Loading...
11/13/2015 - Change order #5-Benn's Church Intersection Improvement ROUTING SLIP From: Jamie Oliver, Transportation Projects Manager Subject: Change Order#5 -Benn's Church Intersection Improvement Project (UPC 98244) Date: 11/13/2015 VDOT is requiring the County to install two (2) temporary traffic signals at the intersection of Route 10 and Route 258 while the project is under construction. Attached for execution is a Change Order in the amount of $15,925.38 to furnish, install, maintain and remove the temporary traffic signals. Below depicts the Change Orders submitted and approved for this contract: Change Order#1: $ 21,175.00 (County approved 9/17/2015) Change Order#2: $ 10,107.20 (County approved 9/17/2015) Change Order#3: $ 19,440.00 (County approved 9/17/2015) Change Order#4: $ 11,000.00 (County approved 10/19/2015) Change Order#5 $ 15,925.38 (current request) Total Overruns: $ 77,647.58 Funding is available in the project expenditure account. Please Sign &Return to Jamie Oliver, General Services Name Approval Initiiaal Date Jamie Oliver,Division Head Approved as to Content 446— Michael Terry,Director of B&F Verification of Funds A b j Michael Coburn,Purchasing Agent Approved as to Procurement A,. 1 1 6 D ( Mark Popovich, County Attorney Approved as to Form 7,17 Anne Seward, County Administrator Execution • 1/ 1 g l I N/A, Clerk Attest u • 11 If y J5' erY ' ation of Funds: I (Division Head Signature( / �ereby certify that funds are available in the project expenditure a .10't(31431044-580400). L Directo of Budge a c Fina r'ce Howard Brothers Contractor, Inc. Change Order P.O.Box 96 — Providence Forge VA 23140 Order#: 5 804-966-2762 Order Date: 11/06/2015 License: 2701 039212A To: County of Isle of Wight Project: 1063 P. O. Box 80 #15-4110-21 Benns Church Isle of Wight VA 23397 UPC#98244 VDOT#0010-046-R10,C501 The contractor agrees to perform and the owner agrees to Plans Attached n pay for the following changes to this contract. Ordered By: 1 Samuel Howard Customer Order: Specifications Attached Description of Work Amount Temp.Video Detection Cameras and Elect Disconnect 15,925.38 Dagan Electric Company (Subcontractor) Notes Change Order#5 to furnish, install, maintain and remove two Temporary Vehicle Video Detection Cameras and Camera Control Equipment at the intersection of Route 10 and Route 258.This proposal also includes furnishing and installing a permanent means of electrical disconnection for the new traffic signal controller in the median of the same intersection.The delivery time for the material is 45 days after approval and will require approximate 7 days to install. (see attached supporting documents) Total$15,925.38 •pp to form ark G Popovich County Attorney Negative changes will lower the overall contract price requiring no additional payment by owner. Requested Amount of Change 15,925.38 The original Contract Sum was 4,225,263.55 Net change by previous Change Orders 61,722.20 The Contract Sum prior to this Change Order 4,286,985.75 The Contract Sum will be changed by this Change Order 15,925.38 The new Contract Sum including this Change Order will be 4,302,911.13 The Contract Time will be changed by - - 0 Days Owner: ��___ `-- Date: ////g/j, fib Contractor: n rytuil ' e" ' ' Date: 11/06/2015 sox • mZ Proposal 11/69/15 Howard Brothers Contractor, Inc. Proposal Land; with Notes Job# 1063 to 1063 Item/Cost Code Description Material Labor Equipment Subcontract Other Amount 1063#15-4110-21 Benns Church 5050.000 Subcontractor Dagan Electric Company 7,119.29 5,235.08 1,573.25 550.00 14,477.62 5050.000 Subcontractor Prime 10% Mark up 1,447.76 