechanically attached thermoplastic membrane over a 1-1/2" thick layer of No
polyisocyanurate insulation.
MEMBRANE ROOFING PREPARATION/DEMOLITION 07591
Community Development Building December 8,2015
SECTION 07591 -MEMBRANE ROOFING PREPARATION/DEMOLITION
PART 1 -GENERAL
1.1 RELATED DOCUMENTS
A. Drawings and general provisions of the Contract, including General and Supplementary
Conditions and Division 1 Specification Sections,apply to this Section.
1.2 SUMMARY
A. This Section includes providing all labor, materials, equipment and supervision as outlined in
the Specifications and Drawings. The following is a brief description of the Work:
1. Roof system demolition and disposal.
' 2. Preparation of surfaces for installation of new roofing.
3. Protection of existing roofing systems.
B. Related Sections include the following:
1. Division 4, Section 04520"Masonry Repair"
2. Division 6, Section 06105 "Miscellaneous Carpentry"
3. Division 7, Section 07311 "Asphalt Shingles"
4. Division 7, Section 07531 "EPDM Membrane Roofing"
5. Division 7, Section 07591 "Membrane Roofing Preparation/Demolition"
6. Division 7, Section 07620"Sheet Metal Flashing and Trim"
C. Unit Prices: Refer to Division 1 Section "Unit Prices" for description of Work in this Section
affected by unit prices.
1.3 MATERIALS OWNERSHIP
A. Except for items or materials indicated to be reused, reinstalled, or otherwise indicated to
remain Owner's property, demolished materials shall become Contractor's property and shall be
removed from Project site.
1.4 WORK INCLUDED
A. Provide all labor, materials, equipment, tools and supervision as required to remove the existing
roof materials and prepare the existing substrates for the application of the new roof system.
B. Provide for the proper disposal of all existing materials to be removed. Provide approved trash
receptacles located in areas designated by the Owner's representative.
MEMBRANE ROOFING PREPARATION/DEMOLITION 07591 - 1
Community Development Building December 8,2015
C. Coordinate the roof preparation work with the new roofing work in such a manner as to keep the
new insulation and roofing materials, building, and building interior absolutely clean, dry and
watertight.
D. The Contractor expressly undertakes, both directly and through his Subcontractors, to take
every reasonable precaution at all times for the protection of all persons and property which
may come on the Site or be affected by the Contractor's Work.
E. The Contractor shall be solely responsible for initiating, maintaining and supervising all safety
precautions and programs in connection with the Work.
F. The provisions of all Federal, State and local rules and regulations governing health and safety
as adopted by the relevant authority, shall apply to all Work under this Contract.
G. The Contractor shall continuously maintain adequate protection of all his Work from damage
and shall protect the Owner's property from injury or loss arising in connection with this
Contract. He shall make good any such damage, injury or loss, except as may be directly and
solely due to errors in the Contract Documents or caused by agents or employees of the Owner.
The Contractor shall adequately protect adjacent property to prevent any damage to it or loss of
use and enjoyment by its owners. The Contractor shall provide and maintain all passageways,
guard fences, lights and other facilities for protection as required by State or local authority,
local conditions, or the Contract.
1.5 DEFINITIONS
A. Roofing Terminology: Refer to ASTM D 1079 and glossary in NRCA's "The NRCA Roofing
and Waterproofing Manual" for definition of terms related to roofing work in this Section.
1.6 SUBMITTALS
A. Photographs or Videotape: Show existing conditions of adjoining construction and site
improvements, including exterior and interior finish surfaces that might be misconstrued as
having been damaged by roofing operations. Submit before Work begins.
1.7 EXISTING CONSTRUCTION
A. Attached to this section is a table with existing construction of the roof as determined by the
Engineer through limited roof core samples. Contractor may obtain additional core samples to
verify existing construction prior to bidding providing membrane repairs are made.
1.8 PROJECT CONDITIONS
A. Owner will occupy the building immediately below roof area. Conduct roofing so Owner's
operations will not be disrupted. Provide Owner with not less than 24 hours'notice of activities
that may affect Owner's operations.
1. Coordinate work activities daily with Owner so Owner can place protective dust or water
leakage covers over sensitive equipment or furnishings, shut down HVAC and fire-alarm
MEMBRANE ROOFING PREPARATION/DEMOLITION 07591 -2
Community Development Building December 8,2015
or -detection equipment if needed, and evacuate occupants from below the work area if
� P
desired.
2. Before working over structurally impaired areas of deck or areas requiring replacement,
notify Owner to evacuate occupants from below the affected area. Verify that occupants
below the work area have been evacuated prior to proceeding with work over the
impaired deck area. Provide temporary barriers and signage to prevent entry of
pedestrians. Remove any equipment that may be damaged and install tarps and
protective sheathing to prevent damage to interior. Upon completion clean all surfaces to
the satisfaction of the Owner.
B. Protect building to be roofed, adjacent buildings, walkways, site improvements, exterior
plantings,and landscaping from damage or soiling from roofing operations.
C. Maintain access to existing walkways,corridors, and other adjacent occupied or used facilities.
D. Owner assumes no responsibility for condition of areas to be roofed.
1. Conditions existing at time of inspection for bidding will be maintained by Owner as far
as practical.
E. Limit construction loads on roof to rooftop equipment wheel loads.
F. Weather Limitations: Proceed with roofing preparation only when existing and forecasted
weather conditions permit Work to proceed without water entering into existing roofing system
or building
1.9 REMOVAL,HANDLING AND DISPOSAL OF ROOFING MATERIALS
A. Codes and Regulations:
1. General Applicability of Codes,Regulations,and Standards
a. Except to the extent that more explicit or more stringent requirements are written
directly into the contract documents, all applicable codes, regulations, and
standards have the same force and effect and are made a part of the contract
documents by reference as if copied directly into the contract documents, or as if
published copies are bound herewith.
2. Contractor Responsibility:
B. The Contractor shall assume full responsibility and liability for the compliance with all
applicable Federal, State, and local regulations pertaining to work practices, hauling, disposal, —
and protection of workers, visitors to the site, and persons occupying areas adjacent to the site.
The Contractor is responsible for providing medical examinations and maintaining medical
records of personnel as required by the applicable Federal, State, and local regulations. The
Contractor shall hold the Owner, the Owner's Representative and the Consultant harmless for
failure to comply with any applicable work, hauling, disposal, safety, health or other regulation
on the part of himself,his employees, or his subcontractors.
MEMBRANE ROOFING PREPARATION/DEMOLITION 07591 -3
Community Development Building December 8,2015
PART 2-PRODUCTS (NOT USED)
PART 3 -EXECUTION
3.1 PREPARATION
A. Protect existing membrane roofing system that is indicated not in work and finished roof
surfaces.
1. Loosely lay 1-inch minimum thick, molded expanded polystyrene insulation (MEPS)
over the roofing membrane in areas indicated. Loosely lay 15/32-inch plywood or OSB
panels over MEPS. Extend MEPS past edges of plywood or OSB panels a minimum of 1
inch.
2. Limit traffic and material storage to areas of existing roofing membrane that have been
protected.
3. Maintain temporary protection and leave in place until replacement roofing has been
completed.
B. Coordinate with Owner to shut down air intake equipment in the vicinity of the Work. Cover
air intake louvers before proceeding with roofing work that could affect indoor air quality or
activate smoke detectors in the ductwork.
C. During removal operations, have sufficient and suitable materials on-site to facilitate rapid
installation of temporary protection in the event of unexpected rain.
3.2 ROOF TEAR-OFF
A. General: Notify Owner each day of extent of roof tear-off proposed. Contactor shall remove
only which can be replaced in the same day. Contractor shall restore the roof system to a
watertight condition at the end of each work day and shall provided necessary protection to the
facility during sudden weather changes if work is in progress.
B. Roof Tear-Off: Remove existing roofing membranes and other membrane roofing system
components down to the existing deck.
1. Remove and dispose of membranes, aggregate, mastics, roof insulation, sheet metal,
flashing, counterflashing, membrane flashing, fasteners and all other items not indicated
"to remain" or "existing" in the project Drawings. Remove materials in their entirety
down to the existing roof decks as shown in the drawings.
C. Remove existing base flashings around parapets, curbs,walls, and penetrations.
1. Clean substrates of loose contaminants such as asphalt,sheet materials,dirt, and debris.
3.3 DECK PREPARATION
A. Inspect deck after tear-off of membrane roofing systems.
MEMBRANE ROOFING PREPARATION/DEMOLITION 07591 -4
Community Development Building December 8,2015
1. Carefully examine the existing roof decks for deterioration, water damage, holes,uneven
areas,moisture, incomplete work or other unsuitable conditions for the proper installation
or performance of the roof membrane and insulation. Remove/replace any deteriorated
wood plank decking or metal decking encountered. Repair of damaged or defective roof
deck in excessive of the quantities provided for in the base bid will be considered an
addition to the Contract. The project inspector will verify quantities prior to replacement
B. If deck surface is not suitable for receiving new roofing, or if structural integrity of deck is
suspect, immediately notify Engineer. Do not proceed with installation until directed by
Engineer.
3.4 DISPOSAL
A. Collect and place demolished materials in containers. Promptly dispose of demolished
materials. Do not allow demolished materials to accumulate on-site.
