11/20/2015 - Nike Park Trail (UPC 91219) Amendment No. 4 ROUTING SLIP
From: Jamie Oliver, Transportation Projects Mana
Subject: Nike Park Trail (UPC 91219)–Amendment No. 4
Date: 11/20/2015
The purpose of the attached amendment is to cover additional expenses ($60,394)which have developed in
the design process due to expiration of environmental permitting because of advertisement delays and
extensive comment responses due to citizen inquiries. Attached is a breakdown of general overages.
Current Contract: 898,853.00
Amendment: 60,394.00
Total 959,247.00
Please Sign & Return Executed Amendment to Janie Oliver, General Services
Name Approval Initial Date
Tony Wilson, Department Head Approved as to Content C`4� " `,-05-/'�
Michael Terry, Director of Budget &Finance Funds Available 'I \\ i)-6) I is—
Michael Coburn, Purchasing Agent Approved as to Procurement A: i 13) [(K
N/A, Risk Coordinator Certification of Insurance
Mark Popovich, County Attorney Approved as to Form
ii / 3 +I-
Anne Seward, County Administrator Execution It 1113011b
Nip-
Carey Mills-Storm, Clerk Attest iti 6 4SA
Certification of Funds:
r
1 I (Dept. Head Si gnat e Sj� ) here by certify that funds are available in the
project expenditure account(31711014-531700).
A Ail■ls.
Direc .r of Budet . A Financ
I
AMENDMENT NUMBER 04 TO THE AGREEMENT BETWEEN ISLE OF
WIGHT COUNTY AND KIMLEY-HORN AND ASSOCIATES, INC.
AMENDMENT NUMBER 04 DATED September 23, 2015 to the agreement
between Isle of Wight County, ("Client") and Kimley-Horn and Associates, Inc.,
("Consultant") dated March 24, 2011 ("the Agreement") concerning Smithfield to Nike
Park Multi-Use Path (the "Project").
The Consultant has entered into the Agreement with Client for the furnishing of
professional services, and the parties now desire to amend the Agreement.
Therefore, it is mutually agreed that the Agreement is amended to include
Additional Services to be performed by Consultant and provisions for additional
compensation by the Client to the Consultant, all as set forth herein. The parties ratify
the terms and conditions of the Agreement not inconsistent with this Amendment, all of
which are incorporated by reference.
Consultant shall perform the following Additional Services, and described in more detail
on the attached Exhibit A:
Environmental and engineering support during the property acquisition
phase. Services were requested to facilitate property or environmental
permit acquisitions and were unforeseen in the original scope
Consultant shall perform the services set forth above and the Client shall pay Consultant
the following additional compensation. Compensation will be paid on a lump sum basis,
derived using manhours and billing rates, according to the approved pre-award audit by
VDOT.
Environmental and Engineering Support during the Property Acquisition
Phase - S60,394 lump sum
CLIENT: CONSULTANT:
Isle of Wight County, Virginia Kimley-Horn and Associates, Inc.
.....— WeJ2A-Prt,e.rYazcZ
By: _ _ By:
Title: CMVtTL AhI'lwl6(1,D_DR Title: Vice President
Date: //---, e)/,S Date: September 23, 2015
Approved to form:
,d<4,GC....■
ark C.Popovich
County Attorney
AMENDMENT NO. 4—EXHIBIT A
Additional Services (through September 2015)
TASK 38 - Additional Survey ($1,985 lump sum)
• Property stakeout for Bristow, Parcel 012
• Property stakeout for Moore, Parcel 016 & Chouinard, Parcel 101
TASK 39 - Bridge Graphics and Justification .($3,887 lump sum)
• Develop bridge graphic for Leah Dempsey to promote project
• Memo explaining design criteria and cost justification
TASK 40 - Civil Design and Property Owner Coordination ($29,637 lump sum)
• Edwards Property- Analysis of timber stand and fencing costs; on-site meeting
(no show)
• Saunders property- (3) mtgs. on site; exhibits for alternative align.; revise final
plans (June 2013-2014; July 2015)
• Smithfield Church of Christ -parking (March- April 2015)
• Smithfield Villas -prior rights memo; design alternatives; VDOT coord.
• Moore Property-meet on site; layout and estimate for replanting; landscape
screening templates (April-May 2015)
• Wellington HOA-respond to various letters, emails, phone calls about drainage
and SWM; etc. (April-May 2015)
• Columbia Gas -parking discussions; layout for new entrance off of Moore
property (June-Aug 2015)
• Coord. with Town/Town Surveyor on Properties with Prior Rights
• List of Frequently asked questions
• Trail Signing Options
• Trail Maintenance Plan
• Coordination with VDOT for safety money
• Continued utility relocation coordination(DVP and Verizon)
• Final resolution assistance for Edwards, Columbia Gas, and Saunders
• One additional plan submittal to VDOT and respond to comments
TASK 41 -Environmental Support and Coordination ($24,885 lump sum)
• Section 6(f) Coordination with DCR, VDOT & County; Research mapping and
comprehensive park plans (2013)
• Additional Section 106 coordination with VDHR(June 2013)
• Additional Section 4(f) Coordination(2013)
• Coast Guard-Application& Figures (January 2015)
• T&E Update (Oct. 2014)
• VMRC - respond to Nov. 2014 letter;prepare, attend and follow-up to Dec. 2014
Hearing
• Revised JPA drawings in response to VMRC Request (Dec. 2014)
• T&E Update,NOAA Coordination& Assessment(Feb-March 2015)
• Planning Commission Meeting (May 26, 2015)
• T&E Update& Coordination on NLEB (August 2015)
• WQIA Supplemental Memo -requested via Edwards property(August 2015)
• Final coordination of Threatened &Endangered species