1,447.76 Grand Totals: 7,119.29 5,235.08 1,573.25 1,997.76 15,925.38 Notes: HBCI price proposal to furnish, install, maintain and remove two Temporary Vehicle Video Detection Cameras and Camera Control Equipment at the intersection of Route 10 and Route 258.This proposal also includes furnishing and installing a permanent means of electrical disconnection for the new traffic signal controller in the median of the same intersection.The delivery time for the material is 45 days after approval and will require approximate 7 days to install. Dagan Electric Proposal$14,477.62 (see attached supporting documents) HBCI Prime Contractor Mark Up$1,447.76 Total$15,925.38 Report 6-1-11-31 11/09/2015 Darlene Page 1 of 1 03:40 PM HOWARD BROTHERS TEMP VIDEO DETECTION BENNS CHURCH BLVD ISLE OF WIGHT COUNTY COST BREAKDOWN MATL LABOR ITEM# DESCRIPTION: QTY: UM: EQUIP M/HR MOBILIZATION 1 LS . CAMERAS 2 EA 3,070.00 4.00 CONTROLLER AND EQUIPMENT 1 LS 2,472.00 8.00 CAMERA CABLE 500 LF 625.00 8.00 TECHNICIAN TO INSTALL CONTROLLER 1 LS 250.00 - PROGRAM CAMERA SYSTEM 1 LS 250.00 - AIM 1 LS - 8.00 MAINTAIN 1 LS - 40.00 REMOVE 1 LS - 16.00 BUCKET TRUCK 1 LS 1,400.00 - 1 LS - - ELECTRIC DISCONNECT IN MEDIAN 1 LS - - 100 AMP LOAD CENTER 1 EA 38.83 2.00 6"X 6"WOOD POST 1 EA 75.00 2.00 1-1/4"HUB 1 LS 12.01 0.15 GROUND BAR ASSY 1 LS 2.85 0.10 40 AMP BREAKER 1 LS 6.71 0.10 20 AMP BREAKER 2 EA 11.82 0.20 1-1/4"LB CONDULET 2 EA 30.18 0.40 CONDULET COVER 2 EA 6.36 - CONDULET GASKET 2 LS 5.38 - 1-1/4"X 8"GRS NIPPLE 2 EA 8.45 0.10 1-1/4"GROUND BUSHING 6 EA 15.58 0.20 1-1/4"LOCKNUT 6 EA 1.06 - NO.6 CONDUCTOR CABLE 240 LF 80.76 1.00 1-1/4"GRS CONDUIT 50 LF 128.61 12.00 1-1/4"GRS ELBOW 3 EA 17.84 0.30 1-1/4"GRS COMPRESSION COUPLING 6 EA 83.40 - 3/4"GROUND ROD 1 EA 22.89 1.00 3/4"GROUND ROD CLAMP 1 EA 1.58 - TRENCH 30 LF 165.00 8.00 1 LS - - 1 LS - 1 LS - - TOTALS $ 8,781.31 111.55 THIS QUOTATION IS BASED ON OUR INTERPRETATION OF THE PLANS THIS QUOTATION IS VALID FOR 30 DAYS TRAFFIC CONTROL IS NOT INCLUDED MATERIAL SALES TAX IS INCLUDED DAGAN ELECTRIC COMPANY,LLC IS A DMBE CERTIFIED SMALL BUSINESS#709874 DAGAN ELECTRIC COMPANY,LLC IS A VDOT PREQUALIFIED CONTRACTOR#D1080 0 RGA, LLC 1550 STANDING RIDGE DRIVE. POWHATAN,VA 23139 _ 804-794-1592 FAX 804-379-1016 A QUOTATION 715380-1 October 22, 2015 TO: DAVID WILLIAMS DAGAN ELECTRIC 757-689-4152 david@a,daganelectric.com RE: TEMPORARY FOR ONE TURN LANE RGA, LLC is pleased to provide the following quotation. Quotations are subject to acceptance within 45 days. RGA, LLC makes every effort to insure that the materials quoted are per appropriate plans and specifications; however, the Customer is solely responsible for determining final acceptability of materials for the intended use. DELIVERY: 30-45 days after receipt of order and approval of submitted data if required. FREIGHT: Standard freight Included ITEM DESCRIPTION QTY PRICE EA EXTENDED VCFLEXSM-PAK VERSICAM FLEX WIDE ANGLE COLOR 2 1,535.00 $3,070.00 CAMERA, MOUNTING BRACKET. ICC CARD 2)ICC INTERFACE COMMUNICATION 1 2,472.00 $2,472.00 EQUIP. CONTROLLER W/ POWER CABLE, F CABLE, MOUSE, VC SURGE, MATING CONNECTORS, ICC RACK, VCABLE 3 PAIR, 19 AWG, STRANDED CABLE TO 500 1.25 $625.00 CONNECT VERSICAM TO ICC UNIT (ORDER IN LINEAR FOOT) ASSISTANCE RGA TO ASSIST WITH INSTALL OF CAMERA 1 250.00 $250.00 EQUIPMENT IN CONTROLLER CABINET SET-UP RGA TO PROGRAM CAMERA AND CARD 1 250.00 $250.00 SETINGS Taxes added as applicable TOTAL $6,667.00 NOTES: RGA TO ASSIST WITH CAMERA INSTALL. WIRE NEEDS TO BE ADDED FOR INSTALL. Any sale resulting from this quotation shall be accepted on the following TERMS and CONDITIONS of SALE: 1- Before using, the customer shall determine the suitability of the materials for the intended use, including the gaining of all required approvals, and assumes all risk and liability in connection therewith. 