1. Storage or sale of demolished items or materials on-site will not be permitted.
B. Transport demolished material off Owner's property and legally dispose of them.
C. Properly dispose of all debris from roof demolition and preparation on a daily basis into a
properly labeled trash receptacle as required by applicable regulations.
D. Provide closed trash chutes or other approved means for removal of debris to the ground level.
3.5 PROTECTION OF SURFACES
A. Contractor shall take all necessary precautions during roof preparation to protect the building
and adjacent surfaces from being soiled or damaged.
B. When weather threatens,cease work under this section and return roof to a watertight condition.
C. Contractor shall restore to original condition any damages caused during work performed in this
Section.
3.6 CLEAN-UP
A. Prior to the completion of the work, remove from the job site all tools, equipment, debris and
waste and properly dispose of off site.
END OF SECTION 07591
MEMBRANE ROOFING PREPARATION/DEMOLITION 07591 -5
Community Development Building December 8,2015
SECTION 07620 -SHEET METAL FLASHING AND TRIM
PART 1 -GENERAL
1.1 RELATED DOCUMENTS
A. Drawings and general provisions of the Contract, including General and Supplementary
Conditions and Division 1 Specification Sections, apply to this Section.
1.2 SUMMARY
A. This Section includes providing all labor, materials, equipment and supervision as outlined in
the Specifications and Drawings. The following is a brief description of the Work:
1. Formed low-slope roof edge metal flashing, counterflashing, cleat, coping.
2. Formed steep-slope drip edge flashing.
3. Frieze board wrap.
4. Gutters and downspouts.
B. Related Sections include the following:
1. Division 4, Section 04520"Masonry Repair"
2. Division 6, Section 06105 "Miscellaneous Carpentry"
3. Division 7, Section 07311 "Asphalt Shingles"
4. Division 7, Section 07531 "EPDM Membrane Roofing"
5. Division 7, Section 07591 "Membrane Roofing Preparation/Demolition"
•
1.3 REFERENCES
A. Factory Mutual Loss Prevention Data Sheet 1-49
B. Sheet Metal and Air Conditioning Contractor's National Association(SMACNA),Architectural
Sheet Metal Manual, 7th Edition
C. ANSI/SPRI ES-1 "American National Standard for Edge Systems Used with Low Slope Roof
Systems."
1.4 PERFORMANCE REQUIREMENTS
A. General: Install sheet metal flashing and trim to withstand wind loads, structural movement,
thermally induced movement, and exposure to weather without failing, rattling, leaking, and
fastener disengagement.
SHEET METAL FLASHING AND TRIM 07620- 1
Community Development Building December 8,2015
B. Fabricate and install roof edge flashing and copings designed and tested in accordance with
ANSI/SPRI ES-1. Shop fabricated sheet metal components in profiles previously tested by
NRCA or SMACNA are acceptable. Sheet metal components shall be designed and tested to
resist the following loads(The following values include a factor of safety of 2):
1. Velocity Pressure: -27.1 lbs./ft.2
2. Vertical Design Pressure: -96.9 lbs.ft.2
3. Horizontal Design Pressure: -48.1 lbs.ft.2
C. Water Infiltration: Provide sheet metal flashing and trim that do not allow water infiltration to
building interior.
1.5 SUBMITTALS
A. Product Data: For each type of product indicated. Include color charts and manufacturers
technical data sheet with material descriptions and finishes.
1.6 QUALITY ASSURANCE
A. Sheet Metal Flashing and Trim Standard: Comply with SMACNA's "Architectural Sheet Metal
Manual — 7th Edition." Conform to dimensions and profiles shown unless more stringent
requirements are indicated.
1.7 DELIVERY, STORAGE,AND HANDLING
A. Deliver sheet metal flashing materials and fabrications undamaged. Protect sheet metal flashing
and trim materials and fabrications during transportation and handling.
B. Unload, store, and install sheet metal flashing materials and fabrications in a manner to prevent
bending,warping,twisting,and surface damage.
C. Stack materials on platforms or pallets, covered with suitable weather tight and ventilated
covering. Do not store sheet metal flashing and trim materials in contact with other materials
that might cause staining,denting,.or other surface damage.
1.8 COORDINATION
A. Coordinate installation of sheet metal flashing and trim with interfacing and adjoining
construction to provide a leak proof, secure, and non-corrosive installation.
PART 2-PRODUCTS
2.1 SHEET METALS
A. Copper Sheet: ASTM B 370,Temper H00 or H01, cold-rolled copper sheet.
SHEET METAL FLASHING AND TRIM 07620-2
Community Development Building December 8,2015
B. Prefinished Sheet Metal flashing: Aluminum sheet meeting ASTM B 209, Alloy 3005H25, or
alloy and temper suitable for forming and structural performance required, but not less than
H14, finished as follows:
1. High-Performance Organic Finish: AA-C12C42R1x (Chemical Finish: cleaned with
inhibited chemicals; Chemical Finish: acid-chromate-fluoride-phosphate conversion
coating; Organic Coating: as specified below). Prepare, pretreat, and apply coating to
exposed metal surfaces to comply with coating and resin manufacturers' written
instructions.
a. Fluoropolymer 2-Coat System: Manufacturer's standard 2-coat, thermocured
system consisting of specially formulated inhibitive primer and fluoropolymer
color topcoat containing not less than 70 percent (KYNAR 500) fluoropolymer
resin by weight.
1) Color: To be selected by Owner from manufacturer's full range.
2.2 MISCELLANEOUS MATERIALS
A. General: Provide materials and types of fasteners, solder, welding rods, protective coatings,
separators, sealants, and other miscellaneous items as required for complete sheet metal flashing
and trim installation.
B. Fasteners: Wood screws, annular threaded nails, self-tapping screws, self-locking rivets and
bolts, and other suitable fasteners designed to withstand design loads.
1. Nails for Aluminum Sheet: Stainless steel ring shank roofing nails
2. Nails for Copper Sheet: Copper or hardware bronze, 0.109 inch minimum and not less
than 7/8 inch long,barbed with large head
3. Exposed Fasteners: Heads matching color of sheet metal by means of plastic caps or
factory-applied coating.
4. Fasteners for Flashing and Trim: Blind fasteners or self-drilling screws, gasketed, with
hex washer head.
5. Blind Fasteners: High-strength aluminum, copper or stainless-steel rivets, to match
materials being fastened.
C. Sealing Tape: Pressure-sensitive, 100 percent solids, polyisobutylene compound sealing tape
with release-paper backing. Provide permanently elastic,nonsag,nontoxic,nonstaining tape.
D. Solder for Copper: ASTM B 32, Grade Sn50, 50 percent tin and 50 percent lead
E. Elastomeric Sealant: ASTM C 920, elastomeric polyurethane polymer or silicone sealant as
indicated in drawings; of type, grade, class, and use classifications required to seal joints in
sheet metal flashing and trim and remain watertight.
F. Butyl Sealant: ASTM C 1311, single-component, solvent-release butyl rubber sealant,
polyisobutylene plasticized, heavy bodied for hooked-type expansion joints with limited
movement.
G. Weather Resistant Barrier: Spun bond polyolefin weather barrier.
SHEET METAL FLASHING AND TRIM 07620 -3
Community Development Building December 8,2015
1. Available Products:
a. DuPont Tyvek Commercial
b. Dow Weathermate
c. Approved equal
H. Flexible Flashing: Polypropylene film faced with butyl rubber adhesive compatible with the
weather resistant barrier; 9 inch minimum width.
1. Available Products:
a. DuPont FlexWrap
b. Dow WeatherMate Flexible Flashing
c. Approved equal
2.3 FABRICATION, GENERAL
A. General: Custom fabricate sheet metal flashing and trim to comply with recommendations in
SMACNA's "Architectural Sheet Metal Manual" that apply to design, dimensions, metal, and
other characteristics of item indicated. Shop fabricate items where practicable. Obtain field
measurements for accurate fit before shop fabrication.
B. Fabricate sheet metal flashing and trim in thickness or weight needed to comply with
performance requirements,but not less than that specified for each application and metal.
C. Fabricate sheet metal flashing and trim without excessive oil canning,buckling, and tool marks
and true to line and levels indicated,with exposed edges folded back to form hems.
1. Seams for Aluminum: Fabricate nonmoving seams with flat-lock seams. Form seams
and seal. Rivet joints for additional strength.
2. Seams for Other Than Aluminum: Fabricate nonmoving seams in accessories with flat-
lock seams. Tin edges to be seamed,form seams, and solder.
D. Sealed Joints: Form non-expansion but movable joints in metal to accommodate elastomeric
sealant to comply with SMACNA recommendations.
E. Expansion Provisions: Where lapped or bayonet-type expansion provisions in the Work cannot
be used, form expansion joints of intermeshing hooked flanges,not less than 1 inch deep, filled
with butyl sealant concealed within joints.
F. Conceal fasteners and expansion provisions where possible on exposed-to-view sheet metal
flashing and trim,unless otherwise indicated.
2.4 LOW-SLOPE ROOF AND TRIM SHEET METAL FABRICATIONS
A. Fabricate in minimum 96-inch long, but not exceeding 10-foot long, sections. Fabricate joint
plates of same thickness as materials being joined. Furnish with continuous cleats to support
edge of external leg and interior leg. Miter corners, seal aluminum watertight.
