12/16/2015 - Change Order #7 Benn's Church Intersection Improvement Project I..
ROUTING SLIP it
'F'
From: Jamie Oliver, Transportation Projects Coordinator
Subject: Change Order #6 and #7 - Benn's Church Intersection Improvement Project (UPC
98244)
Date: 12/16/2015
Attached for execution are Change Orders #6 ($28,111.16) and #7 ($46,924.50) for a total of
$75,035.66. Funding is available in the project expenditure account (see attached for details).
Below depicts the Change Orders submitted and approved for this contract:
Change Order#1: $ 21,175.00 (County approved 9/17/2015)
Change Order#2: $ 10,107.20 (County approved 9/17/2015)
Change Order#3: $ 19,440.00 (County approved 9/17/2015)
Change Order#4: $ 11,000.00 (County approved 10/19/2015)
Change Order#5 $ 15,925.38 (County approved 11/18/2015)
Change Order#6: $ 28,111.16 (current request)
Change Order#7: $ 46,924.50 (current request)
Total Overruns: $ 152,683.24
Please Sign &Return to Jamie Oliver, Public Works Department
Name Approval Initial Date
Jamie Oliver, Division Head Approved as to Content ' '----/-7)0 /Vilidgr
Michael Terry,Director of B&F Verification of Funds Val,_ D--b) 1 s—
Michael Coburn,Purchasing Agent Approved as to Procurement
TM 12-)ZA\1',
Mark Popovich, County Attorney Approved as to Form ,� / /A-7g.
Anne Seward,County Administrator Execution (AI il)41 I
N/A,Clerk Attest iiii;› ,
Certification f Funds:
I'(Department Head Signature ) hereby certify that funds are
available in the project expenditure acco' t(31431044-580400).
Dire for of Bu getd Fina
Howard Brothers Contractor, Inc. Change Order
P.O.Box 96
� 1 dz. Providence Forge VA 23140 Order#: 7
804-966-2762
Order Date: 12/10/2015
License: 2701 039212A
To: County of Isle of Wight Project: 1063
P. O. Box 80 #15-4110-21 Benns Church
Isle of Wight VA 23397 UPC#98244
VDOT#001 0-046-R 10,C501
The contractor agrees to perform and the owner agrees to Plans Attached ❑
pay for the following changes to this contract.
Ordered By: 1 Samuel Howard Customer Order: Specifications Attached ❑
Description of Work Amount
#57 Stone/Ton 23,686.00
VDOT Item#27552 Spec#308
CO is Based on Approximately 325 Tons @$72.88 Per Ton (Unit Price to be used for Overruns)
#3 Stone/Ton 18,063.50
VDOT Item#10250 Spec#308
CO is Based on Approximately 325 Tons @$55.58 Per Ton (Unit Price to be used for Overruns)
UD-4/LF 5,175.00
VDOT Item#00588 Spec#501
CO is Based on Approximately 300LF @$17.25 Per LF (Unit Price to be used for Overruns)
Notes
Change Order per proposal submitted on 11/10/2015 for the purchase and installation of approx..
-325 tons of#57 stone aggregate as a drainage/stabilization course required due to an unsuitable pipe
trench foundation
-325 tons of#3 stone aggregate as a subgrade stabilization course.
-300 LF of VDOT std. UD-4
As noted on Each Item Totals are calculated on Estimated Qtys. shown. This is to add pay items to
Negative changes will lower the overall contract
price requiring no additional payment by owner. Requested Amount of Change 46,924.50
The original Contract Sum was 4,225,263.55
Net change by previous Change Orders 77,647.58
The Contract Sum prior to this Change Order 4,302,911.13
The Contract Sum will be changed by this Change Order 46,924.50
The new Contract Sum including this Change Order will be 4,349,835.63
The Contract Ti _ will be changed by 10 Days
Owner _ Date: I � I4,
12/10/2015
Contractor: ■ ay,f) Date:
Change Order Order: 7
Continued... Date: 12/10/2015
Description of Work Amount
contract with a unit price as given here in.
Page 2 of 2