2- RGA, LLC retains title to all materials until paid in full. Payment is due upon receipt of the material. Payments not received within 30 days shall be charged 1.5% (18%APR) per month until paid in full. All legal and collection fees incurred by RGA,LLC associated with such effort shall be paid by customer. 3- RGA, LLC shall not be held liable for any injury, or damages either direct or consequential arising out of the use, or the inability to use the materials provided by RGA, LLC. 4- No statement, terms, or recommendations not contained herein shall have any affect unless contained in an agreement signed by an officer of RGA, LLC. THANK YOU FOR CONTACTING RGA, LLC Stuart Swift sswift@ rg a-traffi c.co rn • Graybafl. 3808 PROGRESS ROAD,INDUSTRIAL PARK NORFOLK VA 23502-1909 Phone:757-857-1241 Fax: 757-855-2837 To: DAGAN ELECTRIC COMPANY Date: 10/22/2015 1452 TAYLOR FARM ROAD SUITE 107 VIRGINIA BEACH VA 23453-3147 Proj Name: BENNS CHURCH Attn: david williams GB Quote #: 223781822 Phone: 757-689-4152 Valid From: 10/22/2015 Fax: 757-689-8482 Valid To: 11/21/2015 Email: miles.haus @graybar.com Contact: MILES HAUS Email: miles.haus @graybar.com Proposal We Appreciate Your Request and Take Pleasure in Responding As Follows Item Quantity Supplier Catalog Nbr Description Price Unit Ext.Price 100 1 EA SQUARED CO. Q0612L100RB LOAD CENTER QO $38.83 1 $38.83 MLO 240V 100A 1PH 6SP GB Part#:88243006 UPC#:78590178559 Ship From: Stock NORFOLK, VA 200 1 EA SQUARE D CO. B125 HUB 1.25 INCHES $12.01 1 $12.01 RAINPROOF FOR RB DEVICES GB Part#:88239154 UPC#:78590145944 Ship From: Stock NORFOLK,VA 300 1 EA SQUARE D CO. PK7GTA LOAD CENTER $2.85 1 $2.85 EQUIPMENT GROUND BAR ASSY GB Part#:88242155 UPC#:78590102637 Ship From: Stock NORFOLK, VA 400 1 EA SQUARE D CO. Q0140 MINIATURE CIRCUIT $6.71 1 $6.71 BREAKER 120/240V 40A GB Part#:88242662 UPC#:78590140018 Ship From: Stock ZONE-RICHMOND,VA 500 2 EA SQUARED CO. Q0120 MINIATURE CIRCUIT $5.91 1 $11.82 BREAKER 120/240V 20A This equipment and associated installation charges may be financed for a low monthly payment through Graybar Financial Services(subject to credit approval). For more information call 1-800-241-7408 to speak with a leasing specialist. To learn more about Graybar,visit our website at www.graybar.com 24-Hour Emergency Phone#:1-800-GRAYBAR Subject to the standard terms and conditions set forth in this document. Unless otherwise noted,freight terms are F.O.B.shipping point prepaid and bill. Unless noted the estimated ship date will be determined at the time of order placement. Page 1 of 4 To: DAGAN ELECTRIC COMPANY Date: 10/22/2015 1452 TAYLOR FARM ROAD SUITE 107 Proj Name: BENNS CHURCH VIRGINIA BEACH VA 23453-3147 GB Quote #: 223781822 Attn: david williams Proposal We Appreciate Your Request and Take Pleasure in Responding As Follows GB Part#:88242626 UPC#:78590140010 Ship From: Stock NORFOLK, VA 600 2 EA CROUSE-HINDS LB47 1 1/4 LB FORM 7 $15.09 1 $30.18 THRD RIGID OUTLET BODY GB Part#:88073180 UPC#:78227451450 Ship From: Stock ZONE-RICHMOND,VA 700 2 EA CROUSE-HINDS 470 1 1/4 WDGNUT SHT $3.18 1 $6.36 STEEL FORM 7 CVR GB Part#:88067887 UPC#:78227400320 Ship From: Stock NORFOLK, VA . 