B. Sheet Metal Flashing materials and component thicknesses are provided on the drawings.
Where material types are shown and thicknesses of materials are not shown provide sheet metal
components of the following minimum thicknesses:
SHEET METAL FLASHING AND TRIM 07620 -4
Community Development Building December 8,2015
1. Fabricate copings,counterflashing and edge metal from the following material:
a. Prefinished aluminum: 0.040 inch thick,unless otherwise indicated.
2. Fabricate cleats from the following material:
a. Aluminum: 0.050 inch thick,unless otherwise indicated.
3. Fabricate Fascia board wrap and box gutter from the following material:
a. Prefinished aluminum: 0.032 inch thick,unless otherwise indicated.
4. Fabricate box gutter spacer from the following material:
a. Flat stock aluminum: 1/16 inch thick x linch wide,unless otherwise indicated.
5. Fabricate box gutter support bracket from the following material:
a. Flat stock aluminum: 3-16 inch thick x 1 inch wide, paint to match gutter, unless
otherwise indicated.
6. Fabricate box gutter support bracket from the following material:
a. Flat stock aluminum: 3-16 inch thick x 1 inch wide,unless otherwise indicated.
7. Fabricate overflow scupper, picture frame and conductor head, downspout, downspout
brackets from the following material:
a. 16 oz copper,unless otherwise indicated.
8. Fabricate trough wall flashing and through wall counter flashing from the following
materials:
a. 20 oz copper,unless otherwise indicated.
2.5 FINISHES
A. Comply with NAAMM's "Metal Finishes Manual for Architectural and Metal Products" for
recommendations for applying and designating finishes.
B. Protect mechanical and painted finishes on exposed surfaces from damage by applying a
strippable,temporary protective covering before shipping.
C. Appearance of Finished Work: Variations in appearance of abutting or adjacent pieces are
acceptable if they are within one-half of the range of approved Samples. Noticeable variations
in the same piece are not acceptable. Variations in appearance of other components are
acceptable if they are within the range of approved Samples and are assembled or installed to
minimize contrast.
PART 3 -EXECUTION
3.1 EXAMINATION
A. Examine substrates, areas, and conditions, with Installer present, to verify actual locations,
dimensions and other conditions affecting performance of work.
SHEET METAL FLASHING AND TRIM 07620-5
Community Development Building December 8,2015
1. Verify that substrate is sound, dry, smooth, clean, sloped for drainage, and securely
anchored.
2. Proceed with installation only after unsatisfactory conditions have been corrected.
3.2 INSTALLATION,GENERAL
A. General: Anchor sheet metal flashing and trim and other components of the Work securely in
place, with provisions for thermal and structural movement. Use fasteners, solder, welding
rods, protective coatings, separators, sealants, and other miscellaneous items as required to
complete sheet metal flashing and trim system.
1. Torch cutting of sheet metal flashing and trim is not permitted.
B. Metal Protection: Where dissimilar metals will contact each other or corrosive substrates,
protect against galvanic action by painting contact surfaces with bituminous coating or by other
permanent separation as recommended by fabricator or manufacturers of dissimilar metals.
1. Underlayment: Where installing metal flashing directly on cementitious or wood
substrates, install a course of felt underlayment and cover with a slip sheet or install a
course of polyethylene underlayment.
C. Install exposed sheet metal flashing and trim without excessive oil canning, buckling, and tool
marks. Provide elongated holes for securing to allow for thermal expansion.
D. Install sheet metal flashing and trim true to line and levels indicated. Provide uniform, neat
seams with minimum exposure of solder,welds,and sealant.
E. Install sheet metal flashing and trim to fit substrates and to result in watertight performance.
Verify shapes and dimensions of surfaces to be covered before fabricating sheet metal.
F. Expansion Provisions: Provide for thermal expansion of exposed flashing and trim. Space
movement joints at a maximum of 10 feet with no joints allowed within 24 inches of corner or
intersection. Where lapped or bayonet-type expansion provisions cannot be used or would not
be sufficiently watertight, form expansion joints of intermeshing hooked flanges,not less than 1
inch deep,filled with butyl sealant concealed within joints.
G. Provide 6 inch wide back-up plates at end laps of frieze board wrap and coping. Provide 2
beads of butyl sealant on each side of the lap.
H. Provide 6 inch wide back-up plates at end laps of coping. Provide 2 beads of butyl sealant on
each side of the lap.
I. Provide 6 inch cover plates at coping to edge metal transition.
J. Fasteners: Use fasteners of sizes that will penetrate substrate not less than 1-1/4 inches for nails
and not less than 3/4 inch for wood screws.
1. Galvanized or Prepainted,Metallic-Coated Steel: Use stainless-steel fasteners.
2. Aluminum: Use stainless-steel fasteners.
3. Copper: Use copper or stainless steel fasteners
SHEET METAL FLASHING AND TRIM 07620-6
Community Development Building December 8,2015
K. Seal joints with butyl sealant as required for watertight construction.
1. Where sealant-filled joints are used, embed hooked flanges of joint members not less than
1 inch into sealant. Form joints to completely conceal sealant. When ambient
temperature at time of installation is moderate, between 40 and 70 deg F, set joint
members for 50 percent movement either way. Adjust setting proportionately for
installation at higher ambient temperatures. Do not install sealant-type joints at
temperatures below 40 deg F.
L. Aluminum Flashing: Rivet joints in aluminum where necessary for strength.
3.3 LOW SLOPE ROOF&TRIM SHEET METAL FABRICATIONS
A. General: Install sheet metal roof flashing and trim to comply with performance requirements
and SMACNA's "Architectural Sheet Metal Manual." Provide concealed fasteners where
possible, set units true to line, and level as indicated. Install work with laps,joints, and seams
that will be permanently watertight. Provide back-up and cover plates set in sealant at end laps.
B. Anchor sheet metal fabrication flashing components to resist uplift and outward forces
provided.
1. Interlock bottom edge of flashings with continuous cleats anchored to substrate as shown
in the drawings.
3.4 CLEAN-UP
A. Clean exposed metal surfaces that interfere with uniform oxidation and weathering.
B. Clean and neutralize flux materials. Clean off excess solder and sealants.
C. Remove temporary protective coverings and strippable films as sheet metal flashing and trim
are installed. On completion of installation, clean finished surfaces, including removing unused
fasteners, metal filings, pop rivet stems, and pieces of flashing. Maintain in a clean condition
during construction.
D. Replace sheet metal flashing and trim that have been damaged or that have deteriorated beyond
successful repair by finish touchup or similar minor repair procedures.
E. END OF SECTION 07620
SHEET METAL FLASHING AND TRIM 07620 -7
COMMUNITY DEVELOPMENT BUILDING
LOW SLOPE ROOF REPLACEMENT
17146 MONUMENT CIRCLE
ISLE OF WIGHT, VIRGINIA
December 8, 2015
Hentz Engineering Project Number: 15116-110
DRAWING INDEX
COVER PAGE
SHEET 1-CONTRACTOR MATERIAL STORAGE&STAGING PLAN
SHEET 2-ROOF PLAN
SHEET 3-ROOF WIND UPLIFT PLAN
SHEET 4-ROOF DETAILS
SHEET 5-ROOF DETAILS
SHEET 6-ROOF DETAILS
SHEET 7-ROOF DETAILS
�_ti,$OF WjG,
VIRGINIA. -'1
*1634
INVITATION FOR BIDS No. ##-####-##
COMMUNITY DEVELOPMENT BUILDING
LOW SLOPE ROOF REPLACEMENT
17146 MONUMENT CIRCLE
ISLE OF WIGHT, VIRGINIA
HENTZ ENGINEERING PROJECT NUMBER: 15116.110
LOCATION MAP
/_/ Hentz Engineering, inc °°- '« ; sl!��
Building Solutions w y ` �A�r" ✓^�;� `t,
750 Lord Dunmore Drive,Suite 103,Virginia Beach,VA 23464 r S r
Phone:(757)961-7224
14, 40 • /-44t ' `jl"
:� .4444
fyp` { rl Ic L S �'x \
Community Development Building
•
1 -
.-,
. E ,
V,A •_14
..▪= -
Contractor Staging Arca _x. ffi
Nor Fully AdAatd 0 OP R
W 'n
EPIN Manbrate
.0 5.
l_l CO
' ,: ".1% %,-' , P,\•,,, ''''-1 --'-"A•P',.„:4,. 1 'EFBEE°3333333-Fil 11140-Inoo
4 amass=
1111111111111111111111111
5.
.. - ., l'• ''')', , ' ' . i '1‘,f.^.e.•,,,,:,'-',',, "
. .rom frit
, r .'' Typical Roof System-Roof Section Al 4 °. ..,,\
91'
Neve Fay AdTrrn11106fr
CM,g1ILA..
.- N * , ... ,
UM NI emlunc
, ,. ;.• i 14..,■ ' 1 ' :. , ''''.'I'y .' 'a' ' N 1‘.....le*a 1311)
, ■■■__ _..,-. ._.■...............1.
■ % 11333333333333333333 Nov Wro fr.T.0,.., % 4,
. ,. , E133333333333333EEE'833 Nip.,=nu hude., ik,,,t,,,s0,
. ,, , ' NA. ,-''' , A : li, 3333333333333333133333333333333M33 sx. dy,,,,,,"
1-: 933333:83333328$193393$6333333333 m
.." 33333333333333ZEEE 93333333333333333.-
S3333333333333332E33333332E1333333333
• 'r . -:,..,,, .1 i'''::''^- 4,■' 1,'V., 4'A, ^ . , 0 ,,,s, , , ,,,,,
\ 13333333333333333M333333333333333333 E*,_ m*,nt,i,
I W II I -
4. .--oilit c- ,.,..:-.,,, ,,. , - ;.-1.... - •*" s'd ?P.., ,
, . Typical Roof System-Roof Section 42 cr.
' ',41 • „ '3 J " '• , ' New Fully Adhaed DOW
' ■ ) ',,,O#• -:
' L '4' DI ' ' 144'1",'V-.711."1 . '.':4' '4 V- 'k.' ' ''.4i.'• - .— -.-------=.--■—■m ir'''',=72... 2 Ea'-6u,,c,
' EEEEEEEEEEEEEEEEEEEffi .
° :1: ' . te'° '-'=: ''P"'I )<N1,° \'`+'. .. '''• ''' :$ 1':°,. ,°.''''2121*,:l.' '':-.. ' : "1,%?,4::.i.iit4"7 —
1 9333333333333333mEEEEEEEB3333333me ''''''''''""''
________________
3333333333333333:31333333333333333333
,„ 33E133333EB33:EME1333333333333333333 E,,,,,mg ma wa = co CA
0 E-■-•
&•,...,' At'', •'-' ' t1":r i•,..hrtr : ••
co ce o
1'4':: ' ' * 17 Typical Roof System-Roof Sections A3&A4 CI
11) ..—■
. , EMI Alcrobrzu = r•-. .4
...1 .
No.W pa l'oo17,411 E 3
' pob.,....k.b... 0
(...)
- .,t4t.,-. ,--e" ■., ' -t4 4#410,. t'-.-4.:,i. ,''''.,-,..:.°:L ,, ot....‘i.1...
-
4-. At4.-..,..*',.-1.'l;•''"'' — .. 433333333EEEEEEEEE93333333333M333333
• A '
.. .
jr W W I
v:4'1 ‘.t' `' '--:-47M 3'.;:',,t?:'-:-.. IA' ,! .,1; '' L ,. - Typical Roof System-Roof Sections B1&132
-' i •1„ 4, 41•'',1,•:-• \:‘ic44( :4
IF ' . . -1'..r% • "" •••••t',•'
•— :c•" ‘, t..,P ' , :',34 z
ir:/;•1. I $••:, t
i .. , •-;'',:, - , . L .'*- ''''':'!r: ''' ti-4'''''''.+'''71i';',.: .97
c . .... 04 ..=1-10„4: 1;... ..44. ,.. .....3,-,..0, .., . ..
--,,„,
, P
Ci ...'
4 i
a 1
.2 -.
a, :4
a, .
.5 ,!,
b.c) ,
g ., ..:1
r.g 1 Li
Contractor Material Storage/Staging Plan
g rd
,..
0 I g '
`CJ
' ±�`I1 Plan Legend General Notes
Ok" A,' Roof llem I. [mmatwmprovikaR tmlitydiamayatahemmarad �o
.y mmtiimlm'mr]ay to pngamwat Jtn
v+ 0 • PmenatiooPWn 2. CanaalorOA fickl unify all mauancromu and quantities prior a2m2
01 ' Roof Construction Plan m Vaal Pipe to bidding.
R - - - 1. Gmtmamshallprm;dcttaa,aypmtammtnaR:mraes a
D] t� Sm4:lIJ'•1'.0• ®Scapakmm Camara shaIlpmupmmmplaimuf wort
•1 0
�R° v Scupper d. Cmaatmshu➢mtOTeth or»stnwtoaewettpJ condition al k: .°
. yR� . -
the and ormcnerk day awl Sha0 man&necessary protadmm
Q 0 CS O.rI Scupper trier liryawingsuMm ecvnn<pmgnirwnt1 is in proms. ,�+E .�.
.: sryhw Vol C fl arull ma i&moray baduda and gmmp utm aZ
-
S lanky pnwmcl.Drib
NevY•ppaa ® b. CmmnorrEoll parmm emk so m not m interfere Wk the kl. 3 ssliN
New1S•Pa /�. !oa(Hdr ®Sikh. operation and.hill mwdivt po m�aance.up raNity ��
root Cr4ln ____w__Whdeil4 pmlmcl uhcn.mk.in'
]. lmmmrtem dais'bane lava i m ta ground m a notmRed
d as byho'olDashmute a cme FF
N0)3',1'Tapad
��ws� O Demolition Notes E
CO DI. Binh,rool-,hto be rmmddd¢po,r oL Prori&e0e. 0 co
deal to match De arisen dad pmpe d grade.The ].SD Op Pr.maul deck etv4nated ova Ge opc®g and rym from*1m �4ay'
b�— lost Same oermeW decktnjo• aaith UK4,takIODM e
ink IF
E. 0 N selfmt9mgxm]macvadmce.;0ktryimemauofthe
St..]Dealt Costive ISDIC � \
US D3. Rammxdm3 the top ofthcexisting mammy wall doves to tic try ^qo
of abss rustio3 mail deck ofroof crow Rh.Win god page wens
New a ends of removed mmaoyeall. ""ONk4tiM4
A U3. Was aisring bole kmasomy wall twallww fir fiamlUtim of
the new P'vide a J'high Dra4 wall a.m.box.
D,. Remove and&ose of existing PVC dmampm..
'� ,,,,/-fora Oic et D!. known and dispma of existing roof drams.
4 Db. C0 holrtdcough eusdag m a m m y m Gmiata the C
r tv�� O s ■ R aRa fihean nppamedhro,ctgpcn a,
UI C�{ SG` 41
Nrn1YJ'Tapard 3 (� �`I D1.Remmeadstmdbtiet mvaeaaymmsaRnn tmoupb m Jo
msuladow Sump i O 11 wall llu�b Nvrideur+mirkm m•m eaiumg.
0 't c„,..2 Construction Notes E a�i
`�� t W6 C2 Cl. Proaidevw muplm¢dat®ltheatis®geawvmvmtpipe O E '
\v r/] I - 13'rMctl smfa¢o(thmarm(m�mbrmcprimm0admP. N O = c_0)
0 _,Sy_ 3p_______wr______w,__ > O C
DS �Da— �-' C3. Praidctwq nrymat=facthe cmtmg nn apW d C' O
X' / p elzpboaecd4es.ALT tkimu0aionoft eun-EPD74 rmf 03 NI-
tl z Dl synmkprmikmmged WkWdlea,Mmsralmtm3fi'm aq0 O
if ion Quin p ms0
courant!etolvahm to roof eaZ Drama and ware
=VS^ rn-t
�./
El;:
�� CO. Provide mwl1%10V3'a 3'cone.rplaahplak,at tic E p•--•
r+aI p v duchvge and o03)w aoDDerdow1pom.3)1103000) 0 J
69 g EPDMmdb pada uda mall splmhI I wail padam woad U
� Q I eg 6'ow Lau erh side ofnew aplvh War
•N CJ. Reuse mstIlPdlmsptm.m®xs new gar.
■
C3-1 NrtC.• Cl. Provide roping m edge meal o-msilio.T0yiral Coping m Edge
foot Cti• hlnal Lap DamT wished b.
New 3'a4'Tarred
P InaaJaam Swap tl ` [b. [ntadhate,cmmallaumnlftlU wiG lslen(wtigk fumy.
��� Won
'II.
Z
coo a yv
\1° 0
•
a
01 et I
N0)K,'prr P a-U=
foot Wad ' NvY"per
S, ��' (ant[ticks B
v ,
,c,-0 n:
•
® I
}-WC]
N0)k" l W1 kk
foot[tirk�ct tl V.,' tl„
1 Dt t�a w ty.
•
` _ CI e SE
IIII.4/84
T `�f!rasa® wrora®m ym.ra® yrom® W..av® IT-,® ter-ra® vr.ra® rvrvr® r. r
I woo ',or
3
4
a
4
7
'a
z
3
4 i
0 -
a
SO' co--
f
,
5 Ao
4 _o
..y
f
a o.
Steep Slope Roof Not In Scope Of Work b
w
5
4
° ,7 4 ` \
1
G O .
o 4 -1 - \
i
G 1.
$ —
'4 @yyy
[ q E .g.
;
R s i
R"
7
44
Project Name: Community Development Building �y�"�` 4,4, Drawn Checked Number. Date: Sheet:
Hentz Engineering,Inc. Low Slope Roof Replacement
S r By.
f -; e ums Wm..
1 i fr ,�, sw,,,°,.,-„„;� V.z„, 17146 Monument Cirde � �� sa isus ito t�oens 3
°m° "' Isle of Wight,Virginia it- „,"e
•
.
Nov Bp.,Coated Mr Alm :.T
- Coping...Bahlb Plan _ N
VI
New nigh Dasily Wood Fin \
Tam Edge Nov Mile Fluhin ' an
6 Nn Ryoafoud ONO'Aron Coping A'
Bah Up Plain Ni
?kw kT a
N.v'[wc 0.050' �_ Ntw Niyh Density Wrod Fla Tgvcd Edge &ilmt O .