800 2 EA CROUSE-HINDS GASK574 1 1/4 SOLID NEO $2.69 1 $5.38 FORM 7 GASK GB Part#:88072676 UPC#:78227443550 Ship From: Stock NORFOLK,VA 900 2 EA CONDUIT 1-1/4 X 8 GALVANIZED $422.65 100 $8.45 CONDUIT NIPPLE GB Part#:88273035 UPC#:78669200499 Ship From: Stock ZONE-CHARLOTTE,NC 1000 6 EA ARLINGTN IND 453 1-1/4 D/C INS COND $259.74 100 $15.58 BUSH • GB Part#:90080770 UPC#:01899700453 Ship From: Stock NORFOLK,VA 1100 6 EA ARLINGTN IND 404 1-1/4 STEEL $17.67 100 $1.06 LOCKNUT GB Part#:90095767 UPC#:01899700404 Ship From: Stock NORFOLK,VA 1200 240 EA WIRE THHN-6-STR-BLK- 19 STRAND 600V $336.51 1000 $80.76 CUT REEL 90DEG CU GB Part#:22061694 UPC#:98022061694 Ship From: Stock NORFOLK, VA This equipment and associated installation charges may be financed for a low monthly payment through Graybar Financial Services(subject to credit approval). For more information call 1-800-241-7408 to speak with a leasing specialist. To learn more about Graybar,visit our website at www.graybar.com 24-Hour Emergency Phone#:1-800-GRAYBAR Subject to the standard terms and conditions set forth in this document. Unless otherwise noted,freight terms are F.O.B.shipping point prepaid and bill. Unless noted the estimated ship date will be determined at the time of order placement. Page 2 of 4 • To: DAGAN ELECTRIC COMPANY Date: 10/22/2015 1452 TAYLOR FARM ROAD SUITE 107 Proj Name: BENNS CHURCH . VIRGINIA BEACH VA 23453-3147 GB Quote #: 223781822 Attn: david williams Proposal We Appreciate Your Request and Take Pleasure in Responding As Follows 1300 50 EA CONDUIT 1-1/4-GALV RIGID CONDUIT $257.21 100 $128.61 GB Part#:88272870 UPC#:98001000104 Ship From: Stock NORFOLK,VA 1400 3 EA CONDUIT 1-114-90D-GALV-ELL 90 DEG STD RAD $594.66 100 $17.84 RIGID ELBOW GB Part#:88273019 UPC#:78669200164 Ship From: Stock NORFOLK, VA 1500 6 EA CROUSE-HINDS CPR24 1 1/4 RGD CMP CPL $1,390.07 100 $83.40 GB Part#:88315105 UPC#:78456412224 Ship From: Stock ZONE-RICHMOND,VA 1600 1 EA ERICO PROD 613400 GR $22.89 1 $22.89 RODPTDCU- BONDNOM 3/4INX1 OFT1 OMIL GB Part#:94035119 UPC#:78285630617 Ship From: Stock NORFOLK,VA 1700 1 EA ERICO PROD CP34 GRD ROD $1.58 1 $1.58 CLAMPSIL BRZSTD DUTY1/21N-3/4 GB Part#:96078229 UPC#:78285630704 Ship From: Stock NORFOLK,VA Total in USD (Tax not included): $474.31 This equipment and associated installation charges may be financed for a low monthly payment through Graybar Financial Services(subject to credit approval). For more information call 1-800-241-7408 to speak with a leasing specialist. To learn more about Graybar,visit our website at www.graybar.com 24-Hour Emergency Phone#:1-800-GRAYBAR Subject to the standard terms and conditions set forth in this document. Unless otherwise noted,freight terms are F.O.B.shipping point prepaid and bill. Unless noted the estimated ship date will be determined at the time of order placement. Page 3 of 4 To: DAGAN ELECTRIC COMPANY Date: 10/22/2015 1452 TAYLOR FARM ROAD SUITE 107 Proj Name: BENNS CHURCH . VIRGINIA BEACH VA 23453-3147 GB Quote #: - 223781822 • Attn: david williams Proposal We Appreciate Your Request and Take Pleasure in Responding As Follows GRAYBAR TNOFSAE C TM ND ELECTRIC COMPANY, 1.ACCEPTANCE OF ORDER;TERMINATION-Acceptance of any order is subject to credit approval and acceptance of order by Graybar Electric Company,Inc./"Graybar")and,when applicable,Graybar's suppliers. If credit of the buyer of the goods("Buyer)becomes unsatisfactory to Graybar,Graybar reserves the right to terminate upon notice to Buyer and without liability to Graybar. 2.PRICES AND SHIPMENTS-Unless otherwise quoted,prices shall be those in effect at time of shipment,which shall be made F.O.B.shipping point,prepaid and bill. 3.RETURN OF GOODS-Credit may be allowed for goods returned with prior approval.A deduction may be made from credits issued to cover cost of handling. 