,,, .., Alm Cle 0.D50. Nov0040'R5'm Cwmd Drip Edge Nn Pnsson5emmsn
(/// wl�'1wg Stainless p►,1� Nov Cw30.050'Alm❑maamda/�' g N.v'Rasoe SEtidge Stripping Fly. 0.0 4 0. m
/ I��•� Iona Soles.Steel Rafing Us.'ae.,BB. Mad sward a/1 Stamina SUx1 ,mg,,,,, alad mm.F'onto Field Membune Edge stand a/1%•Stainless Sin Drip o
�-(era de
Cg j ►��♦� SleelRmfNLm 2'wm FuM AI®60me Roofine Nmisul"wee.smgytd E .�-h
jj/ �.�♦�♦�. 6'ac.,ayp.bai n � 1 bah side of pampa Rwfin9 Nails u S•oz..stagecrtd a
/ ♦...1 udn New lYUn Cwan5alml New'fuBya&ned0060' = ,'^
Nrw Naia j/ ►���� ;� E.ining Y•sb«thiy uew005n co.,Vin Clean
EMU Mnr�bmne �� NnCona.0450"Alum Clot aZ■
/j ♦���1 �' coed w/Aomless Steel Roamg ,�1� word wllY•stamlm St«7 33333333333333 CwanSealm /���� •r.. Ndls.ae•n<, f/
�♦�.•l•4 Newweuher Ming Banger / Nov Y'FlYwmd 56whie '- - ./1,117 Exi.tinR M<d / ;% n Rtwfmgxmlem6•a.<. S
Existing cing a jA �������4 New Fu11 Mimed FEN Nov D.D50'[quo. Alm 1I Fully EPDM Ilea ���,1/ 'y..
Blocking r II NM D.DNr Fun 111111
Pa.µt Nall Fishing provide Wl lWhing w/6•aide Rack Up I P Wan FWbmg J't.1 1/
raping y wl(Lob hnmmatimm Phtra 1/ J
'V..�.� agiidbYAlmufaron 1� Novtwp Nov Fly Adh1d a06P MIA VIII // l%/® j/ New;•Plprool Seeahivg
►���� New Cwt 0.050'Alm Clog Sdml Aladale ��® NmY.'pafwaioveJ I/
F�gAluawy 1I ./® Polyi,et5mmteinvdaiq I. Eab®g K'FlriWSba�e
1 Nn lap New Fully goal w/IY..•SubJmSteel II.-- I —1 Ir A sm.J'Ibi um I� Les S.!BEEEBEEszersame Wa0 Salm1 Alehobrnw prong Nall at 6'oe
.�♦�♦�♦� _ �A .-_ ,<I' New 5.Goer Evsiio wins eloeFina j/ New Fulyndhaaaaom'Froff O m •
/ ' ►.���.;� Nov High Wong Fibs ► al(imnSpaaCfemr j�� NtwY.'Per foaT,.... 8 V. Nerlap Mobcaps •••���G...���
/ ►♦♦♦.. � Sppm Bmam spade /I.! 31"min. uiw I/ Scalm rl,ap,61,' ® - a'.e}]. _ /////. M•no,spawsilwldwly 4S'mmurimia, II ��
jj/ r' .Ian TgmedEdge - befamed In fins hba3 ►♦��♦♦/
� ►, off nmJSyaad / Using Moil Deck 3® � '
�♦�W v#4//. Nag Otto•Krug:: Vii- -_ ahlw<Iywl Brutm
Existing Masonry N.(Wan i
j ����1„® \Vera FWhinidewide l�
Ng.'Polimry'murue ������� Eaiming Wood Blocking ►�����1� y
/ / Bank Up Phan IyI��IyI/
Insulation. Nnhe Fascia Board thaws m ��
///�� Existing Eat0io Wood Song gat F�gMSmv Wall
4 ••♦♦1 N ow Y r pa foot Taped S e m m u l m w t or/n e %//////// Dancing Alai Dsck Ili'oe.slob Exiling Nlasnuy vl
Polyi e oa no weeps ul6'o.e. Mnvmy Saesa IF at Nov4'Pol2 ate
4•mn Nebo EzmB NrodB1«3iE rsuhtinn 2logo
Ncw 0.032•Kyoa Coated
aiming AIM Deck Fame Bunt W05 Riving Mail Deck
EavmaB Wad BINA* Ol
Note I:Rini&mechanical amtimum of fida sliest as Note I:hocidenceeEari<il lamination ofiicld mliMa<u required by the Mmuf inn. Note,hol a mechanical imnioatiw dfi<M lsmbrme as rryimd by the llanufanwa. C
minitdby au Mandan-tom 57- CC]
O Parapet Wall Flashing Detail xr , O Parapet Wall Flashing Detail y O Roof Edge Flashing Detail �10 O Roof Edge Flashing Detail s� °° cu _CO
xwut-rh ewugah 1u1.J. C N U'Ode
E v
Existing SkyiHh0amwe ad New W000Cwaxgalmt d�
sc�aO maEOr Dasme ._ L
No1EgNF0a ructetd Foisting W'eafa Bmie 1'wi&BaryITmem Nwei by N O O Of ce Fanwniormapnli& _ Tambimw Basn.odal r... w'mr(1van5nlm New SelfAdbad Udo,by o, / v u_
NiNc.Nov OOJO'K)m Coat,Alm 111• Nov Self Adhei ilaili Manhole ��� \ msu0'mdee msimE kb �4 .tZ tO O
CmiwOaAip �►, g a ��1I, hmJ.rhrym uwo&6'vsm Lp ,/�� =N Cr a-�-.
Fautig Nick venm.wmn.eadarnla<mr hone //.j I '� 3.--1
Ncw 0.0.10•Kyua[aatd Alm Drip gcig®gFlWwg ibe euWlaeon oftbcnv Through Wall Flashing
Edge a mod wl IY•Soodmswa Nov fun Nad W'ap,a la'oz. I Nca 0.040'Alm Drip Edge sawed ��� OE J
Rmf,o..1.I.O.nsoggad I r ♦�
• New 30 of Copper Though Wel no/ Soul Roofing Nat U _ U
N'cw Cone 10050 AIOn nut Ntw lap g Poetic 21 ///.1 1'o.eMaaiCnd �i Stripping�Sly.Sknda
Ilnbme nth J
saadwt W'S6mlm Stal Sealant ���, �5, s a Feld Mmi,me Bp.J� New Coati 0.040-Along
Roofing Nails a 6'ae c^ j/ New eel lnaake\'mten at Nip Ggeserwdrl y'
pg�t� t�I New 3002Copps COwOertlubmg /i/ 1 dwlrvn Ul faavmn at r r1�+ Simlsg Sigel Rwfin Nal.
1►,� � /� O eahMerwl 6%.i - Nreloanc had o.0a0'FPDM 1'o.c.tagged g
Nov Wee CmbDSeella 1�//�t� Fes N<w Alm Tnmbwion Arnaud I'�- '-j Alankx Novi
II I�F� t�/� u13'O.a wlllmvonsa AUbrw �/j New Polprol�ne Salve °'i� SmIW Nn.[wCO.05r Akan Cleat hi
New Y'PlfvmJS3taaip, ` /►,�����•, Exhiig ReM �,.. secured w/IY'guhJm Sled
•
de New00Ny FWly Adhered}Van
secure aobiakmdu top u9 I W New WnatLiaQScalint �A Flashing — Rna(m Nmb ue'no. Z
N'is g,rlywaoa. ��I a
,taws and CAN wtWar I ` wdlPtq Dope
Ilammaset Anebra m F1'0.e II Vin OI �GWIy AAiercd HMI New Full Adhered MO'Mgt Is Existing TAG peck ' , AAmdrFul
1
Eustmg35'Plywood angling �1 NMI',fool Twined g Membrane New[,p .�f;\ , •' ` Pargm Wall Flashing a
II Pollisns}amse ho,lno, New Fun Adhered 4.064. Nov l� Sim
Y ` Newt'Plywood Shaming NnY•pr Won Taped
Now 0.060'Funy Adtrrd II O'�0u,lvmmamh.. Mgt hhmmmt Sealant j - \ Isso9'aa0ue huutmeq New fdy dprnd
1 lei htoficeismg wood .'��` Po / ON,EPDM N
N'aa Flasbwg �I blogrlmg - �/ Nat Cawnehearm& 11i's'rm dihm
16 ■ ` �,% 5ecmmalrne. M�absmt■Nov Fully AdhadD060• I������ �� 0 i//'
FPDAI risks 1...♦. 1 E.mwpA5eu111 1 I∎ E.isonH Ma Deck yy•
II/������ �i Nn'PN vAmcgWm ,� d
xtrJ'Pdyisorymuwae �1������ Ea'amg\}'cad Ban«tint ��Sty j/ , .,`, Nokl Neah101VaodBloskmpsmvudw/ .1333 3333333333333333
IzsulatinOlaycn 1������ Purist Wood(lob �//////� mad / `� .� a
EVaamg 1 •�•�� Nov 4'P011'hrcyloue Foisting MUVmy Wall /`t;�`� y ,
AIeml Dec %1 ..:.♦. Prsory'oueT,"`' E'stng Naal Dock cad 2 X'
c Plywood
ol(ihim�mmsa /�j/_� Na.Y•pa foot 'n
33333133331333333 II►.�.�.�.�.�-� S/5.min.iiekm Anchor,at Ir o.c. , Tarred Li asss
®��I•������ Existing Nitta]Deck P tics.we N'o 1
Existing Wood Blacking
®1333,I, 4 oottl:Provide meeb�salterminawm Nnt<I:Roo;a.methmkilASmhwtionnrfidamaotmmeasmurea min.1�®1_�; ♦♦�:.:♦: fMielfm�brmeaaan'i•'dbythe Nate l:Rmidemecbld oSWoIIiwoffiddmanbtleutrytmdbyth eMmufaaea. s' by Mmofactact �' q m q4
Nom 2:Provide newllunugb N'aa Flashing to achieve mg'»®m USOFlUhmglinghtu lktighcu poet ord.new goof III 3:Rnwve eiiamguplull shingles u neensv5'm faelliiate the installation nflhetryla«mmt tongue and gmn.e deck 7)A
��►�����1 alstan,New TNoulWall Flashing slunddmwmuthis level dwughowteHck may well.ITO.iduitlpmary appwm boats.i01000 new uphalt shingles Im.6:Ae.umg.Nv plazsmmishvooksto b epruriddby Irk ofWighl None I:Provide snalumihalls®wiunaffield mmdrlesst9vdby the MmufoNOa. F.dvugMWOttk �ym �6°
twat doing gashing installation Cluny.Fast=sbingla with 5 Caroms pa 16aHlt.