4.TAXES-Prices shown do not include sales or other taxes imposed on the sale of goods.Taxes now or hereafter imposed upon sales or shipments will be added to the purchase price.Buyer agrees to reimburse Graybar for any such tax or provide Graybar with acceptable tax exemption certificate. 5.DELAY IN DELIVERY-Graybar is not to be accountable for delays in delivery occasioned by acts of God,failure of its suppliers to ship or deliver on time,or other circumstances beyond Graybar's reasonable control.Factory shipment or delivery dates are the best estimates of our suppliers,and in no case shall Graybar be liable for any consequential or special damages arising from any delay in shipment or delivery. 6.LIMITED WARRANTIES-Graybar warrants that all goods said are free of any security interest and will make available to Buyer all transferable warranties(mcludin without limitation warranties with respect to intellectual pnro a�tyy tnfrinege��ment)made to Graybar b the manufacturer of the goods.GRAYBAR MAKES NO OTHER EXPRESS OR IMPLIED WARRANTIES AbM SPECIFICALLY DISCLAIMS ALL IMPLIED WARRANTIES INCLUDING BUT NOT LIMTED TO THE IMPLIED WARRANTIES OF MERCHANTABILITY AND FITNESS FOR PURPOSE.UNLESS OTHERWISE AGREED IN WRITING BY AN CONTAINMENT REPRESENTATIVE OF A NUCLEAR FACILITtPORI(2 IN SOLD HEALTHCARE HEREUNDER PLICATION,WHERE THE GOODS HAVE POOTEENNTIALOFOWITH 1 PATISAFETY NTACT OR WHERE THE SIX(6) FOOT CLEARANCE FROM A PATIENT CANNOT B'E MAINTAINED AT ALL TIMES. 7.LIMITATION OF LIABILITY-Buyers remedies under this agreement are subject to any limitations contained in manufacturers terms and conditions to Graybar a copy of which will be furnished upon written m request.Furthermore Graybar s liability shall be limited to either repair or replaceent of the goods or refund of the purchase price,all at Graybaf s option,and IN NO CASE SHALL GRAYBAR BE LIABLE FOR INCIDENTAL,SPEOIAL,OR CONSEQUENTIAL DAMAGES.In addition,claims for shortages,other than loss in transit,must be made in writing not more than five(5)days after receipt of shipment. 8.WAIVER-The failure of Graybar to insist upon the performance of any of the terms or conditions of this agreement or to exercise any right hereunder shall not be deemed to be a waiver of such terms,conditions,or rights in the future,nor shall it be deemed to be a waiver of any other term,condition,or right under this agreement. 9.MODIFICATION OF TERMS AND CONDITIONS-These terms and conditions supersede all other communications,negotiations,and prior oral or written statements regarding the subject matter of these terms and conditions.No change modification rescission,discharge,abandonment,or waiver of these terms and conditions shall be binding upon Graybar unless made in writing and signed on its behalf by a duly authorized representative of Graybar.No conditions,usage of trade,course of dealing or performance understanding or agreement,purporting to modify,vary explain,or supplement these terms and conditions shall be binding unless hereafter made in writing and signed by the party to be bound.Any proposed modifications or additions terms arc�specifica ly rejected and deemed a material alteration hereof.If this document shall be deemed an acceptance of a prior offer by Buyer,such acceptance is expressly conditional upon Buyers assent to any additional or different terms set forth herein. 10.REELS-When Graybar ships returnable reels,a reel deposit may be included in the invoice.The Buyer should contact the nearest Graybar service location to return reels. 