£d.
O Skylight Flashing Detail >ee..,„b10 O Wall Base Flashing Detail Nu tw,.110 O Wall Base Flashing Detail . x.�3.1.A.10 O Wall Base Flashing Detail g,10 r+'''
1,.1,.10 y
S a t �{`oa[.g<® I/1hrc® yrr ® NW,-® Wr,® 3r1r Mac® 00.14.® M1aa® I I/ow® 1--r-a.® :\
•
•
•
Restore aMarylau Balnuu Coping New Po11mn1 Sealant
Joints w/New SS am Seal.and ,P
UaknRad,typical wa➢Coping Nov W IT&1
loom,Rake Afmaml'4pA - j/4 _ .1
New 0040'Kiss road M.
Regis Mwmd l'mmtmladdngm Lel
new Mw
mlTryln __— `
• New Using oIngsgs/Seth / / 1 New Alves Tmnbaum BU Swam �1-r• ———
Nn'PoI}v Am<Scalmu o
w/Ilmvne See AncMmull'oo � uL•a
Existing Copper Ensiling °. % LN, =-- V.,.t.' .,b
New Y'P.T.Plywood Skslhieg ` o'-'E
New Alm.Simi..gas naffed , ' New Wain secured w/l awl of War llammer -- — •y
San Anchonull'as \' New 10"diameter MT Finished
n`.Z
wl Hv®ass Mrbu alll'o.c. (WritrSealal `�j Alas Single Cr.VenoLmr New lap Sealant
New Ve PlyumdSkgataii mrd New 0M0'Fully Adhered FPOM `r New Alva Curb Rootglmm®8 New Stainless Steel Ur.Bad I S
wll mwaof Y'd'Ilm®mn ` �j Wall Flailing 1,1 1St Bascsiubfiton l0'dimna
Maim at ld'ne. 1w A `.. Single Cmai lams New Wats(1.11Sealmt �I�-
Nov Fully Adnertd 0U60'EYOM N.Lep j�j
New 0.060'Fully Adhered Membrane Seal. ` Nn HO Domed Gashed Sax, Nn Prtfmbncud FPOAI Um
FPOAI Wall Hailing 1 `� Ep sid'
New My Adhcrzd0.0W' J 1■,
FPOAIAImMa New lap �`j�j .I,■, N.Fully AdhmdOtkO' em
� EPOM Memk®e New lap p�'.EmEEEEBEEEEEBEBEFEE 9/ New 0.060'Full Adlerd
aaxisig WWYIGNNQ.....- � i
®®, / , `j% Nn Fully AdbmdO.UA' New beery �I NE"
EPDSI Man �Sea1. New:All Wood f.LSb
/�/ New per(ant 7�emd i�% ___ I G^ jta 4 nasal
Newy'per(omT New!a6 Wood Wee warred m .aaV��
Pol' and P°lysmyawm hruladoa .� dakw 6'a.a. Newt ynaommT oO 'h.. 4
yasogmmn[baulatiml OMA4�
U$'mb.thi[kmu OS'min.tldckiwu .��
Existing Maurmy Wag EautmgMUmuy Wall y'nw.adorn
Nw1$'perloot Fai5A0P AICW DaI Fsistmg Metal Deck •
Tapered PoIynayanuate .
Insulation nickel NeOrgcrrod Tpmd
Poirim ramam mwanma •
Existing Mvvl Deck Note l:I'mvid:mahm¢al termini.of Mg minimal u required by t iMaamus. lii.min.@icbme Of
Nolo l:Provide mNwial lamina.of Mg number.uregwred by 0e Manufactures C
Nose l:N°rikmnAmiol tnmbanvn of Aeldn¢mhrnneurtquirtdhy the Flmufanwn. F'ritE"SMavl Deck 'a C
Note II:!inside mech®ral tnmmrom of field meanmme u wind by the Abmufamura. 5 tL
co fO
O Parapet Wall Flashing Detail Wall Pace Flashing Detail Curb Flashing Detail Vent Pine Flashing Detail u
se,..lw.T.ule 10 kg:Mick. ll sma.wT.f.w l2 s010.00SW. F., m te—+rn
rR[moveadTeplaesekmufopmF N.Water o r E
/obis velNew Vie.seal.ad CdFOtiSealm a- 01
Backer UMW.a➢Copbg > o C•-
New KynaCmed0.01P Alan Copbgw/6• Job,Rak Mona to I'aepet d ce O
Bak Up Plate Cl O
N.IBPb Dimity Wood Fag Tapered Edge '=eA n
New Risible Fleshing New Cow 00/P Al.Clew nosed iv/�• Eria®gPmy.Gaping E 3 r∎
rbmg Slakles Steel Roofing Nos u 6'ne,to Sun O
both fide ofpwHm Note Ii Inmlek Ow tmdneide°libel.dram bowl ad vertical kiln. ai 0 J
Note 22:Pmridemnpgemmsiomad Fubegfmntamtuv A®bevstbBOliabb8. New Pd)wc0me5elmt- j V
N.IVUee QUnnkrlal 1110 1/ EusmigdPSbeathkg
p, ►/,Ioy i EaudoBCoppn Flasl®P °•N. �'rI New%'Ply wood Sbewbmg N.FWIv Mimed 0.060'Weubee Rnistat aeon w/Hans.Throbs.Hammed ,r`I N.PalywnAme W.and
III EPDM Mmibaw wlHamn see AmMna Lv'on. ` Bicker Rad ut
�1/ N.0.060'Fdy Adheed ` of ad NdcJm
N..Pit'Kyna Goad p ,f EYIIM YSapn lVaO Flashing N.CUI Ban. Nm SeWP+
Alura Piero Frain I• 1 14 N.lVeurfWOHSeilml FbenP°'P eN.y.'Plywmd Sheathkgfwvd �
�N.0.0w'K)gaCaul Alum New Metal Dtmtstap Aa..ii I'..g.Ia®ass /C j SiJdal4mpcto Newomer' E
N.OadO'Kyne Cmmd lkvugbwa➢OreAaw Sagla Pa fastend m Mk Now CUIlmo SOabv Anslumal]'o.<. S[gga Box mNw(iAq[r
Almon.Wag giggling wl 6' Condmrm/bead
nick Bad lip Plan N.fully Ad6aed Nwa'Poliimcymmwe Nn'0.060'FuByAdbnd `j /
0-6-.....1...- rNn'lap Ir 006PpD11 ............. EI'UMWa➢Flabmg
Nn foal O.U•Aba.(lcw IF I / Rratnu I MntOme huulaia f I L a
emdw/13'Sw,) Steal ..•111 N.Fully/Wised 0.060.
Rmhg Nab ea 6'ae C FPDM Melds. Nev r Ey New V side s er m➢N az
New Ralik Flashing 1/ODA „:?egi--.. �II Ily moans o/ IdrndSwm Soggn Paa� a
....�.;k'�"...x: fay. y U >
r �4/wwm
Nn@ghDmmy Wood Rice .Spxyw...m.:.L"xu I .16 e"[ i
Tapered Edge c. . �_
T7(ff►New Y14• �. .G 5
Seal.).wl I//////// —Existing Mail M4 t
weeps ul6'os. New Can lean Maio Bowl E�rng MmalOM ExistIng!7'gypn Intl g
Existing Wood Blocking / Ouwm5oN W HO €^
• Rnadmtio EPOMMmimaieeatmN I'pail N.sae Wood HlaekbSSnm[d to
deck u 6•ac. OE
clanginglinC.shall Magee disdain pipe diameter / 1 €m
N.Nwbubf m EaistkgMannyWell Nana H i m. vivo Stripping Ply.EVmd min.2'.0 field matins. 0t)e 9 Ta
Noel:Simidsmechani['a!tinsmitis,of field mcmbrme umymd by du Mad<ur. say m 61,
See NmnlaE Note l:Proidemcekaical temwtanm of field laminae u required by lheMauf meT.
all 19 Overflow Scupper Flashing Detail 14 Roof Drain Flashing Detail s•..T.aN IS Scupper Flashing Detail f,.ww,. '
h.T.f.,k i11�
S r
Y re® N6y<® Nr>1',0® 11,.14,® 1,1LT® sere® Mr4,® W•re® 1•x4,®
IVr.l'a'® rtir4,® t'`
•
Remove amdrryma SSJma an Hoping New We.