11.CERTIFICATION-Graybar hereby certifies that these goods were produced in compliance with all apicable requirements of Sections 6,7,and 12 of the Fair Labor Standards Act,as amended,and of regulations and orders of the United States Department of Labor issued under Section 14 thereof.This agreement is subject to Executive Order 11246,as amended,the Rehabilitation Act of 1973 as amended the Vietnam Veterans' Readjustment Assistance Act of 1974,as amended E.O.13496,29 CFR Part 471,Appendix A to Subpart A,and the corresponding regulations,to the extent required by law.41 OFR 60-1.4,60-741.5,and 60-250.5 are incorporated herein by reference,to the extent legally required. 12.FOREIGN CORRUPT PRACTICES ACT-Buyer shall comply with applicable laws and regulations relating to anti-corruption,including,without limitation,(1)the United States Foreign Corrupt Practices Act (FCPA)(15 U.S.C.§78dd-1 et.seq.)irrespective of the place of performance and(ii)laws and regulations implementing the Organization for Economic Cooperation and Development's Convention on Combating Bribery of Foreign Public Officials in International Business Transactions,the U.N.Convention Against Corruption,and the Inter-American Convention Against Corruption in Buyer's country or any country where performance of this agreement or delivery of goods will occur. 13.ASSIGNMENT-Buyer shall not assign its rights or delegate its duties hereunder or any interest herein without the prior written consent of Graybar,and any such assignment,without such consent,shall be void. 14.GENERAL PROVISIONS-All typographical or clerical errors made by Graybar in any quotation,acknowledgment or publication are subject to correction.This agreement shall be governed by the,laws of the State of Missouri applicable to contracts to be formed and fully performed within the State of Missouri without giving effect to the choice or conflicts of law provisions thereof.All suits arising from or concerning this agreement shall be filed in the Circuit Court of St.Louis County,Missouri,or the United States District Court for the Eastern District of Missouri,and no other place unless otherwise determined m Graybar's sole discretion.Buyer hereby irrevocably consents to the jurisdiction of such court or courts and agrees to appear in any such action upon written notice thereof. 15.PAYMENT TERMS-Payment terms shall be as stated on Graybar's invoice or as otherwise mutually agreed.As a condition of the sales agreement,a monthly service charge of the lesser of 1-1/2%or the maximum permitted by law may be added to all accounts not paid by net due date.Visa,MasterCard,American Express,and Discover credit cards are accepted at point of purchase only. 16.EXPORTING-Buyer acknowledges that this order and the performance thereof are subject to compliance with any and all applicable United States laws,regulations,or orders.Buyer agrees to comply with all such laws,regulations,and orders,including,if applicable,all requirements of the International Traffic in Arms Regulations and/or theEx ort Administration Act;as may be amended.Buyer further agrees that if the export laws are applicable,it will not disclose or re-export any,technical data received under this order to any countries for which the UnitectStatesgovemment requires res an export license or other supporting documentation at the time of export or transfer,unless Buyer has obtained prior written authorization from the United States Office of Export Control or other authority responsible for such matters. Signed: This equipment and associated installation charges may be financed for a low monthly payment through Graybar Financial Services(subject to credit approval). For more information call 1-800-241-7408 to speak with a leasing specialist. To learn more about Graybar,visit our website at www.graybar.com 24-Hour Emergency Phone#:1-800-GRAYBAR Subject to the standard terms and conditions set forth in this document. Unless otherwise noted,freight terms are F.O.B.shipping point prepaid and bill. Unless noted the estimated ship date will be determined at the time of order placement. Page 4 of 4 PROPOSAL/ESTIMATE FOR CONTRACT MODIFICATIOI' DATE: 23-Oct-15 CONTRACT TITLE: RT 10/258 INTERSECTION BENNS CHURCH BLVD CONTRACT NO.: 0010-046-R10,C501 ISLE OF WIGHT COUNTY CONTRACTOR: DAGAN ELECTRIC COMPANY DESCRIPTION: FURNISH,INSTALL,MAINTAIN AND REMOVE 2 EACH TEMPORARY VEHICLE VIDEO DETECTION CAMERAS AND EQUIPMENT CONTRACTOR'S WORK Revisions/Comments 1. Direct Material $6,716.31 2. Sales Tax on Materials 6% of line 1 6.00% $402.98 3. Direct Labor $2,342.551 111111111E111111M; 4. Insurance,Taxes,and Fringe Benefits 45% of line 3 45.00% $1,054.15;_________1 _•Ell 5. Rental Equipment $165.00111111111111111111111 6. Sales Tax on Rental Equipment 5% of line 5 5.00% $8.25 7. Equipment Ownership and Operating Expenses ���I1111111111 $1,400.00 8. SUBTOTAL(add lines 1 -7) $12,089.24 9. Field Overhead 0% of line 8 0.00% $0.00 10. SUBTOTAL(add lines 8&9) $12,089.24 Prime Remarks: SUB-CONTRACTOR'S WORN Revisions/Comments 11. Direct Materials $0.001 12. Sales Tax on Materials 0% of line 11 0.00% $0.00111111111111111111111 13. Direct Labor $500.00 14. Insurance,Taxes,and Fringe Benefits 0% of line 13 0.00% $0.00 111111111111111111Q 15. Rental Equipment $0.00 16. Sales Tax on Rental Equipment 0% of line 15 0.00% $0.00 11111111111111111111 17. Equipment Ownership and Operating Expenses $0.00 18. SUBTOTAL(add lines 11-17) $500.00 19. Field Overhead 0% of line 18 0.00% $0.001 20. SUBTOTAL(add lines 18&19) $500.00 21. Home Office Overhead 0% of line 20 0.00% $0.00 22. Profit 0% of line 20 0.00% $0.00 23. SUBTOTAL(add lines 20-22) $500.00 Sub-Contractor's Remarks: SUMMARY 24. Prime Contractor's Work(from line 10) $12,089.24 25. Sub-contractor's Work(from line 23) 11111111111111 $500.00 26. SUBTOTAL(add lines 24&25) , 27. Prime Overhead on Subcontractor 10% of line 25 10.00% $50.00 NM 28. Prime's Home Office Overhead 10% of line 24 10.00% $1,208.921 29. Prime's Profit 5% of line 26 5.00% $629.461 30. SUBTOTAL(add lines 26-29) 31. Prime Contractor's Bond Premium #### of line 30 0.00% $0.00: 32. TOTAL COST(add lines 30&31) $14,477.62 Estimated time extension and justification:60 days Contractor name:DAGAN ELECTRIC COMPANY Date: 23-Oct-15 Jamie Oliver From: Justin Reliford <jreliford @mbpce.com> Sent: Friday, November 06, 2015 10:58 AM To: Jamie Oliver Cc: John Machner;Joseph Modica; Matthew Martin Subject: FW: Camera From: Lewis,Sr.James K(VDOT) [mailto:James.Lewis @VDOT.Virginia.gov] Sent: Friday, November 06, 2015 9:24 AM To:Justin Reliford <jreliford @mbpce.com> Cc: Morrison,Todd 'Crash' (VDOT) <Todd.Morrison @VDOT.Virginia.gov>; Catlett,Tommy(VDOT) <Tommy.Catlett @vdot.virginia.gov>; Dixon, Charles (VDOT)<Charles.Dixon @VDOT.Virginia.gov> Subject: RE: Camera There will have to be some type of detection by the contractor for the left turn coming out of Smithfield Before the support Yp Y g pp junction boxes and wiring are removed. Also the same holds true for the right turn movement coming from Rt.17 going to Smithfield. From: Justin Reliford [mailto:jreliford @mbpce.comi Sent: Thursday, November 05, 2015 2:22 PM To: Lewis, Sr. James K (VDOT) Subject: Camera Can you send me an email requesting the temporary camera at the main intersection for documentation purposes?..We are about to put in for a change order and it's your recommendation.. 1 A