Ivies al New Slisme Sulam and Cw.QSam ,•/t •
BrckerRad opicel at ell Coping % xp
Jame,Rake Marta to I'&ph t
co
Existing Paapet[opmg ../...x-----...x .. m
Sow Nrw Pdymnhme S<Jm +X 11{'x IA'Aluminum Me$•
New Alm.TmFlmlonv r; / /I / _ xiZ
New Alum.Temmunm au sawed / o t
a/Haa®cSn Agchms air o.c. ` Nrwdealmt 1• .y
Nor X.Plywood Shca0mgaetted I
Mawr. o.c.lmmmn d`j / I/ Nn'l6 ox Crcppa Conductor Hod m S
AmAnaat l3'o.c ` j I. �N Up. LlutMr— �a�
New 0.060"Fully Adhvud
FAUnI Wall Robing .{� { both sides
New FWh A&md0060'
EPDM Membamc New N'wirk x{'WI 10 or New16 mr.Capper Picm Frame 1' New 16 ox.Copper Dunn e..
Ncw'Y'pa fmMTa Nv Lap Cmmerlroughwill Soppa Boa cube,uaim BaWt Dm
Sdml ;_ zdtont Eaiamgl'x3•
�hmm=n Throughwall Scupper Box Detail , Cypn Downspout ■ ■ ( ---,.p.;.\tx p./ �' typal Blivd Rivmm'e �j ° faiatmg E'tl'Cnppa lMwnryoM W / - EaitvnemmvJ COppafiwa - r � °ONAL" •
Edisamg'Sr x 31¢Coma owls Tube
Fuamw Meal Dcrk 3' Jr 3 - -
Nv2vfi lVmd Blocking A. E"u®&NI'hen STivgleRmFgyza® 1 f S' r ELEVATION SIDE VIEW
Existing nlmamywan
` rn
Conductor Head Detail 0
Note 1:ProvidemabmisJ armman°nof field mcmbnn<urtgwaany the Almuf a. :0
II m .0
16 Overflow Scupper Flashing Detail NewKymrCOatetl 0.D10. Coping E t..)•2
I P ram aury35ealant, — `
New 6•vdde Kytar Coated each side M)tlnt E cu C 5:,4111111111 Alum.Back Up Hate / O ce co
t
•
O_
• a� /// �tIP I z CU u-
New Alum C,qm:
IWV- D.tO O
dkI U
N e w Now WmaC wQ f\\ II1I :1000 .n ,
Dmmpoui al rapper Dm.wort tn sealant -a
Eviamg Masonry Wall Bmcletnt'va of Two I�
Coypu powwynw Baxkm Steed I \ I i O
from r wide 16 ox Coma IX Faldd, \\ / CJ
provide Yr stand off , \ / r v
New Ky.Costal O.OW Alma New0.050'mM.
Edec kcal w/6'Back Up Mars New Polyffahme Sok.,c p A q/.I Atl°m•n-"'
New fl flexible Flashing °".t.
New TomMairy W°°' ■` \\\� 1 ' Typical Coping Lap Detail
Fla Tgrcrd Edge
fJa�B Ye Sheathing Nrn0.UM Ahm.Regln Momtd C°mumlatAmg, allow 11cm
ma Hack to 111 m wavnGmt0.lon,lmaless mwmnew'14g1n , Mimithaoo•cop g New erevac SenvnveS aumd wl W,'Iwe Samlm Nn�'Plywood5hmlmig hchivd ikeaawayme aogeo Sall Roofing Nalx a 6'o.S New Almn Tmnmation Bar wcmcd w/Hamm,Sa rPlY Hoed roll Nmlme flmge n( }p•By.ho0,aaka efPUapet NewOUW'FunYAdoered FPpAI Avsh°ndll'os. ` Emmg MamuytV. \ Ner Almon Edge Meal end wrier des P WJf Flasla / Coves Plate ontoA am ALmm.
New Fun Adhad0W0'EPOM New FuBYAdkvd 0060'EPDA7Membrme �I I Nn POlymnhaNEm1,3 \ ,,,-.w7 C°PMS a .
1 I 1/I� „/ Mnnbmc II,J\ Nw NaafutoQSaL t .. New Peswe&maive Sm+PPmR
�� 1L New ltl'x1014'et•Gmaete 5➢Issb Black— �I �r /. NewO WO'Funy \\ — T\_ i
/ New P.TPl-•zd Adbmsd EPUM \ PIY C Plne a
Nov New Wata Cl,LnnSeilmt ► New FROMW Pad % Sbea3mp snood u/ Pain N'ill Flvhmg � 1 ,`\ram'ova C)
tVmMResipmu Baba .' a d n ; Andtma Il'oc�a5m New 00a0"Kyna Coved \\\\l� I l __ _ tti '
�"i ` am(bun.actin WUa I N.w Kyaw \ _•I♦�� ticw 0.060"Fully AdAacd GwoQSalam .• Cead00da' ''.22.....Q.............:.., 6
New 0080°K Cold a a ,� EMI WO He \\\� A Almon Ede — _ Qpi-{
AImu Wall Flashing w/6” �I_�� � Y tl New Hamer Sc AmLmr \\\\ I McW N
wide Batupemta I iouivviviiiii L ;/ Mrz^°x '. ( \•� -
Newq•eah;smmame P s
Im..,2layas ` \ Nm 6•wade Kyna w
I Cover D'040'Num `y • e
mpExisting nlaal Uak ExitmRtVmoJ Blaslovg N_arhamfqd bytbc Maaeanamr. Typical Vertical Wall Termination Detail I: a m n
EJadngMml Ma Typical Coping to Edge Metal Lap Detail
f'i^
fl Parapet Wall Flashing Detail 0 wm r wN Wall Flashing Detail R
tar ® I,aa rw® a/ax4a�® gw-ad® 0 10' ® tm..o.® a,eIa® 1,•-®s tNr.aa® >.r.a® ,UUrl'`
•
•
•
•
. T
Ln
an
t
rZoly Omni onst. a
lVatm OUaRSdm Existing Penman
New Wma o_
Nm'SUvdm SmlpnwbmJ k3• New Nansbrak Cmmt CuooRSwlm, 1Ja .-v
Nm'Pomblc SNm ����.JJ1 p E •�•
New Wmatight Stinks,SteilRa Cale
a Z
Aypmil/,'<kam<e al amen overlapping Prnauuw road In
Newland-off Sam New 36 garye Stmlm Seal Pmmtivm Nov Nyma Comd003^Alm.
Pokn w/wda<d teau t'min clmmu CowtmAUloa
Nm9'wide EPuM
from p.m%4'mm.height sad l'mil
Flmlring Almvbrm ):'� y.,g v 11mFe New Up Sedans • 6t-
rNcwFuaYAdbmd bik -it-:-.e• —New Rill
0060-EPIIAI No.Fully Adhered 0.060' f.b
Almkmu EPDM Membrane
%/ Kai it 4rzdi woLmnalarm �New Rata Rod �1 `Fist',Mal Ikti �� '$A� �c�'
—New 4'Polyisoryawae W.-P.7.10 Mad Nakn Existing MeulD %70n1.0
InsuLrvm m.1114 Nei/
euulanmv.fmtrn m dak
w/IWO screws at
Ir o.c.suggacatm.
IT
Nac C
Nov RN Club m be pmiddby Isle of11501C 4.New curb mbeiradaand 0uMJby Canna=Contra=to 'p C
coo*.We ieseRatim atilt N W'
Rw/isle of fn., _ OJ
ePitch Pocket Detail O Curb Flashing Detail m y u
19 mb.w„o,me 2U WWI.. CCi r 2.7'En
E cu 5
oE_,-.--.
•
z"3-‘412 o'
ay
E 3•-.
J
U
E
z
17,5
I
•
C 1
a)
0
Z5
,
< IF IS tl].d® Wee® L,n,tl /1.IP® Vnm® Vm•a'® 1/nlV® VV., ® IVY.tm'® ® 1`
W
•
Local Roan Global Reach
ISLE OF WIGHT
COUNTY,VIRGINIA
December 18,2015
IFB#16-4110-01
INVITATION FOR BID
ADDENDUM #1
Community Development Building Low Slope Roof Replacement
Sealed bids subject to the conditions and instructions contained herein,will be received at the office of the Purchasing Agent listed below,until the
time and date shown below(local prevailing time),for furnishing the items or services described herein.
•
The location for the optional prebid meeting is amended to read as follows:
Optional Prebid Meeting: 10:00 AM, January 12, 2016 at the site: 17140 Monument Circle, Isle
Wight County,VA 23397
Bid Due: 3:00 PM., February 2, 2016
Contract Officer:
Michael Coburn,Sr.,Purchasing Agent,Michael.coburnAisleofwightus.net
**SECTION "A" AND ONE ELECTRONIC CD COPY IS REQUESTED AT SUBMITTAL**
In compliance with this invitation for bids,and subject to all the conditions thereof,the undersigned offers,if this bid is accepted within ninety(90)
calendar days from the date of the opening,to furnish any or all of the items and/or services upon which prices are quoted,at the price set opposite
each item,to be delivered at the time and place specified herein. The undersigned certifies he has read,understands, and agrees to all terms,
conditions,and requirements of this bid,and is authorized to contract on behalf of firm named below.
Company
Name:
Address:
City/State/
Zip:
Telephone: FAX No.:
E-mail:
Print Name: Title:
Signature: Date:
•
Local Roots,Global Reach
ISLE OF WIGHT
COUNTY,VIRGINIA
January 26,2016
IFB# 16-4110-01
INVITATION FOR BID
ADDENDUM #2
Community Development Building Low Slope Roof Replacement
Sealed bids subject to the conditions and instructions contained herein,will be received at the office of the Purchasing Agent listed below,until the
time and date shown below(local prevailing time),for furnishing the items or services described herein.
Please change the paragraph on page 5 to read as follows:
LIQUIDATED DAMAGES:
If said work is not completed within the time stated in the Notice to Proceed,the Contractor shall be liable
and hereby agrees to pay to the Owner as liquidated damages, and not as a penalty, the amount of one
hundred dollars ($100.00)per calendar day for each and every part of a day thereafter that said work
remains substantially incomplete. The County reserves the right, at its sole discretion,to deduct liquidated
damages from any outstanding amount due the Contractor.
Also: Replace: Section 01100 - Summary; Paragraph 1.3-A-5 with the following " Remove the existing asphalt •
shingles from the steep slope roof adjacent to Roof Section Al as necessary to remove and replace the deteriorated
tongue and groove deck boards 12 inches up from the roof eave. Provide new replacement 3/4"plywood to match the
thickness of the existing tongue and groove deck boards. Provide new self-adhered underlayment.
Bid Due: 3:00 PM., February 2, 2016
Contract Officer:
Michael Coburn,Sr.,Purchasing Agent,Michael.coburn(aisleofwightus.net
Company
Name:
Address:
City/State/
Zip:
Telephone: FAX No.:
E-mail:
Print Name: Title:
Signature: Date:
oriP
Local Roots,Global Reach
ISLE OF WIGHT
COUNTY.,VIRGINIA
February 2,2016
IFB# 16-4110-01
INVITATION FOR BID
ADDENDUM #3
Community Development Building Low Slope Roof Replacement
Sealed bids subject to the conditions and instructions contained herein,will be received at the office of the Purchasing Agent listed below,until the
time and date shown below(local prevailing time),for furnishing the items or services described herein.
The Performance Bond in Section B, is changed to read as attached:
Bid Due: 3:00 PM., February 2, 2016
Contract Officer:
Michael Coburn,Sr.,Purchasing Agent,Michael.coburuaisleofwightus.net
Company
Name:
Address:
City/State/
Zip:
Telephone: FAX No.:
E-mail:
Print Name: Title:
Signature: Date:
PERFORMANCE BOND
(CONTRACT DOCUMENT TO BE COMPLETED AT TIME OF AWARD)
Bond No.
Amount: $
KNOW ALL PERSONS BY THESE PRESENTS,that
of ,hereinafter called the Contractor
and a corporation duly organized and existing under and by virtue of the laws of the
State of ,hereinafter called the Surety,and authorized to transact business within the
Commonwealth of Virginia as the Surety,are held and firmly bound unto Isle of Wight County,Virginia as Owner,
in the sum of dollars($ ),lawful money of the United
States of America, for payment of which,well and truly be made to the Owner,the Contractor and the Surety bind
themselves and each of their heirs, executors,administrators,successors,and assigns,jointly and severally,firmly
by these presents as follows:
THE CONDITION OF THE ABOVE OBLIGATION IS SUCH THAT:
WHEREAS, the Contractor has executed and entered into a certain Agreement, hereto attached,with the
Owner dated ,2016, for roof replacement as described in the bid titled Community
Development Building Low Slope Roof Replacement,IFB# 16-4110-01.
NOW THEREFORE, if the Contractor, and its successors and assigns, shall at all times duly,promptly,
and faithfully perform the Work and any alteration in or addition to the obligations of the Contractor
arising there under, including the matter of infringement, if any, of patents or other proprietary rights, and
shall assure all guarantees against defective workmanship and materials, including the first two years of
the guarantee period following final completion by the Contractor and final acceptance by the Owner and
comply with all the covenants therein contained in the Specifications, Drawings, and other Contract
Documents required to be performed by the Contractor, in the manner and within the times provided in
the Agreement, and shall fully indemnify and save harmless the Owner from all costs and damage which
it may suffer by reason or failure to do so, and shall fully reimburse and repay it all outlay and expenses
which it may incur in making good any default,and reasonable counsel fees incurred in the prosecution of
or defense of any action arising out of or in connection with any such default, then this obligation shall be
void; otherwise to remain in full force and effect.
PROVIDED, HOWEVER,that the Surety,for value received, for itself and its successors and assigns,
hereby stipulates and agrees that no change, extension of time, alteration, or addition to the terms of the
Contract Documents or to the Work to be performed there under, or payment there under before the time
required therein, or waiver of any provision thereof, or assignment, subletting or transfer thereof or any
part thereof, shall in any way affect its obligation on this Bond, and it does hereby waive notice of any
such change, extension of time, alteration, addition to the terms of the Contract Documents or any such
payment, waiver, assignment, subcontract or transfer.
PROVIDED,FURTHER,that no final settlement between the Owner and the Contractor shall abridge the
right of any beneficiary hereunder,whose claim may be unsatisfied.
Whenever Contractor shall be declared by Owner to be in default under the Contract,the Owner having
performed Owner's obligations there under,the Owner shall have the right, at its option, to require the
Surety to promptly proceed to remedy the default within 30 days of notice by proceeding or procuring
others to proceed with completing the Agreement with its terms and conditions; and all reserves, deferred
payments, and other funds provided by the Agreement to be paid to Contractor shall be paid to Surety at
the same times and under the same conditions as by the terms of that Agreement such fund would have
been paid to Contractor had the Agreement been performed by Contractor; and Surety shall be entitled to
such funds in preference to any assignee of Principal of any adverse claimant.Notwithstanding the above,
the Owner shall have the right,with the approval of the Surety which shall not be unreasonably withheld,
to take over and assume completion of the Agreement and be promptly paid in cash by the Surety for the
cost of such completion less the balance of the Contract price.
It is hereby expressly further understood and agreed that this Bond is also given and made against
defective material and workmanship in the said work covered by the said Contract,provided, however,
that no suit, action, or proceeding,by reason of any defect whatever, shall be brought upon this Bond after
two (2)years following the date of final acceptance of the completed project by the Owner.
IN WITNESS WHEREOF, all above parties bounded together have executed this instrument this
day of , 2016,the name and corporate seal of each corporate party being hereto affixed
and those presents duly signed by its undersigned representative,pursuant to authority of its governing
body.
CONTRACTOR
By: (Seal)
Name:
Title:
Attest
SURETY
By: (Seal)
Attest
APPROVED AS TO FORM: ,2016
Mark Popovich, County Attorney
NOTE: Date of Bond shall not be prior to the date of the Agreement. If the Contractor is a partnership,
all partners shall execute the Bond.
IMPORTANT: The Surety named on this Bond shall be one who is licensed to conduct business in the
Commonwealth of Virginia, and named in the current list of Companies Holding Certificates of Authority
as Acceptable Sureties on Federal Bonds and as Acceptable Reinsuring Companies, as published in
Circular 570 (amended)by the Audit Staff Bureau of Accounts,U.S. Treasury Department. All Bonds
signed by an agent shall be accompanied by a certified copy of the authority to act for the Surety at the
time of signing of this Bond.
Community Development Building Roof Replacement
IFB#16-4110-01
February 2, 2016 3:00 PM
TST Roofing Block Roofing Old Dominion Shaddeau Roofing Roof Systems Air Tech Solutions
Bidders Roofing
$116,980. $79,533.00 $97,770.00 $74,025.00 $98,700.00 $98,000.00
Lump Sum
Custom Roofing Roof Engineering Commercial Bofam J.D. Miles&Sons Roof Services
Bidders T/A J. King Roofing Contractors
Deshazzo Group
$86,550.00 $71,942.00 $ 181,900.00 $89,500.00 $ 67,700.00 $133,950.00
Lump Sum
try
ISLE OF WIGHT
COUNTY VIRGINIA
February 4, 2016
Mr. Ray A. Coykendall, Vice President
J.D. Miles &Sons, Inc.
210 B Street, P.O. Box 5008
Chesapeake, VA 23324
Dear Mr. Coykendall:
This shall serve as Notice of Intent to award the Community Development Building Low Slope Roof
Replacement, IFB#16-4110-01, project to your firm in response to your bid submittal of February
2, 2016 in the amount of$67,700.
Section B, of the IFB contains the form that you must fill out and return. The addendum #3 has
a replacement Performance Bond that should replace the original. Please return the bonds,
insurance, and agreement so we can move this project forward. Also, to receive faster
payments you have agreed to take payments via the County's Purchasing Card. To allow this to
work through our accounts payable division, you must register at:
www.bankofamerica.com/epayablesvendors
Once you are registered and the required documents are returned and approved, we will
schedule a preconstruction meeting, after which time we will likely issue a Notice to Proceed.
From that time you will be expected to commence work within ten days and finish no later than
seventy (70) calendars days.
Should you have further questions or need assistance in any manner,the County will be
pleased to speak with you.
Sincerely yours,
Michael Coburn
Purchasing Agent
•